CAPM Equations Flashcards

1
Q

Three Point Estimation (aka Triangular distriubtion)

A

Estimate = (Optimistic + Most Likely + Pessimistic) / 3

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

PERT Estimation Formula

A

Estimate = (Optimistic + 4*Most Likely + Pessimistic ) / 6

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Schedule Variance (SV)

A

SV = EV - PV

SV = schedule variance
EV = earned value
PV = present value

SV < 0 = behind schedule
SV > 0 = ahead of schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Cost Variance (CV)

A

CV = EV - AC

CV = cost variance
EV = earned value
AC = actual value

CV < 0 = over budget
CV > 0 = withing budget

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Variance at Completion (VAC)

A

VAC = BAC - EAC

VAC = variance at completion
BAC = budget at completion
EAC = estimate at completion

VAC < 0 = over budget
VAC > 0 = within budget

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Schedule Performance Index (SPI)

A

SPI = EV/PV

SPI = schedule performance index
EV = earned value
PV = present value

SPI < 1 behind schedule
SPI > 1 = ahead of schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Cost Performance Index (CPI)

A

CPI = EV/AC

CPI = cost performance index
EV = earned value
AC = actual value

CPI < 1 = over budget
CPI > 1 = within budget

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Estimate at Completion (EAC)

A

EAC = BAC/CPI

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Estimate to Completion (ETC)

A

ETC = EAC - AC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Planned Value (PV)

A

PV = planned % complete * BAC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Earned Value (EV)

A

EV = actual % complete * BAC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Actual Cost (AC)

A

No equation
This should be the total amount already spent

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Budget at Completion (BAC)

A

No equation
This is the original budget

How well did you know this?
1
Not at all
2
3
4
5
Perfectly