Module 6 Definitions Flashcards

1
Q

Lag Time

A

Is the time between activities.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Lead Time

A

Is when activities are brought closer together or even overlap.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Soft Logic

A

Describes when activities are scheduled bases on preferences, guidelines, or external conditions. Allows the manager to make decisions based on conditions outside of the project, best practices, or guidelines.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Critical Path

A

Is always the path with the longest duration, but there are instances however, when the project’s expected end date is well beyond the duration of the scheduled work. In such cases, the critical path is considered the path with the least amount of float. But mainly the critical path has no float, has the longest duration, and does not necessarily have the most expensive activities.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

ADM (Arrow Diagramming Method)

A

Is also known as “activity on arrow”. This places activities on arrows.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

PDM (Precedence Diagramming Method)

A

Also know as “activity on nodes”. This places activities on nodes.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Analogous Estimates

A

Comparing estimates with another project. Remember this estimate approach by identifying the “analogy” between the two similar project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Parametric Estimates

A

These use a parameter, such as 5 hours per unit.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

PERT Estimating

A

Uses an average of the optimistic, most likely, and pessimistic time estimates for each activity.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Commercial Duration Estimating

A

Use databases the are used to confirm or base time estimates upon.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Parkinson’s Law

A

States that work will expand to fulfill the time allotted to it. Bloated tasks will take all of the time allotted. Management reserve should be used instead.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Law of Diminishing Returns

A

Describes the relationship between effort, duration, and the maximum yield.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Oligopoly

A

Is a procurement issue where there are few vendors available to choose from. Plus, the vendors may seemingly have check and balances with each other.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Contingency Reserve

A

Is a portion of the project schedule allotted for time overruns on activities.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Cost Benefit Analysis

A

May be the part of the process to decide the value of adding more workers to the schedule.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Gantt Chart

A

Is a bar chart that represents the duration of activities against a calendar. The length of the bar represents the length of activities, while the order of the bars represents the order of activities in the project.

17
Q

Slack Time

A

Is the amount of time a task can be delayed without delaying the scheduled start date of dependent activities.

18
Q

Flattening Projects

A

If you flatten your project through resource leveling, the project duration will likely increase.