Product-oriented process

A

Are unique to the product the project is creating.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

EVM Processes

A

Are part of project performance measurement.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

IPECC

A

Is the acrostic for the five process groups, initiation, planning, executing, controlling, and closing.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Planning Process

A

This is progressively elaborated. Throughout the project, the project team and the project manager will revisit the planning processes to consider, update, and react to conditions and circumstances within the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Rolling Wave Planning

A

Describes the planning process in most large projects. It requires the project manager and the project team to revisit the planning process to address the next phase, implementation, or piece of the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Phase Gates

A

Are conditions that allow the projects to move from phase to phase.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Initiating Processes

A

These serve as a direct input to the planning processes.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Change Control Board

A

Will review and approve changes to the project scope. Due to the high requirements of the stakeholders, a CCB can help fend off unneeded changes and allow the project manager to focus on the project management activities, rather than the potential flood of change requests.