MOCK 4 Flashcards
88 Q
- You and your project management staff are performing product analysis. What process are you performing?
●
A.Define Scope
B.Collect Requirements
C.Create WBS
D.Develop Project Charter
Answer: A The Project Scope Statement can be developed by reviewing the Project Charter (high-level product information).
- You and your project management staff are determining calendar dates for your project’s schedule. You are performing which of the following processes?
A.Estimate Activity Durations
B.Develop Schedule
C.Sequence Activities
D.Estimate Resources
Answer: B A determines work periods, not calendar dates. C merely sequences activities. D merely estimates what and how many resources will be required.
- You and your project management staff are determining how to sequence activities. Which of the following dependency relationships is most common and considered mandatory?
A.Start-to-finish
B.Start-to-start
C.Finish-to-finish
D.Finish-to-start
Answer: D All the other activity dependencies are performed concurrently.
- You and your project management staff are determining the budget required to complete the project. You have estimated the costs and aggregated the costs to perform the project activities. When you examine the Project Charter, you note the control account is less than what will be needed to complete the project. This relates to:
●
A.Procurement estimating
B.Cost Control
C.Delphi technique
D.Funding limit reconciliation
Answer: D A is a made up term but would only be a subset of overall project cost. B is not as good as D. C relates to anonymous information gathering.
- You are in the middle of a biomedical device project in Canada. A team member informs you the project currently has a CPI of 1.3. Which of the following should you do first?
●
A.Ask the team if they can work overtime for the foreseeable future.
B.Tell the Project Sponsor you will need to crash the project as soon as possible.
C.Verify that the EV and PV that were used to calculate are correct.
D.Verify that the EV and AC that were used to calculate are correct.
Answer: D (EV/AC = CPI) If these numbers are correct (verify first), the project is under budget. A Since you are likely under budget, this will probably not be necessary. B is not needed—see A. C PV is not used to calculate CPI.
- You are in the middle of a large building project in Brazil. A team member informs you that changes will need to be made soon. Which of the following should you do first?
●
A.Recommend alternatives to the Change Control Board (CCB).
B.Ask for a detailed description of the change.
C.Follow your change control process.
D.Ensure you have sufficient contingency reserves.
Answer: C Follow your change control process, is typically always the best course of action. The other options may all be part of this process.
- You have been assigned to set up a call center in Panama, that will service most of Central and South America. You and a Business Analyst are assisting with developing a business case as an input to the Project Charter. Which of the following does not relate to developing a Project Charter?
●
A.Ensure success can be measured (e.g. SMART Objectives, Key Performance Indicators (KPIs)).
B.Identify key stakeholders/groups, and record in the Stakeholder Register.
C.Developing a Stakeholder Management Plan.
D.Determine high-level goals/objectives.
Answer: C This process is performed in Planning, not Initiating.
- EV = 100, AC = 110, PV = 90. Based on this data, which of the following is true?
●
A.You are over budget, but ahead of schedule.
B.You are under budget, but behind schedule.
C.Vendors may need to be hired to get the project back of schedule.
D.The project should be crashed as soon as possible.
Answer: A (EV / AC = CPI) .90 means you are only getting .90 cents for every dollar invests (over budget). EV / PV = SPI 1.11 means you are 11% ahead of schedule. So, you are over budget, and ahead of schedule right now. Crashing the project would likely put it even more over budget.
- You have been asked by your Project Sponsor where you have documented the steps that will be taken during the course of the project to make continuous improvements. Where is this information documented?
●
A.Quality Improvement Plan.
B.Quality Management Plan.
C.Scope Improvement Plan.
D.Scope and Quality Benchmarking.
Answer: B. Along with quality metrics and quality checklists. A & C are made up terms. Benchmarking is a tool/technique for analysis of scope and quality.
- You have been asked by your Project Sponsor to develop an adaptive lifecycle for your project, that will only take about 2 weeks to complete. Which of the following does not relate to an adaptive lifecycle?
●
A.Plan Do Check Act (PDCA)
B.Agile
C.Iterative and incremental lifecycles
D.CMMI
Answer: D. A relates to Total Quality Management, quality improvement, Edwards Deming, iterative/incremental/adaptive lifecycles, Agile, and possibly rolling wave/progressive elaboration. B relates to C. D looks at maturity level of an organization. Note how A, B, C all relate to each other.
- Your Sponsor wants to understand why you want to include additional money in your project budget to address the cost of conformance. Which of the following relates to the cost of conformance?
●
A.Loss of business
B.Legal liabilities
C.Rework
D.Training
Answer: D. Upfront, preventative costs. A, B, & C all relate the cost of NON-conformance (failure costs).
- Which of the following relates to linking performance to rewards, that may change over time?
●
A.Situational Theory
B.Expectancy Theory
C.Hygiene Theory
D.Theory Z
Answer: B. This relates to Victor Vroom’s Expectancy Theory. A relates to Hersey/Blanchard (leaders, followers, situation). C relates to Herzberg (hygiene factors, motivating agents). D relates to Ouichi’s theory that people are more motivated/committed if they are promised lifelong employment.
- Which of the following relates to “motivating agents”:
●
A.Need to achieve, affiliate, or have power
B.Hierarchy of Needs Theory
C.Frederick Herzberg’s Three Needs Theory
D.Frederick Herzberg’s Hygiene Theory
Answer: D. Hygiene factors and motivating agents. A is three needs theory. B is Abraham Maslow’s theory. C is close, but not the name of the theory.
- All of the following tools can be used to brainstorm the source of defects, except:
●
A.Ishikawa diagrams
B.Causal influence diagrams
C.Quality metrics
D.Nominal group technique
Answer: C. Quality metrics are not a brainstorming tool to determine causes (sources) of defects, but are used to measure quality. A, B, & D are brainstorming tools that can be tools used to brainstorm causes.
- You have been assigned to a hazardous waste cleanup project that will take eight months. Your company’s personnel, and the vendors that will be needed have not received training on how to perform their duties safely. Which is the best course of action to recommend to your Project Sponsor?
●
A.Proceed without training, but tell all stakeholders to be careful while handling the hazardous waste.
B.Tell all stakeholders that need training to pay for their own training.
C.As a cost of conformance, train all stakeholders that will be “in harm’s way.”
D.Train the employees, but not the vendors.
Answer: C “Team training” is considered a cost of conformance. It is best to train both affected parties in this instance, rather than risk legal cases, etc.
- Which of the following best relates to observing/analyzing “feelings”?
●
A.Stakeholder engagement
B.Conflict resolution
C.Emotional intelligence (EI)
D.Communication model
Answer: C Emotional Intelligence (EI), sometimes called emotional quotient (EQ), is the ability to recognize our own as well as other people’s emotions, to discriminate between different feelings, and to use this information to guide thinking/behavior. Having a high EI is considered to be good for leadership, mental health, and better job performance.
.
- Conflicts have been surfacing frequently on your software development project lately. You have determined you should not overlook them. Which of the following relates to the best type of conflict management?
●
A.Compromising
B.Smoothing
C.Avoiding
D.Storming
Answer: A It’s the best answer, because joint problem solving is not listed. B & C do not address the problem. D may be the team development stage that includes conflict, but is not a technique for managing it.
.
- You have just been assigned to build a large state-of-the-art cleanroom for a large computer chip manufacturer. You need to ensure risk is carefully managed over this two-year project. Which of the following lifecycles would be most appropriate?
A.Agile
B.Predictive
C.Iterative
D.Rolling wave
Answer: B With predictive lifecycles, more time is spent upfront planning, including risk management. The other choices relate more to adaptive/change-driven lifecycles.
- All of the following take place during the Monitoring and Controlling, Process Group, except:
A.Formalized acceptance
B.Quality Assurance is performed
C.Changes are recommended to the Change Control Board
D.Risk audits/reassessment is performed
Answer: B Quality Assurance is performed during Executing. All the other choices are performed during Monitoring and Control.
- You will require two, key contractors (SMEs) to execute your landscaping project, and are negotiating now to determine their availability. This is an example of:
A.Fait accompli
B.External stakeholders
C.Pre-assignment
D.Virtual team members
Answer: C These stakeholders will be necessary to begin. A is a negotiating tactic a seller might use. B is wrong because they would actually be internal project stakeholders. D is wrong because it has nothing to do with the need to assign the team members.
- You have included several quality control tools on your toll road project including quality control charts. All of the following relate to a quality control chart, except:
A.Specification and upper/lower control limits
B.Rule of seven and assignable cause
C.Mean
D.Sensitivity analysis
Answer: D Sensitivity analysis relates more to quantitative risk analysis. All the other choices relate to a quality control chart.
- You will need to spend a significant amount of time estimating resources, duration, and cost on your project. Which of the following estimates is most likely the least accurate:
A.Parametric estimating
B.Three-point estimating
C.Bottom-up estimating
D.Analogous
Answer: D Analogous is typically performed during Initiating and high-level (Rough order of magnitude ROM). Note the Estimate Activity Resources, Estimate Activity Duration, and Estimate Costs are performed during the Planning Process Group. The level of accuracy for a ROM estimate (Initiating) is -25% to +75%. The definitive estimate accuracy level (Planning) is -5% to +10%.
- You will need to spend some time estimating resources, duration, and cost on your project. Which of the following estimates may encourage participation and reduce bias:
A.Parametric estimating
B.Three-point estimating
C.Bottom-up estimating
D.Delphi technique
Answer: D Anonymous (i.e. Delphi) estimating is typically performed to help encourage participation.
- You and your project management staff are developing the Human Resource Management Plan. You are currently discussing how to recognize and reward the project team. Which of the following is typically the best approach:
A.Reward the project team at the end of project.
B.Reward only high-performing individuals at the key milestones.
C.This should be done at the employees regular performance reviews with the Human Resources department.
D.Reward the team and high performing individuals regularly (e.g. key milestones) over the course of the project.
Answer: D It’s best to keep everyone as motivated as possible throughout the project lifecycle. A waits too long for recognition, and only focuses on the team—not individuals.
- Which of the following does not relate to Communications Management:
A.Virtual team considerations.
B.Non verbal communication and para-lingual ques.
C.Encoder, Medium, Communication Blockers, Decoder, Feedback.
D.Responsible, Accountable, Consult, Inform (RACI).
Answer: D This relates more to different levels of authority in the ( Responsibility Assignment Matrix (RAM). A may relate to technology, time zones, culture, language. B 55% of communication is body language, and Para-lingual queues relates to the pitch and tone of the voice. C relates to the components of the communications model.
- You are developing a predictive lifecycle on your construction project in Mexico to better manage risk. Process sequence is paramount. Which processes are not listed in the proper sequence?
A.Estimate Resources, Estimate Activity Duration, Sequence Activities
B.Collect Requirements, Define Scope, Create WBS
C.Plan Cost Management, Estimate Costs, Develop Budget
D.Plan Human Resource Management, Plan Communications Management
Answer: A Estimating comes after sequencing activities. All the rest are in the proper sequence.
- You are currently helping senior management determine which project to select. All of the following relate to project selection methods, except:
A.Affinity diagrams
B.Constrained optimization method
C.Benefit cost ratio
D.Monte Carlo Simulation/Modeling
Answer: A. It is more likely to see affinity diagrams mentioned as a quality assurance tool/technique during the Executing Process Group. B relates to using a computer for project selection, as does D. C is a benefit measurement method that often relates to determining value on the exam.
- You are currently closing down your project. Which is a helpful input for closing down the project, and closing procurements.
A.Organizational Process Asset updates
B.Communication logs
C.Project Management Plan
D.Final change requests
Answer: C. The Project Management Plan is an input for both process performed during Closing. A is always an output. B is a made up term. D should have already been completed.
- You are performing quantitative risk analysis during Planning. Expected monetary value analysis (EMV) (e.g. decision tree) provides the following information; Project A has an EMV of $100,000, Project B has an EMV of $75,000, Project C has an EMV of $100,500, and Project D has an EMV of $90,000. You would most likely choose which project based on this information.
A.Project B
B.Project A
C.Project D
D.Project C
Answer: D. With no other information available, just choose the highest EMV. Note that answer “D” is Project “C.” Be careful!
- You have to resolve a conflict that is beginning to plague you and one of the members on your project team. The person you need to resolve the conflict with is in the same city, but not in your building. The best way to resolve the conflict is:
A.Notify the person’s boss via email, to see if all three of you can come to a compromise.
B.Set up a phone conference with the person before the next meeting, to let them know why you are concerned.
C.Bring up the issue at the next project status meeting, and allow the team to help resolve the issue.
D.Set up a time to meet the person, and meet them in the cafeteria or break room to chat about the issue(s).
Answer: D. Face-to-face, one-on-one, informal conflict resolution is always best.
- You are working with your project management staff on your risk register. All of the following could relate to this process except:
A.Scales of probability and impact and the probability-impact matrix.
B.A list of qualified risks based on probability and impact.
C.Residual risks, and secondary risks.
D.Contingency strategies, and reserves.
Answer: A. This information would not likely appear in the risk register, but the other choices would.