- Which of the following is NOT a characteristic of a project?
A. Constrained by limited resources
B. Planned, executed, monitored, and controlled
C.Creates a unique product or service
D.Ongoing and repetitive
Answer: D
Explanation: A project is a temporary endeavor undertaken to create a unique product, service, or result. The temporary nature of projects indicates a definite beginning and ending.
- In which document would you find the code of account identifier, description of work, responsible organization:
A. Scope Statement
B. WBS Dictionary
C. PERT/Charts
D. Responsibility Assignment Matrix
Answer: B
Explanation: Information in the WBS dictionary includes, but is not limited to, code of account identifier, description of work, responsible organization, list of schedule milestones, etc.
- All the following statements relating to Project Management Staff and the project team are accurate EXCEPT:
A. The Project Management Staff helps develop the Project Management Plan.
B. The Project Team is responsible for activities like planning, controlling, and closing.
C. The Project Management Staff is a subset of the project team.
D. For very small projects, the project management responsibilities might be shared by the entire project team or administered solely by the project manager.
Answer: B
Explanation: The Project Management Staff is a subset of the project team and is responsible for the project management and leadership activities such as initiating, planning, executing, monitoring, controlling, and closing the various project phases. This group can also be referred to as the core, executive, or leadership team. For smaller projects, the project management responsibilities can be shared by the entire team or administered solely by the project manager.
- You are considering whether to buy or make a software product. If you want to buy, the cost is $ 80,000, and the cost of procuring and integrating the product in your company is $ 1,000. If you want to build it yourself, the product will require seven engineers working for three months. The salary of each software engineer is $ 4,000 per month. The other related miscellaneous costs budget allocated to the project is $2,000.
Which option will you choose?
A. Buy
B. Build
C. Neither build, nor buy
D. Need more information on suppliers to make a decision
Answer: A Explanation: If you buy, the cost is: $ 80,000 + $ 1,000 = $ 81,000,
If you build, the cost is: $ 4,000 x 7 x 3 + $ 2,000 = $ 86,000. So, in this situation, it is preferable to buy.
- Which of the following would not be helpful in performing the Develop Schedule Process?
Schedule network analysis, critical path method, critical chain method
Project calendars and schedule data
Scheduling tool, schedule compression, leads and lags
Modeling techniques, resource optimization techniques
Answer: B Explanation: Know your Tools/Techniques. Project calendars and schedule data are outputs of the Develop Schedule Process.
- In the context of the communication model, all the following statements are correct EXCEPT:
Noise (communication blockers) should be minimized.
Receiver should decode and reply to the message.
Decoder (receiver) should acknowledge and agree with the message sent by the encoder (sender).
Decoder should send a feedback message to the encoder.
Answer: C Explanation: Inherent in the communication model is an action to acknowledge a message. Acknowledgment signals only receipt of the message, not agreement or understanding
- The government has mandated that you ensure the neighborhood is not adversely impacted by your project. For your project, this directive is regarded as a/an:
Assumption
Ethical practice
Constraint
LEAN
Answer: C Explanation: From a project management point of view, constraints are factors that will limit the Project Management Staff`s options. Since this is a government mandate, it becomes a constraint for your project. LEAN is a quality technique focused on reducing/eliminating waste.
- You are estimating schedule activity costs by determining the unit cost rates, e.g., staff costs per hour. All the following could be used to determine resource cost rates EXCEPT:
Statistical relationship (parametric estimating) between historical data and other variables.
Interviewing those doing the work.
Reviewing standard rates with escalation factors (for contracts).
Reviewing a seller’s published price list.
Answer: A Explanation: Parametric estimating uses a statistical relationship between historical data and other variables. All the other options are valid ways to determine unit cost rates.
- You are performing the Control Risks process, and are on the lookout for indications that a risk has occurred or is about to occur. These indications can also be referred to as:
Triggers
Workarounds
Risk averse
Triggers, early warning signs, and risk symptoms
Answer: D Explanation: Best answer is Triggers. Indications that a risk has occurred or is about to occur. Triggers may be discovered in the risk identification process and watched in the risk monitoring and control process. Triggers are sometimes called risk symptoms or warning signs.
- Stakeholders, including consultants, customers, sponsors, and professional and technical associations, that gather and analyze information with people and/or computers, are some of the sources of:
Enterprise environmental factors
Organizational process assets
Expert judgment
Stakeholder monitoring and control
Answer: C Explanation: Expert judgment: Additional expertise is available from many sources, including… other units within the organization; stakeholders, including consultants, customers, and sponsors; and professional and technical associations.
- You decide to use statistical sampling for your project, because surveying the entire population involves all the following issues, except:
Inaccurate data
More money
More time
More resources
Answer: A Explanation: Survey of the entire population would yield the most accurate data.
- Your organization requires that all technical projects go through Initiate, Analyze, Design, Implement, Test, and Closeout project life cycle which is:
Defined as the product life cycle.
Defined by having applicable project phases.
Contains several product life cycles.
Has deliverables that must be completed before work starts during the next phase.
Answer: B Explanation: A project life cycle is a collection of generally sequential and sometimes overlapping project phases whose name and number are determined by the management and control needs of the organization or organizations involved in the project, the nature of the project itself, and its area of application. Option A and Option C are wrong because project life cycle does not include the product life cycle. Option D is not accurate because work in the next phase may, at times, start before the deliverables of the previous phase are completed.
- Your team started creating a work breakdown structure for your project, but soon realized the project was too complex to be depicted completely in graphic format. You began using a work breakdown structure code of accounts to:
Determine the complexity of the project
Identify the level at which individual WBS elements are found
Help in automating the WBS using appropriate software
Present justification for completing the project
Answer: B Explanation: The WBS is finalized by establishing control accounts for the work packages and a unique identifier from a code of accounts. These identifiers provide a structure for hierarchical summation of costs, schedule, and resource information.
- You advocate active participation of your team members; this is because you believe in:
Theory Y (McGregor Model)
Theory X (McGregor Model)
Maslow`s hierarchy of needs
Referent Power
Answer: A Explanation: Douglas McGregor advocates that most workers can be categorized according to two theories: Theory X: This assumes that the workers are inherently lazy and require supervision Theory Y: The average worker finds physical and mental effort on the job satisfying and likes his work.
- Which of the following is the most widely used contract type?
Cost plus incentive fee contracts
Fixed price incentive fee contracts
Cost plus award fee contracts
Firm Fixed Price Contract
Answer: D Explanation: Firm fixed price contracts (FFP) is the most commonly used contract type. (And the type that is easier to budget for, typically provides the lowest risk, and requires no day-to-day administration.)