MOCK 2 Flashcards
- You are responsible for meeting the project schedule deadlines. If there is some delay in the project schedule, you should:
A.Increase the timeline for the project.
B.Determine what would happen if you fast tracked or crashed the project, and let the Change Control Board know the impact.
C.Ask the resources to work overtime to meet the project deadlines.
D.Change the project scope.
Answer: B Explanation: Schedule compression shortens the project schedule without changing the project scope to meet schedule constraints, imposed dates, or other schedule objectives. Schedule compression techniques, include crashing, fast tracking, re-estimating, and/or cut scope/quality.
- You are performing the Manage Communications Process. Which of the following is NOT an Tool/Technique:
A.Work performance information
B.Communications technology
C.Communications methods
D.Information management systems
Answer: A Explanation: Performance reports are the output from the Control Communications Process; not from Manage Communications Process.
- One of your team members filed a critical report ten minutes before a bidder conference. You notice some serious errors have crept into the report. You should:
A.Reschedule the meeting for a later date.
B.Go ahead with the meeting and tell the participants what is wrong with the report.
C.Go ahead with the meeting, but ask your team member to make the presentation.
D.Refer the team member`s report to management and ask them to cancel the meeting.
Answer: A Explanation: Option A is the best choice. It’s always best to understand things before you try to discuss them . Option B and C can adversely impact the team morale and undermine your position in the bidder conference. Option D is not recommended, as you should take ownership to solve the problem.
- You are creating a cost performance baseline for your project. All of the following statements related to cost performance baseline are correct EXCEPT:
A.It is a time - phased budget.
B.To measure disbursements, a spending plan can be used as a cost-baseline.
C.It is used to measure, monitor, and control overall cost performance.
D.In the earned value management technique, it is also known as cost measurement baseline.
Answer: D Explanation: In the earned value management technique, the cost performance baseline is referred to as the performance measurement baseline (PMB).
- You are the project manager in an automobile manufacturing company. Machine parts required in your manufacturing process supplied by a vendor did not reach in time because of heavy rains. You had anticipated this risk and planned for it in your risk register. You started using unutilized machine parts supplied one year ago. However, this has subjected your project to a new risk - the machine parts which were not used for one year suffer from higher level of defects. This new risk can also be called:
●
A.Contingency risk
B.Pure risk
C.Secondary risk
D.Residual risk
Answer: C Explanation: Components of risk register…Secondary risks that arise as a direct outcome of implementing a risk response.
- You are in the process of performing the work as defined in the project management plan to achieve the project`s objectives. This is done during:
A.Direct and Manage Project Work
B.Develop Project Management Plan
C.Validate Scope
D.Create Deliverables
Answer: A Explanation: Performing the work is done during Executing. Direct and Manage Project Work is the process of performing the work defined in the project management plan to achieve the project`s objectives.
- You are managing the tools/spare parts section for an aircraft manufacturing company. Your team members have discovered some defective tools/spare parts. The probable cause for these could be materials used, defective measurement systems, inaccurate tolerances in the machines, or other factors. To determine what caused the defect, you use:
●
A.Use a quality control chart
B.Draw an Ishikawa diagram
C.Create a flowchart
D.Draw a Pareto chart
Answer: B Explanation: Cause and effect diagrams (also called Ishikawa or fishbone diagrams), illustrate how various factors might be linked to potential problems or effects.
- You have been managing a project to construct a bridge on an Interstate highway. You have divided the project into phases to provide better management control. Which of the following is a characteristic of a project phase?
A.Formal phase completion necessarily includes authorization for the subsequent phase.
B.A project phase can be closed with a decision not to begin the subsequent phase.
C.Project phases shouldn’t be divided into sub-phases even in complex projects, as it becomes too difficult to manage.
D.All deliverables in the project phase should correspond to the project management process.
Answer: B Explanation: Formal phase completion does not necessarily include authorization for the subsequent phase. For instance, if the risk is deemed to be too great for the project to continue or if the objectives are no longer required, a phase can be closed with the decision not to initiate any other phase.
- An environmental remediation project has succeeded in reducing costs. This is achieved by implementing a change request for new technology not available when the scope was originally defined. An approach used to optimize project life cycle costs, save time, increase profits, improve quality, expand market share, solve problems, and/or use resources more effectively is called:
A.Value engineering
B.Unanimity
C.Voice of customer
D.Kanban
Answer: A Explanation: This is the definition for Value Engineering. Kanban is a method for managing knowledge work with an emphasis (JIT), and LEAN. Work is pulled from a que. May also relate to visual process management.
36.According to Herzberg`s theory, all of the following are motivating factors, except:
●
A.Recognition
B.Increased responsibility
C.Career advancement possibilities
D.Salary
Answer: D (Although an increase in salary for additional performance can be a motivator, salary by itself is not.)
- You have to provide a critical deliverable within five months and do not have time to go through the Conduct Procurements process. You decide to sign a contract with a supplier with whom your company has done some work in the past. The risk you are accepting in this situation is:
A.The ability/skills of the supplier to deliver the goods.
B.Collusion between the supplier and your team.
C.Lack of proper scope definition.
D.Lack of a legally binding agreement.
Answer: A Explanation: The risk here is that even though the supplier has worked with the company in the past, they may not have the required skills for the current project.
- You are in the process of performing the Develop Schedule process to determine planned start and finish dates for project activities. Which of the following inputs will be helpful for beginning this process?
A.Activity attributes, project scope statement, and activity list
B.Activity list, activity attributes, and schedule data
C.Project calendar, requested changes, and schedule data
D.Work performance information, schedule baseline, and performance reports
Answer: A Explanation: In the Develop Schedule Process, planned start and finish dates for project activities are determined by using activity attributes, project scope statement, and activity list as inputs. The other options contain outputs.
- You are performing the Control Communications Process to organize and summarize the information gathered. Later, you present the results of the analysis as a comparison to the performance measurement baseline. Some common formats for performance reports that you could use are:
A.S-curves, histograms, Pareto diagrams, GERT Charts
B.S-curves, responsibility assignment matrices, histograms
C.Bar charts, S-curves, histograms
D.Bar charts, control charts, project network diagrams
Answer: C Explanation: Common formats for performance reports include bar charts, S-curves, histograms, and tables.
- You are managing a project in a foreign country, and now you realize you will have to pay a fee to some government agencies to get your work done. You should:
●
A.Pay the fee to the government agencies.
B.Refuse to pay the fee, because they are bribes and hence unethical.
C.Make a case why fees should be paid to government agencies, and present it to your management.
D.Offer gifts to the government officials instead of fee to get their support.
Answer: A Explanation: A project manager has the responsibility to refrain from offering or accepting inappropriate payments, gifts, or other forms of compensation for personal gain, unless it is in conformity with applicable laws or customs of the country where the project management services are provided. In this scenario, however, since the law of the country requires payment of fee to the government agencies, you will not be committing any breach of the Code if you pay the same. It is a constraint.
- There have been several variances in the cost and schedule estimates on your project, and the original estimating assumptions are no longer valid. The variances will likely continue until the end of the project. Calculate the estimate at completion (EAC) for your project based on the following data?
BAC = $ 1,000,000
EV = $ 200,000
PV = $ 400,000
AC = $ 150,000
A.$ 1,425,142
B.$ 1,200,120
C.$ 751,879
D.$ 1,050,000
Answer: A Explanation: Since original estimating assumptions are no longer valid, use: AC + (BAC – EV) / (SPI x CPI) Reminder: SPI = EV / PV and CPI = EV / AC $ 150,000 + ($1,000,000 - $200,000) / (.5 x 1.333) so…. $950,000 / .6666