Measurement Performance Domain Flashcards

1
Q

What Do Project Managers Measure?

A
  • Deliverable Metrics / Which Metrics to Measure
  • Delivery / Work Performance Metrics
  • Baseline Performance
  • Resources
  • Business Value
  • Stakeholders
  • Forecasts
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Leading Indicators

A
  • KPI to predict changes or trends in project
  • Example: Project Size, # of items in progress or backlog
  • Can help reduce performance risk when used in tandem with identified performance variances
  • Qualitative indicators include stakeholder engagement, risk management, success criteria definitions, etc.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Lagging Indicators

A
  • KPI that measures the past performance of project deliverables or events
  • Can correlate performance outcomes with environmental variables
  • Example: work amount completed vs. morale
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Examples of Deliverable Metrics Specific To Product Type

A
  • Error or Defects (source, # of, and # resolved)
  • Performance Measures (size, weight, capacity, accuracy)
  • Technical Performance Measures (requirements for technical Components or technical solutions)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Delivery Metrics

A
  • WIP
  • Lead & Cycle Time
  • Queue Size
  • Batch Size
  • Process Efficiency
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

WIP

A
  • # of items that are in progress
  • # is limited to partition work to a manageable size
  • Compared to Queue Size
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Lead Time

A
  • The total time an item takes from entering the backlog to iteration or release
  • Can indicate a more effective overall work process or project team
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Cycle Time

A
  • The amount of time it takes to complete at ask
  • Shorter times indicate productive project teams
  • Consistent cycle times can help predictions
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Queue Size

A
  • The # of items in a queue
  • Compares with WIP limit
  • Can help forecast overall completion
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Batch Size

A
  • The estimated amount of work to be completed for an iteration
  • level of effort, story points, etc.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Process Efficiency

A
  • Value Adding Time / Non-Value Adding Time
  • Tasks in development or in-verification = value adding time
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Metrics for SCHEDULE Baseline

A
  • Start & Finish Dates
  • Efforts & Duration
  • Schedule Variance
  • Schedule Performance Index
  • Feature Completion Rates
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Metrics for for COST Baseline

A
  • Actual vs Planned Cost
  • Cost Variance
  • Cost Performance Index
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Cost Variance

A
  • CV = EV - AC
  • Earned value - Actual Cost
  • Component of Cost Baseline
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Cost Performance Index

A
  • CPI = EV / AC
  • Earned Value / Actual Cost
  • Component of Cost Baseline
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Schedule Performance Index

A
  • SPI = EV / PV
  • Earned Value / Planned Value
  • Component of Schedule Baseline
17
Q

Schedule Variance

A
  • SV = EV - PV
  • Earned Value - Planned Value
  • Part of Schedule Baseline
18
Q

Identify This System & Delivery Method

A
  • Value Management System
  • Commonly used in Predictive / Waterfall Delivery
19
Q

Business Value Metrics

A
  • Cost-Benefit Ratio
  • Planned vs. Actual Benefits Delivery
  • Return on Investment (ROI)
  • Net Present Value (NPV)
20
Q

Net Present Value

A
  • NPV = Value Inflow - Value Outflow of all business capital
  • Used to decide starting or continuing a project
  • Business Value Metric
21
Q

Return on Investment

A
  • Financial return compared to cost
  • Business Value Metric
22
Q

Exception Plan

A
  • An agreed upon plan to make an exception if a threshold is crossed or forecasted to occur
  • Important to plan:
    1) the exception,
    2) what needs to be done, and
    3) criteria to measure if the exception is helping
23
Q

Forecast Metrics

A
  • Estimate To Completion (ETC)
  • Estimate At Completion (EAC)
  • Variance At Completion (VAC)
  • To-Complete Performance Index (TCPI)
  • Regression Analysis
  • Throughput Analysis
24
Q

Estimate To Completion

A
  • ETC = (BAC - EV) / CPI
  • Forecasts the expected cost to finish all REMAINING work
  • Component of Forecast Measurements
  • Earned Value Management System for Waterfall metric
25
Q

Estimate At Completion

A
  • EAC = BAC / CPI
  • Forecasts expected cost to finish all work
  • Component of Forecast Measurements
  • Earned Value Management for Waterfall metric
26
Q

Variance At Completion

A
  • VAC = BAC - EAC
  • Variance at Completion = Budget At Completion - Estimate At Completion
  • Component of Forecast Measurements
27
Q

To-Complete Performance Index

A
  • Estimates the cost of performance to meet a specific management goal
  • Cost to Finish Remaining Outstanding Work / Budget Remaining
  • Component of Forecast Measurements
28
Q

Regression Analysis

A
  • Estimating the relationship between variables on multiple dimensions
  • Used to forecast or infer future performance
29
Q

Throughput Analysis

A
  • The # of items being completed in a fixed timeframe
  • Can be used for adaptive practices
  • Examples include Features Complete vs. Remaining, Velocity, or Story Points Completed
  • Used to evaluate progress and estimate likely completion dates
  • Can help verify or update cost estimates when used with burn rates for stable project teams