Measurement Performance Domain Flashcards
1
Q
What Do Project Managers Measure?
A
- Deliverable Metrics / Which Metrics to Measure
- Delivery / Work Performance Metrics
- Baseline Performance
- Resources
- Business Value
- Stakeholders
- Forecasts
2
Q
Leading Indicators
A
- KPI to predict changes or trends in project
- Example: Project Size, # of items in progress or backlog
- Can help reduce performance risk when used in tandem with identified performance variances
- Qualitative indicators include stakeholder engagement, risk management, success criteria definitions, etc.
3
Q
Lagging Indicators
A
- KPI that measures the past performance of project deliverables or events
- Can correlate performance outcomes with environmental variables
- Example: work amount completed vs. morale
4
Q
Examples of Deliverable Metrics Specific To Product Type
A
- Error or Defects (source, # of, and # resolved)
- Performance Measures (size, weight, capacity, accuracy)
- Technical Performance Measures (requirements for technical Components or technical solutions)
5
Q
Delivery Metrics
A
- WIP
- Lead & Cycle Time
- Queue Size
- Batch Size
- Process Efficiency
6
Q
WIP
A
- # of items that are in progress
- # is limited to partition work to a manageable size
- Compared to Queue Size
7
Q
Lead Time
A
- The total time an item takes from entering the backlog to iteration or release
- Can indicate a more effective overall work process or project team
8
Q
Cycle Time
A
- The amount of time it takes to complete at ask
- Shorter times indicate productive project teams
- Consistent cycle times can help predictions
9
Q
Queue Size
A
- The # of items in a queue
- Compares with WIP limit
- Can help forecast overall completion
10
Q
Batch Size
A
- The estimated amount of work to be completed for an iteration
- level of effort, story points, etc.
11
Q
Process Efficiency
A
- Value Adding Time / Non-Value Adding Time
- Tasks in development or in-verification = value adding time
12
Q
Metrics for SCHEDULE Baseline
A
- Start & Finish Dates
- Efforts & Duration
- Schedule Variance
- Schedule Performance Index
- Feature Completion Rates
13
Q
Metrics for for COST Baseline
A
- Actual vs Planned Cost
- Cost Variance
- Cost Performance Index
14
Q
Cost Variance
A
- CV = EV - AC
- Earned value - Actual Cost
- Component of Cost Baseline
15
Q
Cost Performance Index
A
- CPI = EV / AC
- Earned Value / Actual Cost
- Component of Cost Baseline
16
Q
Schedule Performance Index
A
- SPI = EV / PV
- Earned Value / Planned Value
- Component of Schedule Baseline
17
Q
Schedule Variance
A
- SV = EV - PV
- Earned Value - Planned Value
- Part of Schedule Baseline
18
Q
Identify This System & Delivery Method
A
- Value Management System
- Commonly used in Predictive / Waterfall Delivery
19
Q
Business Value Metrics
A
- Cost-Benefit Ratio
- Planned vs. Actual Benefits Delivery
- Return on Investment (ROI)
- Net Present Value (NPV)
20
Q
Net Present Value
A
- NPV = Value Inflow - Value Outflow of all business capital
- Used to decide starting or continuing a project
- Business Value Metric
21
Q
Return on Investment
A
- Financial return compared to cost
- Business Value Metric
22
Q
Exception Plan
A
- An agreed upon plan to make an exception if a threshold is crossed or forecasted to occur
- Important to plan:
1) the exception,
2) what needs to be done, and
3) criteria to measure if the exception is helping
23
Q
Forecast Metrics
A
- Estimate To Completion (ETC)
- Estimate At Completion (EAC)
- Variance At Completion (VAC)
- To-Complete Performance Index (TCPI)
- Regression Analysis
- Throughput Analysis
24
Q
Estimate To Completion
A
- ETC = (BAC - EV) / CPI
- Forecasts the expected cost to finish all REMAINING work
- Component of Forecast Measurements
- Earned Value Management System for Waterfall metric
25
Q
Estimate At Completion
A
- EAC = BAC / CPI
- Forecasts expected cost to finish all work
- Component of Forecast Measurements
- Earned Value Management for Waterfall metric
26
Q
Variance At Completion
A
- VAC = BAC - EAC
- Variance at Completion = Budget At Completion - Estimate At Completion
- Component of Forecast Measurements
27
Q
To-Complete Performance Index
A
- Estimates the cost of performance to meet a specific management goal
- Cost to Finish Remaining Outstanding Work / Budget Remaining
- Component of Forecast Measurements
28
Q
Regression Analysis
A
- Estimating the relationship between variables on multiple dimensions
- Used to forecast or infer future performance
29
Q
Throughput Analysis
A
- The # of items being completed in a fixed timeframe
- Can be used for adaptive practices
- Examples include Features Complete vs. Remaining, Velocity, or Story Points Completed
- Used to evaluate progress and estimate likely completion dates
- Can help verify or update cost estimates when used with burn rates for stable project teams