Management Of Natural Environment And Landscape Flashcards
What steps need to be taken to remove a hedgerow? What is the sanction if these are not followed?
Apply for consent from LPA.
42 days to respond following receipt confirmed
Can appeal notice within 28 days
Unlimited fine is not followed
Who is responsible for protected hedgerows?
Natural England and LPA
What is the legislation protecting hedgerows?
Hedgerow regulations 1997
What sensitivities were in place on the Basingstoke diversion?
NVZ present
TPO on trees in access - Basingstoke and Deane council. Application to LPA under TCPA 1990. TCP (tree preservation) (England) regulations 2012 - part 4 = application to consent
Hedge removal also required
Full ecology survey recommended
What is the penalty for not complying with TPO regulations?
£20,000 fine
What are the TPO regulations?
The town and country planning (tree preservation) (England) regulations 2012
What pre commencement works did you advise of at chobham common?
Liaised with Surrey WT regarding their requirements
Ground nesting birds in the access route. Wood larks, night jars, dartboard warblers.
Nesting season March-August.
Shut down September.
I advised my client to undertake clearance of scrub on access route in February to ensure minimal impact on birds. SWT agreed
What legislation are bird protected under?
Wildlife and countryside act 1981
What is the penalty for not complying with bird protection regulations
Unlimited fine
6 months imprisonment
What permit was required on the river Trent?
Who From?
A bespoke permit from the environment agency
What did the contractors have to supply for the bespoke permit at the river Trent
Risk assessment
Management system
Plans and documents describing the works
Standard forms
What are the permits available from the EA
Exemption - where permit isn’t required
Standard rules permit- common activities with fixed rules
Bespoke permit - tailored to the risks of specific activity
What sensitivities were on the land at southwold?
Turtle doves nesting - April to September
What scheme was in place over the land where CP works were required
SW1 - 4m - 6m buffer strip on cultivated land
Mid- tier stewardship
£451/Ha
What protection regulations are in place for aincient woodland?
NPPF paragraph 180(c) - planning should be refused unless wholly exceptional reasons and suitable compensation
What is the TPO removal process
Application to the LPA under Town and Country Planning (tree removal)(England) Regulations 2012
Part 4-includes plan and statement for application
8 weeks
What are the three types of environmental permit
Standard Rules
Exemption
Bespoke Permit
What is the legislation for the Permit at River Trent?
The Environmental Permitting (England and Wales) Regulations 2016
What is the penalty for not getting an environmental permit
A fine or Imprisonment for up to 5 years
What is the process for getting a Natural England consent
1- Fill in consent notice form - SSSI details, FG/Exolum details, description of works (vehicles, access route, locations, ground pressures for bogs etc), removal of spoil, proposed dates
2- Send completed form to Protected Sites
3- Await response - NE aim for 28 days but could take up to 4 months. NE will assess the carrying capacity of the site - can it sustain the activity without significant negative effects
4- You have 2 months to apply to Defra to appeal the decision
What list shows can restricted activities on a SSSI?
The unique site’s ORNEC list
Operations requiring natural England consent