1
Q
What would we use if PMS was to fail?
A
> The Reversionary Panel. It provides limited, hard-wired, control & indication facilities in the event of PMS Failure
2
Q
Follow up actions for a total loss of PMS are?
A
> SM close up at Diving Stations
Monitor & Control systems using Hard wired controls & indications if available (Reversionary panel)
Local control of systems be required
3
Q
The electrical audit card consists off?
A
> Location of one or more compartments
Numerical list of equipment or lighting
A tick box if equipment has failed
Name of auditor & ID of the Audit