LO8 Schedule and Resource Flashcards

1
Q

2 differences between critical path and critical chain techniques

A
  1. They differ in the way they manage and display contingency.
  2. They differ in the way that expectations are set over the completion of activities.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Network diagram

A

Derived by inserting logical relationships between activities from WBS.
Estimates entered onto diagram allowing start and finish (early and late times)
Total float calculated for each activity (late start or finish - early start or finish)
Critical path determine - continuous path through network.
Updated with actuals during implementation.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Schedule - optimise and baseline

A

Schedule reviewed by stakeholders to ensure realistic and deliverable.
May need several iterations.
Once agreed, schedule is baselined - used to measure progress and change.
May need to be re baselined following major approved changes.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Schedule - update timescales with actuals

A

Dynamic document - what has been done and forecast what is still to be done.
Mechanisms in place to gather progress data in agreed / timely way
Finished tasks shown as 100% complete. Update incomplete tasks.
Forecast completion.
Impact of delays on subsequent activities, critical path, free and total float and end date aid forward planning and recovery.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

2 different categories of resource

A
  1. Fixed cost - single cost attached to activity or spread across lifecycle. Certainty - known and agreed.
  2. Human resources / labour - use RAM / RACI. Allocated based on skills / work required. Add to schedule and smooth / level.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

3 things that need to be considered when allocating resources to a schedule

A
  1. Time to obtain resources
  2. Amount of resources needed (resource demand profile histogram)
  3. The cost of resource (appropriate quality / training / qualification)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Differences in funding (linear vs iterative)

A
  1. Phase v sprint based
    Iterative - more frequent review, more prone to failure (supports governance)
  2. Different funding priorities
    Iterative - constant expenditure (people costs)
    Linear - S-curve, increased resources from planning to implementation.
    Add contingency.
  3. Estimated costs vs fixed costs
    Iterative - fixed (but may not deliver all requirements)
  4. High change budget vs low change budget
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Considerations - resource levelling vs smoothing

A
  1. Amount of float available
  2. Importance of end date
  3. Amount of resource available
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Resource Smoothing

A

Time Limited
Maintain schedule - add resources.
Realign tasks where they can be moved without impacting overall duration.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Resource Levelling

A

Resource Limited
Modify schedule dates to stay within specified resources available as first priority.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

3 things to consider when maintaining a schedule

A
  1. Measurement of progress
  2. Whether schedule is realistic (based on performance to date)
  3. Impact of under or over performance
How well did you know this?
1
Not at all
2
3
4
5
Perfectly