Level 3 Questions - SCB BMS Upgrade Contract Selection Process Flashcards

1
Q

What was the CDP element of works on the BMS upgrade project?

A

The contractor was asked to design the control systems for the BMS upgrade

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Why did you not advise to go down a design and build route?

A

.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Why did you make your recommendation for a minor works contract?

A

The Project:

  • The works were of simple character
  • Low value project - £500,000
  • Programme less than 12 months

Procurement:
- Suited a traditional form of procurement

Contract:

  • Simple to administer
  • Speed of getting in to contract
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Why did you make your recommendation for an intermediate contract?

A

The Project:

  • The works were of simple character
  • Low value project - £500,000
  • Programme less than 12 months

Procurement:
- Suited a traditional form of procurement

Contract:

  • Allowed for sectional completion
  • Allowed for advanced payment
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What’s the main differences between a Minor Works contract and an Intermediate?

A

Client control:

  • QS not required in a MW
  • Clerk of works not provided for in MW

Commencement and completion:

  • Sectional completion not provided for in MW
  • Partial possession not provided for in MW

Variations:

  • Detailed rules not in MW
  • Both IC and MW dont have schedule 2 quotation

Payment:
- Advanced payment not provided for in MW

Insurance:

  • Option A - both IC and MW
  • Option B - Only IC
  • Option C - both IC and MW

Warranties:

  • Collateral warranties not in MW
  • Third party rights not allowed for in IC and MW
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Why didn’t you go for a Standard Building Contract?

A
  • Typically used for large or complex projects

- Given the scale of the works, it was not a requirement

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

How did you advise on contract selection?

A

Issued a recommendation in a procurement report formally issued to the client

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What documents did you refer to when providing advice on contract selection?

A

JCT Practice Note - Deciding on the appropriate JCT contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is sectional completion? Why did the client want to complete the work in sections?

A

.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

If the decision was to go to sectional completion, what was the method of delivery beforehand?

A

.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

If the project was a BMS upgrade, why did you advise a minor works / intermediate if the works are specialist?

A

.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly