Level 3 Questions - SCB BMS Upgrade Contract Selection Process Flashcards
What was the CDP element of works on the BMS upgrade project?
The contractor was asked to design the control systems for the BMS upgrade
Why did you not advise to go down a design and build route?
.
Why did you make your recommendation for a minor works contract?
The Project:
- The works were of simple character
- Low value project - £500,000
- Programme less than 12 months
Procurement:
- Suited a traditional form of procurement
Contract:
- Simple to administer
- Speed of getting in to contract
Why did you make your recommendation for an intermediate contract?
The Project:
- The works were of simple character
- Low value project - £500,000
- Programme less than 12 months
Procurement:
- Suited a traditional form of procurement
Contract:
- Allowed for sectional completion
- Allowed for advanced payment
What’s the main differences between a Minor Works contract and an Intermediate?
Client control:
- QS not required in a MW
- Clerk of works not provided for in MW
Commencement and completion:
- Sectional completion not provided for in MW
- Partial possession not provided for in MW
Variations:
- Detailed rules not in MW
- Both IC and MW dont have schedule 2 quotation
Payment:
- Advanced payment not provided for in MW
Insurance:
- Option A - both IC and MW
- Option B - Only IC
- Option C - both IC and MW
Warranties:
- Collateral warranties not in MW
- Third party rights not allowed for in IC and MW
Why didn’t you go for a Standard Building Contract?
- Typically used for large or complex projects
- Given the scale of the works, it was not a requirement
How did you advise on contract selection?
Issued a recommendation in a procurement report formally issued to the client
What documents did you refer to when providing advice on contract selection?
JCT Practice Note - Deciding on the appropriate JCT contract
What is sectional completion? Why did the client want to complete the work in sections?
.
If the decision was to go to sectional completion, what was the method of delivery beforehand?
.
If the project was a BMS upgrade, why did you advise a minor works / intermediate if the works are specialist?
.