Extensions of time / loss and expense Flashcards

1
Q

What is an extension of time?

A

Extension on the date of completion due to the occurrence of a relevant event

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is the process of an EOT?

A

1) Contractor notifies CA of EOT as soon as reasonably apparent + details on cause / effect
2) CA assessment
3) CA notifies PC as soon as reasonably apparent but within 12 weeks

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is a relevant events?

A

A delay which impacts the completion date not caused by the fault of the contractor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What are some examples of relevant events?

A
  • Variations / instructions
  • Deferment of giving possession of site
  • Antiques found on site
  • Exceptionally adverse weather
  • Works by statutory undertakers
  • Force majeure
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What counts as Exceptionally adverse weather?

A

Exceeding the long term average for that time of year / location

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is the time frame for a contractor to raise a relevant event?

A

As soon as reasonably apparent

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is a Relevant Omission?

A

Omission of any work or obligation through an instruction for a variation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is Concurrent Delay?

A

Where contract delay and employer delay occur at the same time, need to assess in detail to see which arose first

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is Loss & Expense?

A

Contractor can claim direct loss and / or expense as a result of the progress of the works being materially affected by a relevant matter

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Process of Loss & Expense?

A

1) Contractor gives written notice as soon as reasonably apparent with cause + effect
2) CA assessment
3) CA has 28 days to respond and 14 days per subsequent monthly update

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is a Relevant Matter?

A

A relevant matter is a matter for which the client is responsible that materially affects the progress of the works.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Examples of Relevant Matters?

A
  • Failure to give the contractor possession of the site
  • Delays in receiving instructions
  • Opening up and testing works
  • Discrepancies in contract documents
  • Issues relating to CDM
  • Disruption caused by works being carried out by the client
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What’s the difference between a Relevant Event and a Relevant Matter?

A

Time and cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What are the common heads of claim in Loss & Expense claims?

A
  • Prolongation
  • Thickening of preliminaries
  • Disruption
  • Head office / administration costs
  • Acceleration costs
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is force majeure?

A

Events that are beyond reasonable control of a party, such as war or an epidemic

How well did you know this?
1
Not at all
2
3
4
5
Perfectly