Construction Security and Performance Documents Flashcards
What is a Bond?
Bonds are means of protection against the non-performance of the contractor. They are an undertaking by a bondsman or surety to make a payment to the client in the event of non-performance of the contractor.
Intends to encourage performance
Typically expire on PC date
Cost of the bond usually borne by the contractor, although likely to be reflected in their tender price
Rules of Bonds?
Must be in writing and in the form of a deed
Duration depends on the terms given by guarantors
Financial limit of liability are expressed in the contract of guarantee
What are “On Demand” & “Conditional” Bonds?
On Demand
• Value of bond can be raised straight away
Conditional
• Requires the client to provide evidence that the contractor has not performed their obligations under the contract and that they have suffered loss as a consequence
What types of bonds are there in construction?
- Performance bond
- Advanced payment bond
- Off-site materials bond
- Retention bond
- Defects liability bond
- Adjudication bond
What is a performance bond?
A bond that insures a client against the risk of the contractor fulfilling contractual obligations to the client
Typically set at 10% of the contract value
Cost of the actual bond is typically 1% of contract value (dependant on financial stability contractor)
Usually Conditional
Section 7 of JCT
Example would be if contractor went insolvent, the bond would finance the employer to re-tender the works
What is typically included within a performance bond?
Parties names (Contractor / Guarantor / Employer)
Background (refer to contract, the works, limitations)
Deed witnessed (guarantor guarantees to the Employer that in the event of a breach of the contract by a contractor or termination of the employment of the contractor)
Maximum aggregate liability of the guarantor and the contractor under the bond
The laws that govern bond e.g. England and Wales
Benefit of the contract may be assigned to the guarantor
Company numbers & addresses (contractor / guarantor / employer)
Bond Amount
Expiry date of bond e.g. date of issue of certificate of making good defects
Execution as a deed
Disadvantages of “On Demand” Performance Bond?
More expensive to client
Negative impression on contractor
Parent Company Guarantee can sometimes be better as Parent company can step in and fulfil all of obligations of the insolvent contractor
What is an advanced payment bond?
Schedule 6 Part 1 OR Contract Particulars 4.6
If the client agrees to make an advanced payment to the contractor (e.g. where the contractor incurs significant start up and procurement costs before construction begins) a bond may be required to secure the payment against default by the contractor.
Usually on Demand
Taken out by Contractor
What happens if the Bondsman disputes the amount?
If the guarantor refuses to pay because it disputes the actual amount, it will be liable for interest and costs as a result of it’s delay.
What is an Offsite materials bond?
Schedule 6 Part 2 OR Contract Particulars 4.15.4 / 5
It can sometimes be appropriate for the client to pay for items even though they remain off site e.g. plant or materials.
Bond secures payment against default by the contractor
Usually on demand
Usually up to the value of the materials offsite, with the value of the bond reducing as deliveries to site are made
What is a defects liability bond?
Can be used to ensure that the contractor continues to provide services rectifying defects that become apparent after PC has been certified.
Usually on demand
What is an adjudication bond?
Can be used to ensure that the contractor continues to provide services rectifying defects that become apparent after PC has been certified.
Usually on demand
What is a Retention Bond?
Schedule 6 Part 3 OR CP 4.17
Retention bonds are way of avoiding problems associated with retention recovery.
Amounts that would otherwise have been held as retention are instead paid, with a bond being provided to secure the amount.
Contractor pays for bond but usually reflected in their tender price
Bond must be increased for variations during the project. If not increased during the project, then the % percentage can be taken against variations through interim valuations
Similar to retention, the bond’s value will usually reduce after the certification of practical completion.
Why may a retention bond be used?
May be used in difficult market conditions to aid the contractor’s cashflow
Disadvantages of retention bond?
Employer pays a premium on taking out the bond
Harms the employers cashflow
May reduce the contractor’s incentive to complete works to a good standard and promptly