General Contract Practice Questions Flashcards
What is a contract?
- A contract is a legally enforceable agreement between 2 or more parties.
- It may be oral or written
- A contract is essentially a set of promises to do something for the other in exchange for a benefit
What 5 things must a contract have to be legally binding?
- Offer and acceptance (one party to make an offer to another)
- Consideration (parties must exchange some value for the contract to be binding)
- Capacity (the ability to understand the terms of any obligations under the contract)
- Intention (clear that the parties intended to enter in to a legally binding contract)
- Legality
What is the law of tort?
- law which deals with civil wrongs (such as negligence)
What are the elements of the law of tort?
1) Negligence (a party was found to be negligent)
2) Duty of care (the negligent party owed a legal duty of care to the victim)
3) Breach of duty (the defendant breached the legal duty of care)
4) Causation (once (3) is established, the causation must be proved)
5) Harm or injury (as a result of (4) there was loss / damage / injury)
What are the 2 remedies in tort law?
- Damages
- Injunction
What are the categories of tort?
- Intentional (e.g. hitting someone)
- Negligent (e.g. causing an accident by failing to obey traffic rules)
- Strict liability (e.g. making and selling a defective product)
What do you know about the term “Heads of Claim”?
- The term heads of loss or heads of claim refers to categories of damage that a party may incur.
- It uses the term “head” in its sense of category, each head is a category
What is a simple contract?
- Contract that is signed under hand by both parties
* Limitation period of 6 years
How can a contract be executed?
- By Hand
- By Deed
- Oral
What is Novation?
- Contractual rights and obligations are transferred from one party to another
- Normally associated with D&B where…
- Alternative is a “Consultant Switch” - initial appointment ends at the point of the new appointment beginning
What is a Contract Under seal?
- Signed by the parties, witnessed and most importantly made clear that it is executed as a deed
- Limitation period of 12 year
How many sets of contract documents would you usually produce?
Usually 2 (1x set for client signature, 1x set for suppliers)
What is a consultant switch?
- an alternative to novation
- instead of a partys obligations being transferred from one party to another, its where one agreement ends and another begins
What is a letter of intent?
- A document expressing an intention to enter into a contract at a future date but creating no contractual relationship until that future contract has been entered into.
- NOT an agreement to enter into a contract
- Can be used as an interim arrangement to mobilise construction prior to a formal contract being executed
- Should NEVER be seen as an alternative to a contract
- Should place a limit on expenditure & client’s liability prior to the contract being put in place
What should generally be included within a letter of intent?
- Acceptance of the contractors offer and definition of the project
- The agreed contract sum
- Reference to tender documents and subsequent amendments
- Instruction to proceed on a certain date
- Site possession date / PC date
- Description of the proposed form of contract, any amendments, collateral warranties, performance bonds, PCGs, etc
- How the contract will be executed
- Dispute resolution procedures
- Terms for cancelling the letter
- Rate of LDs
- CAP ON EXPENDITURE
Under a letter of intent, how is access to the site given to the contractor?
Under a license
What are the types of letter of intent?
- Comfort letter
- Instruction to proceed with consent to spend
- Recognition of the existence of a binding contract
What is a ‘comfort letter of intent’?
Gives assurance about financial stability to parties (such as a lender) that will in turn give the assurance that the obligation will be met
The receiving party will typically be a lender, who are given the comfort letter before credit is granted by them to fund the project
What is ‘an instruction to proceed with consent to spend letter of intent’?
Where the employer reimburses the contractor of reasonable costs
What is a ‘recognition of the existence of a binding contract letter of intent’?
Used to execute the contract before signing it (e.g. Director away).
What are the dangers of a letter of intent?
- Not as robust as a formal contract
- Allows the contractor a position of re-negotiation of the contract sum (for example unknown ground risks)
- A letter of intent may act as a disincentive to execute a formal contract
What is a purchase order?
- a document issued from seller to buyer indicating their intention to purchase goods / services
- used to control procurement from suppliers and kept as records of this
- Once a supplier accepts the purchase order, it is legally binding
What information would you typically find in a purchase order?
- PO number
- Description of the product/service being purchased
- Technical details
- Quantities
- Any discount if required
- Agreed prices
- Payment terms
- Shipment dates
What goes in to contract documentation?
- Contract
- Contract amendments
- Pricing document / contract sum analysis
- Preliminaries
- Design and specifications
- Employers requirements / Contractors proposals
- Tender addendums
- Performance bonds / PCG
- Bonds
- Collateral warranties
What are the typical sections within a contract?
- Articles of agreement
- Articles
- Recitals
- Contract particulars
- Attestation
- Contract conditions
- Schedules
What are the articles of agreement?
Set out the core obligations between the parties
4 sections - what are they?
What are articles?
Set out what is agreed between the parties
Articles 1-9 in both SBC and D&B:
- Defines contractors obligations
- States contract sum
- Identifies parties involved
- Right to adjudication / arbitration
- Legal proceedings
Articles 10-12 in both SBC and D&B:
- States the immediate affect of amendments
- Schedule of amendments
- Amendment 1 (for 2011 contracts)
- Contract supersedes all previous agreements
What are recitals?
Contextualise the agreement, giving factual explanations for the basis of the contract
Examples of recitals in standard building contract:
- Recital 1 - Describes work / site
- Recital 2 - Identifies design info / ERs
- Recital 3 - Identifies pricing option (A or B?)
- Recital 4 - CIS, employer a contractor?
- Recital 5 - Information release schedule
- Recital 6 - Sections
- Recital 7 - Framework agreement supplementation?
- Recital 8 - Supplemental provisions 1-6 & 9
What are the contract particulars?
Sets out the aspects of the contract that are particular to the project to which the contract relates
Split in to two parts
- Part 1 - General
- Part 2 - Third party rights and collateral warranties
Examples of contract particulars include:
- Base date
- Dates for possession / completion of sections
- Rates of liquidated damages
- Rectification period
- Method of payment
- Advance payment
- Retention percentage
- Contractors retention bond
- Fluctuation options
- Daywork
- Insurance / PII
- Joint fire code
- Period of suspension
- Adjudication
What is attestation
- confirming something is genuine
- signature, oath or other forms of certification
What is an information release schedule?
If not all the information required to construct the works has been prepared or issued when the tender documentation is issued, or the contract executed, then an information release schedule may be prepared which gives dates for the release of information from the consultant team
What are the conditions of a contract?
Set out the legal principle relationships between the parties to a construction contract, determines the allocation of risk
9 Sections:
- 1 - Interpretations and definitions
- 2 - Carrying out the works
- 3 - Control of the works
- 4 - Payment
- 5 - Variations (SBC) / Changes (D&B)
- 6 - Injury, damage and insurance
- 7 - Assignment, Performance bonds and guarantees, third party rights and collateral warranties
- 8 - Termination
- 9 - Settlement of Disputes
What are schedules?
Detailed procedural rules for certain situations
- Schedule 1 – CD submission procedure
- Schedule 2- Variation and acceleration quotation
- Schedule 3 – Insurance options
- Schedule 4 – Code of Practice
- Schedule 5 – Third party rights
- Schedule 6 – Form of bond
- Schedule 7 – Fluctuations options
- Schedule 8 – Supplemental provisions
Explain schedule 8 supplemental provisions
Additional provisions that can be included to the contract
D&B has 10, SBC has 9
The difference is DB does not have a schedule 2 quotation therefore the need for the valuation of changes is included (with associated timescales)
Examples:
- collaborative working
- Health and safety
- Cost savings and value improvement
- Sustainability / environment considerations
- Performance indicators and monitoring
- Notification and negotiation of disputes
- Transparency
- The public contracts regulations 2015
- Named specialists
What is the base date?
- a reference date from which changes in conditions can be assessed
- JCT recommends 10 days before tender return
- Sets a reference point from which the conditions of the tender was prepared
What are contra claims?
Claims from third parties as a result of the contractors operations
Typically resulting from the contractor’s negligence or contractual breach
Example: flooding a neighbours property
What is a contract sum?
The amount originally set out in the contract to be paid to the contractor for completion of the works
What is Retention?
- A percentage of the amount certified to be paid to the contractor which is retained by the client
- A form of security
- Retained to ensure that the contractor properly carries out the activities required of them under the contract
How is Retention Held?
The employer deducts retention. The contract states the following: ‘…the Employer’s interest in the retention is fiduciary as trustee for the Contractor (but without obligation to invest)’.
The contractor can request that the monies are held in a separate bank account to comply with the above statement (unless the employer is a local authority)
The employer benefits from interest earned on this account
What happens if the Client had spent the money or will not pay the retention?
- If retention is due to the contractor, then the client has a contractual obligation to pay
- If they do not pay they are in breach of contract
- Contractor can exercise dispute resolution techniques as listed in the contract
What is the default retention in the JCT form of contract?
MP - 0%
SBC and D&B - 3%
IC and MW = 5%
Why may a Contract Sum need to be adjusted when it comes to Final Account?
- Variations
- Fluctuations
- Prime Cost sums
- Provisional sums
- Payment to nominated sub contractors
- Statutory fees
- Loss & Expense
- LD’s
When is retention released?
50% upon completion and 50% released at the end of the defects liability period (final certificate)
What is included with Retention?
- Preliminaries
- Measured works
- Variations
- Materials on site
- Materials off site
What is excluded with Retention?
- Insurance
- Statutory fees and charges
- Costs relating to patent defects
- Cost of opening up the works and testing the works
- Loss and expense
- Fluctuations
What happens if the contractor fails to return during the rectification period?
Retention money can be used to fund the payment by others to correct the defects
Relevant notices should be given to the incumbent contractor prior to appointing others to carry out the works
What is the Joint Fire Code?
- Contract Particular 6.14
- Refers to fire prevention on construction sites
• The Joint Fire Code covers activities through all
stages of design, procurement and construction.
- Published in 1992 by the Fire Protection Association due to concerns from insurers regarding fire’s on construction sites
- Applies if value of more than “£2.5 million”
- Can apply to project with lower value if considerable fire risk
- Is a “Large Project” if value is over £20 million
Provisions of Joint Fire Code?
Contractor must provide: • Hand bells, whistles & klaxons • Security guards • Fire signage • Fire doors • Water supplies • Portable fire extinguishers • Where it is a large project, the contractor must provide an appropriate number of fire marshals
What happens if the contractor does not comply with Joint Fire Code?
- Non-compliance can invalidate insurance, contractor should always carry out remedial works to ensure compliance
- Cost of compliance should be stated in contract
1) CA issues notice to comply
2) If the contractor does not carry out remedial work within 7 dyas, the CA can issue an instruction for the employment of someone else to carry out remedial works
3) CA can deduct cost for remedial works from amount due to contractor via a payless notice
What is the most recent version of the Joint Fire Code and what changes came about?
9th edition published in 2015
- Included fire prevention checklist
- Updates to on-site fire precautions
- New emphasis on the need to conduct periodic reviews of fire safety
- Changes to reflect CDM 2015
- Guidance on the installation of PV’s
- Changes to hot work permits
What are fluctuation options?
- Provisions within the contract to deal with the effects of inflation
- Typically applied to larger projects with a longer programme
- On smaller projects, the contractor would be expected to factor in inflation within their tender price
- On larger projects, the contractor may be asked to base their tender price on current market rates, and then the contract will make provisions for the contractor to be reimbursed for price changes to specified time items over the duration of the project
Under JCT 2016 what are the different fluctuation options?
Option A – Contribution, Levy and tax fluctuations
Option B – Labour & Material cost and tax fluctuations
Option C – Formula adjustment
Option A is found in Schedule 7 of contract. Options B & C are no longer included within the contract but can be applicable through the contract particulars.
What is the procedure of fluctuations options?
1) Check contract for entitlement
2) Contractor to notify CA / EA in writing
3) Contractor must provide relevant info and calculations relating to the adjustment
4) Should be adjusted via an interim certificate