Level 3 - Cashflow Forecasting Flashcards
How did you go about preparing your cashflow forecast for Devonshire Row?
I used indicative stage 3 programme from the EA
Split the cost plan (formal cost plan 2) works elementally across the programme which indicated a ‘S curve’ in expenditure
What would you advise the Client on a project where actual payments are behind the anticipated forecast?
Could be a number of things - I would discuss with the contractor first to find out reasons and report back to the client
This happened on Devonshire Row, I advised the client that this indicated the project was in delay and a potential risk to the overall completion date.
What are some other causes of contractor being behind on cashflow?
The cashflow was wrong in the first place
- Works being omitted
- Resequencing of the Works
- Lots of variations Changes
- Inaccurate Cashflow
- Materials not being delivered in time
- Materials behind stored offsite and not claimed for
If the cash flow was ahead of schedule what could this indicate?
- Ahead of programme
- Contractor front loading costs
- Resequencing (higher value works carried out earlier)
- Inaccurate cashflow
- Advanced payments
- Materials offsite not taken into account when preparing cashflow
- Materials being stored on site way before they’re required
- Variations
- Acceleration (to complete works earlier
What is the purpose of a cash flow forecast?
Pre contract Tells client how much money they will be spending on a monthly basis.
Post contract Helps the client drawdown funds from funders / creditors. Helps the client to understand whether the contractor is ahead or behind the programme. Helps the client understand how much money is being spent in relation to anticipated cash flow.
Why is it important to have a cash-flow?
Outlines anticipated expenditure
Gives an indicated of when funds are required
How was the cash flow produced post contract?
The contractor produced the cashflow post contract using their programme and CSA and splitting works into the appropriate months. They then deducted the retention each month to give a net cumulative total. I then reviewed it and agreed it with them.
How did you update the cashflow forecast in every monthly cost report?
Cumulative net amount paid till date and then minus the retention
Updated the cashflow forecast taking this into account
Continuously compared actual cash flow to predicted cash flow to predicted cashflow forecast in every updated cost report using a line graph.
When might you adjust the cash flow forecast?
to reflect EAIs reflect anticipated variations reflect loss and expense reflect prov sums reflect risk allowances
What’s the risk of using a PM programme when preparing a cashflow?
Inaccurate sequencing of the works, contractor might have different methodology.
Cash flow forecast should be updated when entering in to contract and based on the contractors programme
Why is it important that the contractor prepared the cashflow rather than you preparing one?
They are more aware of how works will be sequenced and therefore should be more accurate
How often was the cashflow updated?
Monthly to reflect actual expenditure and post contract changes
Should also be updated to reflect any large variations / provisional sums
You mentioned you advised the client that the contractor was delayed due to cashflow indicating they was behind, would this be your first action / advise to the client if cashflow is behind?
I would discuss with the contractor before making any assumptions
Could be number of things
1. Works may be omitted
2. Sequenced
3. Lot of changes Variations
4. Inaccurate baseline cashflow
On this project it was clear the contractor was progressing much slower than anticipated
What is the issue for the client is actual payments are ahead of cashflow?
Potential funding issues
You had a variations tracker, was variations included in the cashflow?
Yes, I would ask the contractor to update cashflow if:
• They wasn’t progressing diligently – ie behind programme
• To reflect EAI
• To reflect Anticipated Changes
• Loss & Expense
• Changes to provisional sums