Level 1 - Cost Reporting GN Flashcards

1
Q

How do different procurement routes affect a cash report structure?

A

Lump sum contracts track lump sum and adjustments

Construction Management will track CM fee and separate contract sums and adjustments for all trade packages

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is the structure of a cost report?

A

D&B Lump sum

Contract Sum 
Adjustments for provisional sums
Adjustments of variations 
Adjusments for Loss & Expense 
Adjusment for risk allowances
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

How often should a cost report be updated?

A

Monthly (as per valuations) unless another frequency is required by the client

How well did you know this?
1
Not at all
2
3
4
5
Perfectly