Lessons Learned from 3 past Exams Flashcards
Anything that includes “May”
Is Attached to Risk
Risk Register: A list positive & negative risks project, responses.
Project started a new phase , they have complied a list of issues that were solved where they should save it?
In the OPA
Once a phase is done update the OPA
In case a project manager discovered not feasible feature within the project so he highred different resource
Avoiding risk in this case
Avoid is the process of eliminating the risk
When the PMO Outsources development tasks what should the PM do?
Review the Procurement Management Plan
When it is getting diffcult working with a customer for being stubborn what should the project do?
Meet with the client to review the ground rules
When the Project Manager needs to understand how customers will use this product?
Focus Group
It gather feedbacks from actual customers
When a stakeholder is not willing to cooperate and meet with project manager. What should the project manager do?
Review the project Management plan since it has the communication management plan and stakeholder engagement plan
The PM is doing the following:
* Conducting a cost analysis based on high level scope
* Using an expert Judgment to make a document
The Project Charter:
* High level document
* Has high level scope and budget
The Project is in the execution phase with an approved plan,Correcting the issue “May” cause:
* Increase in scope
* Costs
Remeber “May”
Conduct Risk analysis
Analyze before the change
A new product that is not done before in the organization what should the PM to collect the requirments
- Expert Judgement
- Prototypes
The PM is working on a virtual project with a “Scheduling Priority conflict” among team members what he should do in this case?
He should uses Collaborate/Problem solving technique
Win-Win situation
It is important to clairfy to the team members change terms after execution terms?
Teach them about change request principle
The Project is agile and the PM found their will be an issue with a vendor and the product will be shipped late, What should the project Manager do in this case?
Add this to issue log and meet with team to brainstorm solution
List of all issues on the project.
A customer asks the project manager for a new product feature during a meeting , what document should the project manager refer to find change request authority?
Change Management Plan
Descripes the process for submitting and evaluating change
The PM assigned new project and the PMO has given him a list of all stakeholders what should the PM do?
Stakeholder Analysis
it is done before stakeholder register
PM working on new project a natural disaster occured and had major schedule issue and delayed project which might affect the budget and scope?
- Use Compression technique to shorten the schedule
- Implement a Fast-tracking method on the schedule
A project Manager that deals with a vendor, the vendor missed a major component of a deliverable. After having one-on-one meeting the PM understands the issue, What should the PM do in this case?
Review the risk register & Implement the risk response
Since the risk has materilazed next implement the risk
The agile team has completed two sprints so far. The team is about to conduct the sprint planning meeting for the 3rd sprint?
**Sprint goals **are clear objectives set before the beginning of a sprint. They are set by the product owner and delivery team collaboratively.
- A development team is creating a new website. The team needs to identify what are the visual requirement for the site.
What is an appropriate** tool or technique** to use for this situation?
Focus groups organize stakeholders and subject matter experts to learn about their expectations and attitudes about a product.
A client brings a project manager onto a project during the project’s execution stage. The project manager reviews the project scope for cost estimating purposes and notices that some deliverables were missed in the work breakdown structure (WBS).
Which step should the project manager take next?
Include the work in the WBS and** recalculate** the total project cost.
The Project Manager invites team members to a meeting to create a document that will guide the team in defining the main project objectives.
What will be the final output of this meeting?
The scope management plan is a component of the project management plan that describes how the scope will be defined, developed, monitored, controlled, and validated.
A network implementation project has just been executed. The plan is approved and the work has started. Quality is the most important part of this project.
The best answer here would be to** review the work on a regular basis**, this would ensure work is getting done according to plan
A Project Manager is preparing to develop a new product for a company. The new product will require a potential law change in order to be sold. The law is pending approval.
To initiate this project, what should the Project Manager do?
The risk should be listed in the project charter, so its impact can be analyzed before project initiation.
An organization has moved from traditional to** agile methods** and is now conducting its first agile project. The newly appointed product owner would like the team to prioritize the features as soon as possible so they can start the sprints immediately.
What should the project manager do in this scenario?
Educate the product owner on the benefits of having him prioritize the features
product owner to prioritize the features store them product backlog.
A smartphone company reports that customers are complaining that a new phone is very slow to boot, while others are saying it boots times are okay. A Project Manager needs to determine if something needs to be changed during the production of the smartphone.
Which tool or technique can the Project Manager use for this?
Control charts are used to determine whether or not a process is stable or has predictable performance.