Drag and Drop Control Cost Continue Flashcards

1
Q

Amount of money you already spent on the Project

A

AC: Actual Cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Amount of money worth of work that should done on the project

A

PV: Planned Value

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

The rate of how much we are spending to actually earning on the project

A

CPI: Cost Performance Index

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Original Budget of the Project

A

BAC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

The Difference between the work done and Money spent

A

CV: Cost Variance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly