Lecture 8 - Subcontract Agreements Flashcards
subcontracts should never be signed before the______ _____ is signed
prime contract
With subcontractors, the contractor needs to know with whom it is dealing as to
(1) reputation,
(2) financial resources
(3) experience and qualifications
(4) union versus non-union status
a______ ______ could be more expensive if it is unable or unwilling to do the work.
low bidder
a ____ ______ is still fully liable for the subcontractors work
prime contractor
What should a subcontract contain? (Red Flag provisions)
(1) a description of the project, and identification of the
(2) owner
(3) designer
(4) owner’s field representative
(5) contractor
(6) subcontractor
If the work is a section of work specified in the prim contract, the subcontract may refer to the _______ _____ and the applicable sections of the specifications.
plan pages
The subcontract should clearly state the basis of measurement of the subcontractor’s work, the ________ _______, and the rules (such as work hours, cleanup expected, etc.).
payment procedures
Most subcontracts have “________” and retention provisions permitting the contractor to hold some of the subcontractor’s money (actually the owner is holding it) to secure the quality and timeliness of the subcontractor’s work
“no-pay-until-paid”
It must be written into the purchase order and the subcontract because it is not provided for the in the contract and therefore cannot be flow-down language
“no-pay-until-paid”
Most state laws provide for payment to the subcontractor within _____ to ____ days after the contractor has received payment from the owner.
seven to ten days
The subcontractor must work within the overall contract schedule. It is controlled by the ________ and it must be reasonable. A rough schedule should be provided to the subcontractors when subcontract bids are requested
prime contractor
T/F: changes can result in adjustment to the schedule
True
Explain the Texas Case
the subcontractor was understaffed so the prime contractor took over the work to avoid delays.
Explain the Idaho Case
the prime contractor tried to force the subcontractor to work during inclement weather and the subcontractor refused. When the subcontract was terminated by the prime contractor, the subcontractor sued. The subcontractor won, with punitive damages because the prime contractor falsified records
liquidated damages are owed by the ________ for liquidated damages charged to the prime contractor caused by the subcontractor.
subcontractor