Lecture 8 - Subcontract Agreements Flashcards

1
Q

subcontracts should never be signed before the______ _____ is signed

A

prime contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

With subcontractors, the contractor needs to know with whom it is dealing as to

A

(1) reputation,
(2) financial resources
(3) experience and qualifications
(4) union versus non-union status

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

a______ ______ could be more expensive if it is unable or unwilling to do the work.

A

low bidder

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

a ____ ______ is still fully liable for the subcontractors work

A

prime contractor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What should a subcontract contain? (Red Flag provisions)

A

(1) a description of the project, and identification of the
(2) owner
(3) designer
(4) owner’s field representative
(5) contractor
(6) subcontractor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

If the work is a section of work specified in the prim contract, the subcontract may refer to the _______ _____ and the applicable sections of the specifications.

A

plan pages

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

The subcontract should clearly state the basis of measurement of the subcontractor’s work, the ________ _______, and the rules (such as work hours, cleanup expected, etc.).

A

payment procedures

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Most subcontracts have “________” and retention provisions permitting the contractor to hold some of the subcontractor’s money (actually the owner is holding it) to secure the quality and timeliness of the subcontractor’s work

A

“no-pay-until-paid”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

It must be written into the purchase order and the subcontract because it is not provided for the in the contract and therefore cannot be flow-down language

A

“no-pay-until-paid”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Most state laws provide for payment to the subcontractor within _____ to ____ days after the contractor has received payment from the owner.

A

seven to ten days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

The subcontractor must work within the overall contract schedule. It is controlled by the ________ and it must be reasonable. A rough schedule should be provided to the subcontractors when subcontract bids are requested

A

prime contractor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

T/F: changes can result in adjustment to the schedule

A

True

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Explain the Texas Case

A

the subcontractor was understaffed so the prime contractor took over the work to avoid delays.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Explain the Idaho Case

A

the prime contractor tried to force the subcontractor to work during inclement weather and the subcontractor refused. When the subcontract was terminated by the prime contractor, the subcontractor sued. The subcontractor won, with punitive damages because the prime contractor falsified records

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

liquidated damages are owed by the ________ for liquidated damages charged to the prime contractor caused by the subcontractor.

A

subcontractor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

This provision adds damages owed by the subcontractor to the prime contractor for delays (in additional to liquidated damages) if the prime contractor’s cost of performance increased as a result of the subcontractor caused delays.

A

“flow of contract”

17
Q

The prime contractor may have the right to make changes unilaterally, delay of suspend work, or terminate work in the same manner as the owner can do to the prime contractor.

A

Subcontractor changes clause

18
Q

T/F: Insurance is not required with subcontractors but required with bonds

A

False; they are with subcontractors but not necessarily with bonds

19
Q

T/F: The prime contractor wants coverage, but does not want overlaps

A

True

20
Q

increase the amount of the

subcontractor’s bid and thereby increase the prime contractor’s bid, possibly to where it is no longer the low bidder.

A

Bond premiums

21
Q

compensation for harm or loss

A

idemnification

22
Q

gives the prime contractor the right to remedy the subcontractor’s work if it is not done by the subcontractor within 48 hours of receiving notification from the prime contractor

A

48 hour provision

23
Q

gives the prime contractor the right to terminate the subcontract if the subcontractor does not rectify the problem with 72 hours of receiving notification from the prime contractor

A

72 hour provision

24
Q

T/F: If a prime contractor is bound to a labor agreement, then it must include a union labor only provision in the subcontract. This requires the subcontractor to pay union scale wages to the workers and union scale benefits to the union

A

True

25
Q

recruiting tool: the union hopes the workers will appreciate the pay and benefits increase and see the benefit of joining the union.

A

Union labor only provision