Exam 1 Flashcards
1
Q
- An item joint venture requires working capital
A
F
2
Q
- An item joint venture is when each joint venturer has a specific part of the project to do.
A
T
3
Q
- Insurance and bonds are purchased in the name of a conventional joint venture.
A
T
4
Q
- A conventional joint venture does not require working capital.
A
F
5
Q
- The participation percentage may be disproportional in a conventional joint venture.
A
T
6
Q
- Joint venturers do not have to agree on the terms of the bid in a conventional joint venture.
A
F
7
Q
- A conventional joint venture has at least one joint venturer that does work onsite
A
T
8
Q
- Joint and several liability is known as “in solido” in Louisiana.
A
T
9
Q
- A joint venture is a partnership for more than one project.
A
F
10
Q
- A joint venture is a pooling of resources, sharing risk and profit.
A
T
11
Q
- An LLC may be member managed or manager managed.
A
T
12
Q
- An LLC may select whether to be taxed as a C corporation, an S corporation, or a partnership.
A
T
13
Q
- “LLC” stands for limited liability corporation.
A
F
14
Q
- A C corporation is taxed as an entity separate from its shareholders
A
T
15
Q
- Shareholders of a corporation have liability for corporate actions.
A
F
16
Q
- A corporation has perpetual duration (until dissolved by some action).
A
T
17
Q
- A joint venture is a partnership for multiple business ventures.
A
F
18
Q
- A partnership has flow-through tax characteristics.
A
T
19
Q
- A partnership in Louisiana must be in writing.
A
F
20
Q
- The simplest form of business is the proprietorship
A
T
21
Q
- Building codes are enforced by use of permits, inspections, and testing reports.
A
T
22
Q
- The prime contractor determines the delivery method to be used.
A
F
23
Q
- The owner is the “prime contractor” when a force account (day labor) project
A
T
24
Q
- Integrated Project Delivery is the Team Approach to project delivery
A
T
25
Q
- “Fast-track” works best when the delivery method is design/bid/build
A
F
26
Q
- Construction financing is short-term financing.
A
T
27
Q
- An architect is usually the lead designer on a commercial project.
A
T
28
Q
- A material supplier may do extensive work onsite.
A
F
29
Q
- An “at-risk” agent may act as a prime contractor during construction
A
T
30
Q
- An A/E’s principal job is to be the owner’s representative during construction.
A
F
31
Q
- A subcontract should always have a 24 hour clause.
A
F
32
Q
- Subcontractors do not like “flow of contract” provisions
A
T
33
Q
- The subcontractor controls when it does its work.
A
F
34
Q
- The subcontract work must be included in the prime contract work.
A
F
35
Q
- The prime contract must exist to have a subcontract.
A
T
36
Q
- “No pay until paid” language means that the contractor does not have to pay until it has received payment.
A
T
37
Q
- A description of the project is not necessary in a purchase order.
A
F
38
Q
- Purchase orders should include “flow down” language.
A
T
39
Q
- A material supplier’s quote will have controlling language unless the purchase order states otherwise.
A
T
40
Q
- A purchase order may be used for work onsite if the work is minimal.
A
T
41
Q
- A Change Directive requires the contractor’s signature
A
F
42
Q
- A subcontractor is an entity in contract with the prime contractor to perform a portion of the Work onsite.
A
T
43
Q
- If the Architect is the Owner’s rep during construction, he or she must be onsite at all times of construction.
A
F
44
Q
- Indemnification is considered to be intermediate.
A
T
45
Q
- The Owner designates the superintendent to be used by the contractor
A
F
46
Q
- Usually the contractor determines means, methods, techniques, sequences, and procedures.
A
T
47
Q
- The Architect is the owner of the plans and spec’s even though the Owner paid for them.
A
T
48
Q
- The contractor has no rights to know the Owner’s finances for the project.
A
F
49
Q
- The Contract Documents include more than just the signed Agreement
A
T
50
Q
- The Index in the General Conditions is three pages long.
A
F
51
Q
- An “escalation” clause may be included in a short-term, lump sum contract
A
F
52
Q
- A “variation-in-quantities” clause may be included in a unit-price contract.
A
T
53
Q
- There is an implied obligation for the owner to provide access to the construction site.
A
T
54
Q
- The time provisions in a construction contract are usually measured in calendar days.
A
T
55
Q
- Contractors prefer a limited list of excusable delays in the contract
A
F
56
Q
- Usually, an owner may terminate a contract for convenience.
A
T
57
Q
- The absence of a differing site conditions clause is advantageous to the contractor.
A
F
58
Q
- The changes clause usually gives the owner the unilateral right to make changes to the contract.
A
T
59
Q
- A limited waiver of sovereign immunity is important on private (non-governmental) projects.
A
F
60
Q
- Threshold red flag clauses need to be addressed before starting estimating on a project.
A
T
61
Q
- The completed bid form is the offer.
A
T
62
Q
- In an AIA standard form contract, if there is any bias it is in favor of the owner
A
T
63
Q
- A fixed price contract holds more risk for the contractor than a cost-plus contract
A
T
64
Q
- Fast-track construction works especially well in a design-build approach.
A
T
65
Q
- If an owner contracts with an A/E for design services, the A/E is the owner’s agent in that contract.
A
F
66
Q
- The traditional approach is for the owner to have one contract with a design-build company.
A
F
67
Q
- A prime contract is any contract in which one of the parties is the contractor.
A
F
68
Q
- Cost-plus-fixed fee contracts encourage the contractor to finish quickly.
A
T
69
Q
- A cost-plus-percentage fee contract encourages the contractor to hold down costs.
A
F
70
Q
- Most negotiated contracts use a cost-plus fee arrangement.
A
T
71
Q
- A warranty period may last for more than one year.
A
T
72
Q
- An owner-caused delay may entitle the contractor to extra money and extra time
A
T
73
Q
- “Time … of the essence” means finishing late may be a material breach of the contract
A
T
74
Q
- The owner has the responsibility of providing funding for a construction project
A
T
75
Q
- The textbook covers all possible contract clauses.
A
F