Lecture 7 - Purchase Orders Flashcards

1
Q

a sale of materials for the contractor to use at the project site.

A

purchase order

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

When can a purchase order be issued?

A

any time after the contractor is awarded the contract, which is before the actual contract is signed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

is defined as a contractor under the prime contractor who does a portion of the work ______

A

Subcontractor, onsite

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

usually involves offsite work, with the finished product being delivered to the site and incorporated into the project

A

Fabrication

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

If the fabricator merely constructs the fabrication offsite and a different contractor installs it, then the fabricator is a

A

material supplier

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

If the fabricator installs the fabrication onsite, then it would be a

A

subcontractor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

if significant amounts of onsite labor are required, use a ________. Otherwise, use a ______

A

subcontract, purchase order

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

T/F A purchase order for continuing supplies may be open ended and should have an approximate quantity or maximum quantity in the purchase order.

A

True

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

a _____ will depend on the quantity estimated and may be subject to adjustment if the amount actually ordered differs

A

quote

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

should have an approximate quantity or maximum quantity

A

purchase order for continuing supplies

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

T/F You should use “boilerplate language” (A contractor’s purchase order form should specifically state the purchase order provisions control no matter what the quotation provisions are)

A

True

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

T/F A copy of the contractor’s contract should be provided with the purchase order to the material supplier, with language that the contract is incorporated by reference

A

True

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Necessary identification information: The purchase order should have

A

(1) a description of the project,
(2) the owner,
(3) the designer,
(4) the owner’s field representative,
(5) the contractor, and
(6) the material supplier.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Description of goods being purchased: The purchase order should contain either

A

(1) a complete description or

2) reference to the contract section that adequately describes the materials (flow-down language

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Shipping instructions: The purchase order should identify the

A

(1) receiving party and address (if a receiving area different the front gate for the project is used, it needs to be identified),
(2) how the materials are to be marked and packaged (very important for prefabricated materials).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Pricing and basis for quantity measurement: The purchase order should differentiate between

A

lump-sum materials versus unit price materials.

The materials need to be purchased on the same basis, unit-by-unit, as provided in the contract (flow-down language).

17
Q

2/10 net 30

A

This means that if the contractor pays within ten days of delivery, the price will be discounted by two percent, but that in any event the full amount is due in 30 days.

18
Q

T/F Provided that the contractor can afford it (paying the supplier before being paid by the owner), it should always pay early and get the discount.

A

True

19
Q

then the payment received from the owner is a condition precedent that must be met or the contractor never owes the supplier.

A

“Conditions Precedent”

20
Q

T/F If the project site has plenty of room to store the materials, the contractor may decide to receive delivery of the materials far in advance of when they may be needed.

A

True

21
Q

T/F The completion of the purchase order contract is delivery of the materials to the contractor.

A

True

22
Q

“FOB” stands for_______ and is used to determine the delivery location.

A

free on board

23
Q

means that the material supplier delivers the materials to the site, at which time the contract is completed and payment is due in accordance with the purchase order contract.
The material supplier is responsible for loading the materials onto a truck, properly marked and packaged, and delivering them to the construction site, where they are off-loaded by the contractor.
As they are off-loaded the contractor should be examining the materials as to quality and quantity. Any defective materials should be re-loaded and returned to the supplier.

A

“FOB construction site”

24
Q

means that the contractor provides for the transportation of the materials. At the supply house, the contractor inspects the materials as to quality and quantity and loads its own truck, or a third-party hauler, and delivery and off-loading at the construction site (or wherever the materials are to be stored until needed).
The sale of the materials is completed at the supply house.

A

“FOB supply house”

25
Q

If the sale is completed at the construction site, the______ is responsible for damage to the materials during transport.

A

supplier

26
Q

If the sale is completed at the supply house, the ______ is responsible for damage to the materials during transport.

A

contractor

27
Q

If a third-party hauler is used, then damages to the materials during transport would be owed by _________

A

the party responsible for the transport (who would then involve the third-party hauler).

28
Q

T/F If sales taxes are applicable (and in many states there are no sales taxes on materials being incorporated into an immovable object), then be sure to have the material supplier include them in the quote so that the contractor includes them in the estimate and bid.

A

True

29
Q

Provision in a purchase order

A

(1) dispute resolution, (2) changes (remember that the owner can change things freely and such changes can and do affect the materials to be used), (3) termination provisions (similar effect to changes), (4) provisions regarding late delivery, (5) insurance and bond requirements, if any, (6) indemnification (in case it is the materials that somehow damage the owner and representatives, and (7) escalation.

30
Q

T/F: Most contractors have their own purchase order forms

A

True

31
Q

If a supplier refuses a contractor’s form what do you do?

A

Use one of the AGC forms