Project manager often save a copy of the _________ as a _______, to allow future analysis in reference to the original plan.

A

Original Plan, or Baseline Plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

The analysis of project progress could be done in two dimensions:

A
  1. ) Time: based on the current progress, are we expected to finish the project On Time? Early? Late?
  2. ) Money (or resources): based on the current progress and the actual expenditures, are we expected to finish the project On Budget? Below? Over?
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

4 Steps of Analyzing Gantt Chart in Excel

A

Step 1: Copy the schedule onto Excel
Step 2: Calculate planned task days
Step 3: Calculate Progress (task-days)
Step 4: Calculate ratios