lecture 16 Flashcards

office standards

1
Q

what are the contractual relationships of a typical building project?

A

owner contract with architect

architect contract with civil, structural, and MEP engineers + consultants

interior designers could replace architects or consultants

interior designer also could have contract with owner

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

what can happen with some contractual relationships within a project?

A

the owner had contracts with a consultant independently

happens with engineers or geotechnical engineers

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

think of a design/bid/build
situation what contract relationships happen.

A

owner contracts with architect

owner has contracts with contractor

architect DOES NOT have contract with contractor

contractor has contractors with subcontractors

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

what is the architect responsible for:

A

the what and where of the building

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

what is the contractor responsible for:

A

the how and when of the building

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

what does the architect not have control over?

A

how the contractor chooses to build any component or part of the building

as long as the product is represented in the construction document set

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

what is the makeup of a typical project contract document?

A

bid document
project manual
construction documents
- specification and drawings
contract documents

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

5 typical phases of design and construction:

A

pre-design

design
- schematic design
- design development
-construction documents

bidding and negotiation

construction

post-construction

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

what are the key parties involved in the pre-design phase?

A

owner

architect- but alot of this work may happen prior to the designers on the project

specialist- programers

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

what activites occur during the pre-design pahse?

A

the project is defined in terms of function, purpose, scope, size and economics

building program definition

economic feasibility assessment

sit assessment and selection

governmental constraints- codes, zoning, legal issues

design team selection

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

if during the pre-design phase the architect or designer ate hired what does this intel?

A

these are additional services to the typical contractual agreement

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

what are the stages of the design?

A

schematic design

design development

construction document

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

what activites occur during the schematic design stage?

A

series of options
focus in on the character and the design qualities
generate plan, section, elevation, and model(tpicallY)
consutlt integrated is typical minimal
cost estimat
ower approval

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

what actions take place in the design develop stage?

A

engineers and consultants on board
real construction
decision making
building envelope, structure, fenestration systems, interiors and some of the finishes
cost estimate
owner approval

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

what activites occur during the construction documents stage?

A

fully develop every inch of the project in detail
the achitect/designer acts as the coordinator of all the consultants’ work
review and approve

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

what are the two parts of construction documents

A

construction drawings- quantitative
specificaitons- qualitative

17
Q

if there is a question (discrepensy) between the specification and drawing which wins?

A

specification wins out

18
Q

what do the documents with in the construction document stage do?

A

communicate to the owner in DETAIL

establish the contractual obligations

lay out the responsibilities

communicate to the contractor

bids

regulatory and financial approvals needed to proceed with construction

19
Q

CSI- Masterformat=

A

a program that provides a functional way of organizing the specifications for a given project

20
Q

CSI=

A

construction specificaiton institute

21
Q

division 01:

A

covers items that apply to ALL divisions

  • payment procedures is an ex.
22
Q

division 02-14=

A

cover the basics fo the architectual work on the project

23
Q

divion 10:

A

specialties

24
Q

division 13:

A

special construction

25
Q

pre-construction-

A

bidding and negotiation

this is the pahse during which the contractor is selected to construct the project

26
Q

what is the role of the architect or interior designer during the pre-construction phase?

A

initialize the bidding process

evaluate the bids

27
Q

What are some of the things you need to note about these documents?

A

YOU ARE not a Lawyer and should not prepare any legal documents for the owner

28
Q

bid bond:

A

ensures they have the experience, ability, and financial resources available to perform the work

29
Q

performance bond

A

the funds required to finish the work

30
Q

payment bond:

A

pay the subcontractor and supplies

31
Q

surety bonds:

A

insurance type documents used to ensure that if the contractor fails, someone else will be there to clean up the mess

32
Q

What is the role of the architect or interior designer during the construction phase?

A

review shop drawings

a review of shops for compliance with the construction documents

review of mock-ups and other submittals like material samples and product cut sheets

be the eyes and ears of the owner
- FEILD OBSERVation of the project not inspection

report found issues

review and sign-off on request for payment

respond to change orders and RFI’s

33
Q

what is the role for the architect/interior designer during the post-construction phase?

A

project closeout
- inspections
- substantial completion
- the facility is able to be occupied
- warranties
- punch list
- certificate of occupancy
final completion
- everything has been completed
- record documents, keys, equipment instructions, etc.
- certificate of final completion: allows the contractor to obtain the final payment
- contractor is no longer liable for the project outside of the warranties