Lecture 13 - Monitoring and Controlling Software Projects Part I Flashcards
What are the two areas to monitor?
- Schedule
- Cost
What are used to monitor Schedule? (2)
- Milestones
- Action items
What are used to monitor Cost? (3)
- Expense
- Staffing
- Effort
TF: Holding team meetings does not keep project on track
False. It does
TF: An effective warning system is an indicator of effective progress reporting
True
What are the 5 types of Project Status Reports?
- Current period reports
- Cumulative reports
- Exception reports
- Stoplight reports
- Variance reports
The value that compares the planned amount of work with what has actually been completed, to determine cost, schedule, and work accomplished are progressing as planned is called…
Earned value
What is “Earned” or “Credited” as it is completed?
Work
What presents an “early warning” call for corrective actions?
Earned value
What specifies many of the diverse activities in the development process?
Earned value
What outlines for the long management journey?
Earned value
What does Earned value start with?
A good WBS
The lowest level WBS elements is known as…
Work packages
What are the three components that make up a Work package?
- Scope of work to be accomplished
- Total (direct and indirect) cost
- Time frame for completion
What is the problem with a work package that is too big?
Multiple people responsible for work