Lecture 13 - Monitoring and Controlling Software Projects Part I Flashcards

1
Q

What are the two areas to monitor?

A
  • Schedule
  • Cost
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What are used to monitor Schedule? (2)

A
  • Milestones
  • Action items
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are used to monitor Cost? (3)

A
  • Expense
  • Staffing
  • Effort
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

TF: Holding team meetings does not keep project on track

A

False. It does

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

TF: An effective warning system is an indicator of effective progress reporting

A

True

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What are the 5 types of Project Status Reports?

A
  • Current period reports
  • Cumulative reports
  • Exception reports
  • Stoplight reports
  • Variance reports
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

The value that compares the planned amount of work with what has actually been completed, to determine cost, schedule, and work accomplished are progressing as planned is called…

A

Earned value

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is “Earned” or “Credited” as it is completed?

A

Work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What presents an “early warning” call for corrective actions?

A

Earned value

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What specifies many of the diverse activities in the development process?

A

Earned value

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What outlines for the long management journey?

A

Earned value

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What does Earned value start with?

A

A good WBS

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

The lowest level WBS elements is known as…

A

Work packages

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What are the three components that make up a Work package?

A
  1. Scope of work to be accomplished
  2. Total (direct and indirect) cost
  3. Time frame for completion
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is the problem with a work package that is too big?

A

Multiple people responsible for work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is the problem with a Work package that is too small?

A

Program manager winds up micromanaging everything

17
Q

slide 19

A