Lecture 11 - Software Project Scheduling II Flashcards
The amount of time an activity can be delayed without delaying the early start of any immediately following activities is called…
Slack or Float
The amount of time an activity may be delayed from its early start without delaying the planned project finish date is called…
Total Slack or Total Float
The property that determines the early start and finish dates is called…
Forward pass
The property that determines the late start and finish dates is called…
Backward pass
The amount of time a task can be delayed without affecting the scheduled start time of its immediate successor tasks is called…
Free slack
The early schedule is determined using what?
Forward pass
The late schedule is determined using what?
Backward pass
What is the critical path?
Represents how long it takes to complete a project
TF: The critical path is the longest path through a network diagram
True
TF: The critical path can have a float above 0
False. There is no float for critical path
Calculating float to determine which activities have the least scheduling flexibility is the focus of what?
CPM (Critical Path Method)
What are the three main techniques for shortening schedules?
- Shortening duration of critical activities by adding resources or changing their scope
- Crashing activities by obtaining the greatest amount of schedule compression for least incremental cost
- Fast tracking activities by doing them in parallel or overlapping them
TF: One of the purposes of Goals is to know the status of the schedule
True
TF: One of the purposes of Goals is to see factors that cause schedule changes
True
TF: Goals are not used to determine that schedule has changed
False. It is used