Lecture 11 Afsluitbrick Flashcards

1
Q

What does the Afsluitdijk do?

A

It brings safety
Connects Friesland to North Holland
Created land food and cities (Zuiderzeewerken)
* barrier that created largest fresh water serservoir in Western Europe
* Iconic landscape
* Early example Dutch Delta Design
* Not of any particular interest to politicians nor society.  vulnerability complex

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What in 2006 happened and affected the Afsluitdijk?

A

People realized that the infrastructure was ageing and that the dike needed to be strengthened.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Explain the Natuurlijk Afsluitdijk scenario

A
  • Place with water, go out,
  • Create energy
  • Superbus
  • Solar wall
  • Energy lake
  • Room to experiment
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Explain the Waddenwerken

A

Building with nature, sea defense and ecology join forces.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Explain the Afsluitdijk 21e eeuw scenario

A
  • overleaping/overtopping dam
  • combination of
    water management, sustainable tidal energy
    (pumping), ecology and recreation
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Explain the Monument in balans scenario

A

Keep the Afsluitdijk as it is, A long line of infrastructure, but redevelop the surrounding areas at both ends of the Afsluitdijk.

  • preserve characteristics
    and rhythm of the dam
  • develop the ‘halters’
  • create an ‘energy-isle’
    (to experiment)
  • Storm-shield for safety
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Explain the interests and cultures with this project

A
  • National authority:
    o Safety and icon
    o Budgets available
    o Budget and planning and risk management
    o Commitment of others
    o Strict scope/procedure
    o Slow public process
  • Regional authorities
    o Better and cheaper
    o Broad scope
    o Funding project while working
    o Fess hierarchical, able to change scopes quickly, less strict procedures
    o Slow public processes.

Local authorities
* Broad scope
* Less hierarchical
* Less experience with complex projects
* Slow public processes

Privat partners:
* Technology development
* Small companies with limited resource
* Quick decision making
* Core business is not viable business case

Semi government: like TenneT
* Slow process
* Small rigid scope
* Follow the market

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What do you need to do when you have so many different interests?

A
  • Connect and organize people
  • Become flexible
  • Lobby
  • Meet
  • Translate
  • Guarantee risks
  • Finance and help to arrange money
  • Communication budget = marketing
  • Make use of existing organisations
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What kind of elements did they add to the Afsluitdijk eventually?

A
  • Fish migration river
  • Tourism and recreation: bringer of safety, new land and fresh water. Icon of NL. UNESCO. National monuments, also landscaping. Lots of tourist that want to visit it.