Lecture 10: Labour and Subcontractor Pricing Flashcards

1
Q

What are the two main approaches in pricing labour?

A

1) Productivity rates - Convert takeoff quantities into labour-hour then apply wage rates and
equipment rates to the total hours to estimate prices

2) Use of unit prices - Applied to listed takeoff quantities by using RSmeans

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What basic wage depends on?

A

Location and craft

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Explain about the 3 wages type

A

1) Union wage - Contract b/w local union & contractors’ Mgmt
2) Open-shop wage - Agreement between worker and employer
3) Prevailing wage - Survey of wage in the geographic area

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is “ Labour burden” ?

A

Additional expenses related to labour such as different kind of insurance, taxes and benefits.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is the challenge in estimating long-duration projects?

A

The estimator has to predict how wage rates may change over the term of longer projects for each of the different crafts used in the work.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is a productivity rate?

A

The number of units of work produced by labour in a unit of time (one hour, day or week).
Should be realistic -No person works 60 min/hr.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

If the task involves a crew?

A

Estimate for each member labour hourly rate (basic wage + labour burden)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

How much of the work is done by subcontractors?

A

80%

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Subcontractors pricing issues

A

1) Different subcontractors use different price bids (Lump-sum, unit price, hourly basis)
2) Interoplate works differently than GC
3) Failure to perform (banckrupcy)
4) Errors in sub-trade bids and more

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

When does a list of sub-trades required for the project should be prepared and notified?

A

As soon as bid drawings and specs are obtained

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Explain what are performance bonds and bid bonds.

A

1) Performance bonds: manage construction risk
2) Bid bonds: issued by the contractor to the project owner, guarantees that the winning bidder will undertake the contract under the terms at which they bid

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is the best way to evaluate subcontractor quotes?

A

Compare the subs’ quotes with your own estimate

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is the best way to compare different quotes?

A

Start with the most complete quote, find out what it includes. Adjust the others quotes by adding items they miss.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

When general expense requirements can be calculated?

A

Only when the quantity take-offs are complete

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What are general expenses? Give examples important Q)

A
  1. Site personnel (not associated with a specific work item)
  2. Safety & first aid
  3. Travel and accommodation
  4. Temporary site offices
  5. Hoardings and temporary enclosures
  6. Temporary heating
  7. Site access and storage space
  8. Site security
  9. Site equipment
  10. Site cleanup
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

How do you price site personal?

A

Multiplying the monthly payroll
cost of the personnel on the list by the number
of months they are required to be on the
project

17
Q

Which expenses may be included in safety requirements?

A

1) The cost of workers’ time when attending safety meetings
2. The cost of workers’ time when engaged in other safety-related activities
3. The provision of safety awards on the project
4. The provision of safety supplies at the site