Chapter 1 Flashcards

1
Q

What is cost estimation?

A

Probable total cost of a future activity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is the purpose of cost estimation? (part A)

A
  1. Developing an initial project budget for an owner
  2. Determining project feasibility
  3. Designing the project within the owner’s budget
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is the purpose of cost estimation? (part B)

A
  1. Evaluating alternative designs
  2. Preparing bids
  3. Re-estimating for an addendum (change in scope during the bidding process)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is the purpose of cost estimation? (part C)

A
  1. Substantiating claims and resolving issues

8. Preparing a payment schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What are the applications of approximate estimate?

A

1) Evaluating project feasibility
2) Evaluating cost of proposed design modifications
3) Establishing a preliminary budget for control purposes
4) Screening a number of alternative projects

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

How is an approximate estimate prepared?

A

Use only basic criteria such as :
Output
Total sqft
Number of units etc’

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

When is it good or not good to rely on an approximate estimate ?

A

Good:

1) Evaluation of design alternatives
2) Presentation of preliminary construction estimate to the owner

Not good:
Bid purposes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

List the 4 components of a detailed estimate

A

1) Estimated cost (materials, labour, equipment, subcontract work)
2) General expenses (Overhead, tax, insurance)
3) Contingency (Risk analysis)
4) Profit ( Top level mgmt)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is the basic approach to prepare detailed estimates?

A
  • Identify work items to be completed
  • Measure work items size
  • Asses likely cost of work
    (Identify + measure + evaluate cost) of work
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What are the components of bid estimate (detailed estimate)?

A

Bid price = Cost estimate +Contingency +General exp + Profit

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Name factors of contingency

A
  • Experience on similar projects
  • Season of construction
  • Contract condition
  • Project size
  • likelihood of profit
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is traditional (design - bid - build) delivery?

A

The project is fully design before work begins

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is design-built delivery?

A

A single organization responsible for design and construction

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is construction management delivery?

A

Facilities overlap between project stages. The main objective is earlier completion

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is a public-private partnership?

A
  • Long term contracts between the public and private sector

* Private sector will operate at first and then handover the asset to the public sector

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Name 3 types of contracts

A

1) Lump-Sum contracts
2) Cost-plus contracts
3) Unit-price contracts