What is conceptual cost estimation?

A

A quick method for determining the approximate cost of a project without a detailed definition of work scope

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is a parametric estimate?

A

Relates all costs of a project to just a few physical measures that affect the size or scope of the project. It’s done using historical records.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What can you learn from historical data?

A

1) Unit cost

2) Cost adjustments

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is the formula of weighted unit cost? (PERT)

A

Uc = (min+4 X mean + max)/6

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Name 4 criterias historical data is adjusted for:

A

1) Time - inflation/deflation
2) Location - /cost difference between location
3) Size - relationship between size and total cost
4) Unit cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What are the 3 ways to solve for unit cost adjustment?

A

1) Average unit cost
2) Y = mx+b
While m is the slope of the 2 endpoints