Chapter 3 Flashcards

1
Q

At what stage it is possible to use elemental estimate?

A

Feasibility stage

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What data is required to prepare elemental estimates?

A

1) Size and shape of the building
2) Use and location
3) Historical cost data of similar buildings

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is more accurate, elemental estimate or cost-unit-area estimate?

A

Elemental estimates, but it can vary according to the quantity and quality of historical data available

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Who uses UniFormat?

A

Consultants, since it’s simple and function-based

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Who uses MasterFormat?

A

Contractors, used for bidding. (More detailed items can be found)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What are building elements? give examples

A

A building element is a major component of most buildings that always perform the same function.

Examples: Foundation system, roof covering, floor finishes etc’

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

How many elements are in UniFormat and which one is used for estimates?

A

4 level
Level 1 - Major elements
Example: A: Substructure, B: shell, C: interiors

Level 2 - Group elements
Example: Substructure: A: substructure 10:Foundations

Level 3 - Elements -> Used for estimating
Example: What inside of level 2

Level 4 Subelements

How well did you know this?
1
Not at all
2
3
4
5
Perfectly