LE Case Study Flashcards
What were the key differences between the bespoke contract and the JCT SBC 2016?
Introduced a Nike code of conduct
Removed compensation for deferment of possession / delayed access to site
Timescale for notification of change / relevant matter for loss and expense - 5 days instead of as soon as reasonably practical
Obligation added with regard to compliance with modern slavery act
What did the Nike Code of Conduct State?
Sets out Policies with regard to Diversity and Inclusion
Behaviours and treatment of others with respect.
Health and Safety Policy
Environmental compliance
Why was the client concerned about keeping hold of the mechanical design?
Because they wanted to be able to control how it looked asthetically; in terms of grilles, and in terms of finished look as it would partially be on display.
Additionally, they wanted the flexibility to make changes later on.
What is two stage tendering?
You mentioned setting up a framework, how would this cater for the whole country?
In our pre-qualification questionaire we checked that contractors had capability to perform works in the regions where our stores were to be.
The rates were to be adjusted by location price adjustment formulae based on BCIS location tender price studies.
There was also price adjustment formulae, based on the general construction building index.