Contract Practice Flashcards

1
Q

What is a Relevant matter?

A

A matter that the employer is responsible for that materially affects the progress of the works. This will entitle the contractor to submit a loss and expense claim

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What are the relevant matters?

A
  • Deferment of possession
  • Variations / Changes
  • Postponement of works
  • Instruction of prov sums
  • Opening up or testing instructions
  • Discovery of antiquities
  • Building control delays
  • Delays caused by the employer whether by act or omission
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are the timescales to do with relevant matters?

A
  • The contractor should notigy the employer as soon as reasonably apparant
  • Once information received, employer has 28 days, or 14 days from each subsequent update to notify of loss and expense
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What are the options within NEC?

A

Option A: Priced contract with activity schedule.
Option B: Priced contract with bill of quantities.
Option C: Target contract with activity schedule.
Option D: Target contract with bill of quantities.
Option E: Cost reimbursable contract.
Option F: Management contract.
Option G: Term contract (for the appointment of a consultant based on a priced schedule of tasks).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What are the sections within the JCT?

A

Agreement
Recitals
Articles
Contract Particulars
Attestation
Conditions of contract
Section 1 - Definitions
Section 2 - Carrying out the Works
Section 3 - Control of the Works
Section 4 - Payment
Section 5 - Changes / Variations
Section 6 - injury, damage and insurance
Section 7 - assignment, third party rights and collateral warranties;
Section 8 - termination;
Section 9 - settlement of disputes.
Schedules

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What are the key differences between the NEC / JCT?

A

Project Manager
Works Information (ERs)
Compensation Events (time/money)
Time Constraints on CE’s
C.Es are both time and cost
No Prov Sums
Programme is a contractual document
EWNs
No Schedule of Rates
NEC is a lot more collaborative
NEC dispute resolution is different
NEC does not reference other clauses like the JCT

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What are the JCT insurance options?

A

Option A – All Risks Insurance of the works by the Contractor
Option B – All Risks Insurance of the works by the Employer
Option C (existing buildings)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What are the heads of claim for L&E?

A

Prolongation (site overheads, prelims)
Disruption
Increase in Labour
Loss of Profit
Acceleration
Material cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What are the differences between FIDIC and JCT?

A

Use
FIDIC is used internationally, whereas JCT is UK Centric
Payment
JCT Timescales, 7 days to assess payment application, 14 days from due date to final payment (21 days from application)
FIDIC Timescales - 28 days to assess payment application, 56 days from payment application to final date for payment. No payment entitled until performance security received (if required)

Time
FIDIC- Detailed programme required to be submitted within 28 days of notice of commencement and needs to show detailed aspects listed in contract. Must be regularly updated.
JCT - Date for possession and completion stated. Programme to be submitted as soon as reasonable practicle - no teeth.

Variations
FIDIC - Cost and time together. Time limitation – must declare within 28 days of becoming aware or forfeit entitlement.
However, if the engineer does not inform the other party of this within 14 days, then the entitlement is valid

JCT - Cost and time seperated. Declare as soon as reasonably apparent - no consequence for late submission

Terminology
Engineer is key person in FIDIC vs CA / EA in JCT

Disputes
FIDIC is more proactive with regard to disputes with a Dispute avoidance / Adjudication board to be appointed from the outset to proactively manage disputes.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What are the provisions under the Construction Act? (HGCRA 96)

A

o The right to be paid in interim, periodic or stage payments.
o The right to be informed of the amount due, or any amounts to be withheld.
o The right to suspend performance for non-payment.
o The right to adjudication.
o Disallowing pay when paid clauses.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What were the 2011 changes to the construction act?

A

o Amended local democracy, economic development and construction act October 2011 to close loop holes within its provisions. Effectively changed the construction act.
o The act now applies to construction contracts including those that are not in writing.
o Adjudication clauses must still be in writing, otherwise the scheme applies.
o No longer allowable to define within a contract who should bear the cost of adjudication.
o Adjudicators have the right to correct errors in their decisions within 5 days.
o The dates for payments must be set out in the contract.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

When should an intermediate contract be used?

A

Designed to be used when the traditional procurement route has been chosen. To help fill the gap between the detailed and lengthy provisions of the SBC and the simplicity of the minor works contract.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is the Scheme for Construction Contracts (England and Wales) Regulations?

A

o A scheme which applies when construction contracts do not comply with the Housing Grants Construction Regeneration Act 1996.
o Supplements contractual provisions where the contract has deficiencies
o Part 1 – Makes the provision for adjudication
o Part 2 – Replaces provisions in relation to payment

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What were the aims of the amendment to the construction act in 2011?

A

To increase clarity and certainty as to payment in construction contracts;
To introduce a ‘fairer’ payment regime, and improve rights for contractors to suspend their work in non-payment circumstances; and
To make adjudication more accessible for the resolution of disputes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Can you give me two examples of Relevant Events

A
  • Variations.
  • Exceptionally adverse weather.
  • Civil commotion or terrorism.
  • Failure to provide information.
  • Delay on the part of a nominated sub-contractor.
  • Statutory undertaker’s work.
  • Delay in giving the contractor possession of the site.
  • Force majeure (events that are beyond the reasonable control of a party, such as a war or an epidemic).
  • Loss from a specified peril such as flood.
  • The supply of materials and goods by the client.
  • National strikes.
  • Changes in statutory requirements.
  • Delays in receiving permissions that the contractor has taken reasonable steps to avoid.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Within the JCT form of contract what insurances are there within the contract?

A

Construction all risk insurance
Option A – New building taken out by contractor
Option B – New building taken out by employer
Option C – Existing building taken out by employer

Contractor will need to take out public liability and employers liability.

17
Q

What are the differences between standard and Intermediate JCT?

A

No quotation provision for in variations in IC
No 3rd party rights provided for in IC
No retention bond in IC

18
Q

What are the differences between intermediate and minor works JCT?

A

No QS required in MW
No clerk of works required in MW
No full list of events for EOT in MW
No sections of work in MW
No detailed rules for variations in MW

19
Q

How would you go about a latent defect after the defect liability period?

A

This should be covered by the limitation period and will be 6 years or 12 years. If it is after the limitation period it is up to the clients building insurance.

20
Q

What is the difference between a latent and patent defect?

A

A
Latent defects cannot be inspected by a reasonably thorough inspection whereas patent defects can.