LARE Definitions-S1 Flashcards
Addenda
Written or graphic instruments issued to clarify, revise, add to, or delete information in the procurement documents or in previous addenda. Typically, these are issued before the opening of bids/proposals.
Allowance
An allowance is a specified monetary sum, a specified quantity, or time not otherwise defined by the specifications and drawings, but which the contractor is required to include in the bid or price. Two types of allowance are cash allowance and quantity allowance.
Alternate
A defined portion of the work that is priced separately and thus provides an option for the owner in determining the final scope of the project. This will provide the owner with a choice between different products, or it can define the addition or deletion of a portion of the work.
Landscape Architect Supplemental Instructions:
Minor changes in the work are defined as instructions or interpretations not involving adjustment to the contract sum or time. Such changes are made by the architect supplemental instructions directing the contractor to make stated modifications. The architects supplemental instruction does not require the owners signature.
Basis of Payment
The three bases of payment are stipulated sum, unit price, and
cost-plus fee.
Bid
An offer to perform a contract for work or supply materials or goods at a specific price. A ___is a response to a solicitation such as an invitation to bid or an advertisement for bid.
Bid Bond
This bond is to protect the owner from losing the benefit of an accepted bid. The ___ bond is provided by the bidder at the time of bid and is submitted with the bid. The ___ bond generally provides for a penal amount expressed either in dollars or as a percentage of the total amount of the bid. In the event that the selected bidder fails or refuses to enter into a contract for the price that was bid, the surety is obligated to pay the owners damages up to the penal amount of the bid bond.
Bid Form
The bid process requires a bid form that is prepared as a document that the bidder will submit to the owner.
Binding Arbitration
he parties to the contract select a neutral arbitrator or panel of arbitrators and the matter is submitted for a decision.
Certificate of Substantial Completion
If, after this inspection, the A/E agrees that the project is substantially complete , the A/E prepares a certificate of substantial completion. This certificate includes the date of substantial completion, identification ofthe substantially complete portion of the project, and responsibilities of the contractor and the owner for utilities, maintenance, security, insurance, and damage to the project. The certificate of substantial completion also includes the specified time limit for the contractor to complete outstanding items of work.
Change Directive
Directs the contractor to make a change to the project before the owner and contractor have agreed upon the proposed changes in contract sum or time. Change directives are used in the absence of an agreement between the owner and the contractor on the terms of a change order or when the value of a change cannot be determined until after the work is performed.
Change Order
a written instruction to the contractor issued after execution of the agreement. It authorizes an addition, deletion, or revision to the project in consideration of an adjustment in the contract sum, contract time, or both. A _____ is used for changes to the contract documents that affect contract sum or time.
Change Order Request
A change order request may be used by the contractor to initiate proposed changes that the contractor deems necessary.
Closeout Meeting
Used to review requirements for the completion of the contract and to obtain submittal of the necessary final documents. Separate meetings may be required for substantial completion, final completion, and warranty inspections.
Closeout Submittals
A written notices of substantial and final completion (prepared by the contractor) and delivered to the A/E, indicating when the contractor believes these milestones are reached. Final application for payment; record documents (shop drawings, record drawings and specifications, addenda, change orders, field orders, photographs); O&M data; spare parts and extra stock materials; certificates of payment; release of liens and waiver of debts and claims; consent of surety to final payment; special warranties; and keying.
Competitive Bidding
It is a method of determining the lowest cost for accomplishing work defined by the procurement documents. The objective of bidding is to ensure that the cost of the project is reasonable and consistent with prevailing conditions in the construction industry.
Conditions of the Contract
General conditions have wide applicability to almost all projects and are available as standardized documents that are prepared by various professional associations.
Construction Documents
These include two major groups of documents: Procurement documents and contract documents.
Construction Management
The process of professional management applied to a construction project from conception to completion for controlling project time, cost, and extent. The construction manager as advisor (CMa) is employed by the owner to act as an adviser. The construction manager as contractor (CMc) is engaged to provide construction. The construction manager may provide construction expertise, estimating, and scheduling services. The construction manager may perform contracting, purchasing, and supervising of construction by guaranteeing the cost of the project and signing subcontracts, in which case the construction manager acts as a contractor andnot an adviser.
Contingency Allowance
The negotiated cost should include contingency allowances for unforeseen circumstances due to the incomplete nature of the information available at the time of negotiations. This contingency amount should be documented so that it may be returned to the owner if not spent.
Contractor’s Punch List
When the contractor considers that the work, or a portion thereof that the owner agrees to accept separately, is substantially complete, the contractor shall prepare and submit to the A/E a comprehensive list of items to be completed or corrected. The contractor is required by the AIA and EJCDC general conditions to prepare what is commonly referred to as a punch list.
Cost Plus Fee
Cost of the actual direct expense of construction work plus a fee for overhead and profit usually based on partially completed construction documents for a defined scope of work. The fee can be fixed, a percentage of the actual direct cost, or some other arrangement.
Design Development
This phase follows the ownerss approval of the schematic design and any necessary program or budget adjustments. The emphasis shifts from overall relationships and functions to more technical issues of constructability and integration of systems and components. Aesthetic concerns move from massing and arrangement to materials, surfaces, and details.
Design Team
Works with the owner to determine the design requirements, design the project, produce the construction documents, and administer the construction contract. The design team participants also review submittals and substitution requests before and after award of the construction contract. The design team is responsible for addressing planning issues, product research and selection, code research and compliance, quality control and assurance reviews, and construction contract administration.