export_laresection 1 Flashcards
affidavit
a written statement in which the facts stated are sworn or affirmed to be true
arbitration
a contractual provision whereby those bound to it give up their right to go to court
common law
a system of law that is derived from judges’ decisions (which arise from the judicial branch of government), rather than statutes or constitutions (which is derived from the legislative branch of government)
certify
process of verifying that a record is complete
commencement of improvements
first actual preparation or construction on the site, or the first delivery to the site of substantial materials
deposition
a sworn statement of a witness or other party in a judicial proceeding
due care
a theory of tort law to explain the standard of care or the legal duty one owes to others, what a reasonable person would do under circumstances
exoneration
a request to release the surety bond
license
a privilege or right granted to a person by a state to practice a profession
limit of liability
the maximum amount for which an insurer is liable as set forth in the contract
lis pendens
a recorded legal document giving constructive notice that an action affecting a particular property has been filed in either a state or a federal court
malfeasance
the doing of an act in an improper wrongful or unlawful manner (by public official)
malpractice
failure of a professional to act in accordance with the acceptable course of conduct, negligence of a member of a profession in a professional capacity
mediation
an informal means of trying to promote settlement of liability claim with a third party mediator who meets with the parties and tries to get them to agree on a settlement
misfeasance
performing a legal action in an improper way (private)
negligence
failure to exercise that degree of care which an ordinary prudent person would exercise under the same or similar circumstances
original contractors
a contractor who has contractual relationship with the owner
petition
a written request to the court for legal action, which begins a court case
remand
the decision of an appellate court to send a case back to the trial court with instructions on how to correctly decide the case, often used with the term “reversed”
statue of repose
set of laws used to define the maximum time period for filing claims against professionals
summary judgment
judgment entered when there is no genuine issue of material fact and party is entitled to prevail as a matter of law
statute of limitations
time limit within which as civil or criminal action may be brought after its cause arises
tort
a private wrong, independent of contract and committed against an individual, which gives rise to a legal liability and is adjudicated in civil court
tort law
aims to restore the injured person to the position he or she was in before the tort was committed (the expectation or rightful position principle)
addendum
document that addresses changes or modifications made to the contract and issued prior to the bidding process
competitive bid
a process whereby an underwriter submits a sealed bid to the issuer. the issuer awards the contract to the underwriter with the best price and contract terms
lump sum
comprised of a one total price to complete all of the work
unit price bids
based on predetermined major items of work, the items’ quantities and the contractor’s price per unit multiplied by the total quantity to create the total cost for each major item of work
fixed price contract
price is not subject to any adjustment on the basis of the contractor’s cost experience in performing the contract
cost-plus-fee contract
normally negotiated between the owner and the contractor. In most cses, the owner pays actual costs of construction plus an additional mount based on a fixed percentage of the project’s cost
notice of award
written notice by the Owner to the apparent successful bidder stating that upon compliance by the bidder with the conditions presented in the notice the Owner will the agreement
notice of proceed
written notice from the Owner to the Contractor that establishes the date on which the Contractor shall begin performing its duties and obligations as outlined in the Contract Documents
live loads
consist of the people, furniture and other items that are not part of the building, but are supported by the building
dead load
weight of the building or structure itself
contract form
dictates form of bidding conditions
-agreement
- performance and payment bonds
- certificates
technical specifications
prepared for each specific project in the CSI Master format. individual items that will be installed in the project
retainage
a portion of a contract payment that is withheld until contract completion to ensure full performance of the contract terms
assignment
refers to the transfer of an obligation from one person or firm to another
negation
canceling of a prior action
contingency
requires a certain act to be done or a certain event to occur before the contract becomes binding
binding arbitration
parties agreeing to accept as final the arbitrator’s decision
nonbinding arbitration
parties free to not accept the arbitrator’s decision and to seek satisfaction through other means, including lawsuit
mediation
parties agreeing to enter into good faith negotiations through a neutral mediator in order to attempt to resolve their differences
change order or work change directive
modifies (add/delete/change) the plans and specifications and/or the price and the contract time of the construction contract
contract admendment
provides for a change of contract provisions, including additional work outside the scope of the original contact
stop work order
a demand to stop an ongoing work activity due to a real or perceived dangerous operation or condition
quality circle
composed of project principals who meet on a frequent basis to identify, discuss and solve productivity and quality problems
substantially completed
that stage in the progress of the work of minor items that do not impair the owner from occupying and fully utilizing the work for its intended purpose
punch list
list of items to be completed or corrected by the contractor before substantial completion can be established
Final Completion
The completion of all work in accordance with the terms and conditions of the contract documents.
liquidated damages
specific sum of money stipulated by the contracting parties as the amount to be recovered for each day of delay in delivery of the product
bonus
refers to a certain percentage of the payment that is awarded to the contractor for finishing the job ahead of schedule
shop drawings
drawings, diagrams, schedules and other data specifically prepared for the work, by the contractor or a subcontractor, to illustrate some portion of the work
surety company
the entity responsible for fulfilling the contract in the event the original contractor defaults for any reason
bonds
include bid, performance, payment, maintenance and other instrument of security
bid bond
submitted with the bid by the contractor. security to the owner that the successful bidder will enter into an agreement for the work and not withdraw or nullify its bid after submission
indemnification
part of an agreement that provides for one party to bar the monetary cost, either directly or by reimbursement, for losses incurred by a second party
maintenance bond
guarantees the owner that any defects found after the work has been completed will be corrected by the original contractor or other agent of the surety company
performance bond
guarantees the owner that the project will be completed for the contract price in the event the original contractor fails to perform the work
Statutory Bond
guarantees the owner that all labor, equipment, and materials will be completely paid for in the event the original contractor fails to perform the work
prevailing wages
under these laws, federal contractors must pay their employees at rates at least equal to ___ wages in the local area.
30% of the local labor force
cost plus or cost plus fee agreement
contractor is reimbursed for direct and indirect costs and in addition is paid a fee for its serves. Fee is usually stated as a percentage of cost, but may be fixed amount. The agreement may or may not include a guaranteed max price or a savings split.
Percentage of Construction Cost
A method of compensation for construction or professional services based on a percentage of the total cost of construction
Percentage of Prime Consultant Fee
- a method based on a portion of the project cost set using the prime consultant’s fee amount in some percentage as the subconsultant’s fee
- does not limit overall cost
guaranteed maximum upset
sets a guaranteed maximum or ceiling price to owner for the cost of construction
stipulated sum agreement
a written agreement in which a specific amount is set forth as the total payment for completing the contract
unit price contract
owner agrees to pay the contractor a specified amount of money for each unit of work successfully completed as set forth in the contract, includes all extra costs incidental to the item
payment bonds
gives protection to the owner if the subcontractors and suppliers are not paid by the prime contractor
lien
a claim or charge on property for the payment of a debt
addenda
formal changes or clarifications issued to all identified bidders by the owner or the owner’s representative during the bidding period
agency agreement
an arrangement between a principal and an agent by which the agent agrees to perform certain tasks for the principal, the principle is bound by the actions of the agent
ADR - alternative dispute resolution
a means used for settling conflicts by means of an alternative procedure to formal litigation
additional work
construction work that was not recognized at the contract award but that must be performed in order to deliver a project as planned.
arbitration
a well-established alternative to litigation in which the conflict is resolved by an impartial third party or an impartial panel of selected individuals