export_lare section 1 Flashcards

1
Q

Rules of Professional Conduct
(A) Competence

LARE Orientation Guide!!

A

(A) In engaging in the practice of landscape architecture, a registered landscape architect shall act with
reasonable care and competence and shall apply the technical knowledge and skill which are ordinarily

applied by registered landscape architects of good standing, practicing in the same locality

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What are the three strategies to address site operations and maintenance?

A
  1. Develop a sustainable management plan. Not only should an integrated pest management (IPM) plan be implemented by the maintenance team, but so should a plan for cleaning the exterior surfaces.
  2. Implement conservation programs. Protect species and habitat by working

with local ecologists and nonprofi t organizations.

  1. Maintain site lighting to prevent light pollution. Whenever higher light levels are needed, put the fixtures on timers to shut off automatically after hours.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are the strategies to reduce rainwater runoff?

A

Wet or dry ponds. Both of these approaches utilize excavated areas used to detain rainwater from leaving the site and therefore slow runoff.

Two other options include on‐site

filtration methods. Bioswale can be utilized to increase groundwater recharge and reduce peak rainwater runoff.

The other option, rain gardens, functions to collect and fi lter runoff while reducing peak

discharge rates.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

three design strategies to address

rainwater management

A
  1. M inimize impervious areas . Remember open‐grid pavers, porous paving, pervious
    concrete, and green roofs to increase pervious surfaces
  2. Control rainwater. Remember rain gardens, dry ponds, and bioswales slow

down runoff while allowing the natural environment to infi ltrate and clean

the water of pollutants.

  1. Incorporate rainwater management into site design . Implement multipurpose

features, such as streets with bioswales to collect and hold rainwater.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

There are two strategies for rainwater management in operations and maintenance

A
  1. Redirect rainwater r into rain gardens, bioswales, or other water‐retaining
    landscape features.
  2. Harvest rainwater. Collect it and use it later for nonpotable uses, such as irrigation,
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

MasterFormat DivisionsMasterFormat Divisions

A

MasterFormat was first released in 1975 and only had 16 Divisions until the new 50-Division MasterFormat 2004 was released in late 2004. Divisions that are not listed below are reserved for future use (including Division 49.)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Which of the following answers correctly lists the order of project management activities according to Ramroth in “Project Management for Design Professionals”?

A

Defining, Planning, Directing, Coordinating, Monitoring, Learning

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Licensed landscape architects may seal and sign drawings that have been prepared …

A

1 - Under their supervision by an unlicensed graduate of an accredited landscape architecture program

and

2- Under their supervision by a draftsperson

(KEY IS UNDER THEIR SUEPRVISION)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is the main responsibility of a landscape architect under contract with a client

A

Exercising prudent and consistent standards of care.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Construction Specifications

A

According to the American Institute of Architects (AIA) Document A201-2007, the Contract Documents for a construction project consist of “the Agreement, Conditions of the Contract, Drawing, Specifications, Addenda…”, as well as other miscellaneous documents associated with the contract between the project Owner and the Contractor hired to complete the work. Construction specifications, as noted, become a part of the legal documents of the agreement and form a cornerstone of the project design. In fact, in most cases, the construction specifications override the project drawings in the event of conflicting information.

The purpose of construction specifications is to delineate the requirements regarding the materials, products, installation procedures and quality aspects involved with execution of the work and fulfillment of the contract. Specifications can be divided into three primary categories: performance, prescriptive and proprietary, which are described below.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Performance Specifications

A

A performance specification is a document that specifies the operational requirements of a component or installation. Simply put, a performance specification tells the contractor what the final installed product must be capable of doing. The contractor is not instructed as to how to accomplish the task of meeting the performance specification requirements - only as to how the component must function after installation. For example, a performance specification may be used in the construction of an industrial pumping system. The specification would provide a required pumping rate (say 500 gallons per minute), a required pressure (20 psi) and the difference in height between the pump and the final destination (+40 feet). The specification will also state that the liquid to be pumped will be at a temperature of 140°F and is corrosive (pH of 3). It is up to the contractor to provide pumping equipment that meets or exceeds the requirements stated in the specification. In many cases the contractor will also be required to test equipment to make sure that is operating properly, and will provide operations manuals.

The general concept behind the performance specification is for the architect or engineer to describe what they need, and the contractor to determine the best way to get there. The performance specification focuses on the outcome and shifts the selection of materials and methods, as well as a portion of the design work, onto the shoulders of the contractor. This approach can provide incentives for innovation and flexibility in the construction approach, but also reduces the amount of control that the architect or engineer has over the project./p>

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Prescriptive Specifications

A

Prescriptive specifications convey the requirements of a project through a detailed explanation of the materials that the contractor must use, and the means of installing those materials. This type of specification will typically be formatted in a manner similar to the following sections:

General: This section will typically contain references to national/international standards, design requirements, a list of required submittals from the contractor to the architect/engineer, quality control requirements and product handling requirements.

Products: This section will describe, in detail, the various products required for the task covered by the specification along with the individual structural and performance requirements of each product.

Execution: This section will explain how to prepare the materials and conduct the installation, including the testing requirements to be followed.

Prescriptive specifications shift more of the project design control onto the shoulders of the architect or engineer and away from the contractor by establishing a set of rules that is to be followed for each project component. This type of specification provides more certainty regarding the final product composition than the performance specification, and is very frequently used for highly complex portions of a project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Proprietary Specifications

A

Proprietary specifications are those that require the use of a single approved product type for any particular installation. Proprietary specifications are often used in cases where there is existing equipment or installations already on site. In these cases the owner may want to maintain consistency of materials or possibly simply prefers a specific type of product. Also, in highly complex installations where there is only one specific piece of equipment that will accomplish a specified task, a proprietary specification is required.

Architects and engineers typically try to avoid utilizing proprietary specifications except when absolutely necessary, and will usually allow the contractor to select from a list of approved suppliers. Requiring the use of one specific product type can lead to the perception of favoritism towards a certain manufacturer and may eliminate competition during the bid phase, which may increase the project cost.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Construction Specification Standards

A

Construction specifications used in the United States typically conform to the guidelines of the Construction Specifications Institute (CSI), who have created a specifications index entitled MasterFormat. The MasterFormat index groups specification sections into easily identifiable disciplines using a six-digit system with digits in groups of two, such as: 01 24 30.

The first two digits denote the primary section (of which there are 48 sections). For example, all the items regarding concrete start with the digits 03.

The second two digits identify the main headings and subheadings. In this case, we look at main headings Concrete Reinforcing (03 20 00) and Cast-in-Place Concrete (03 30 00) which can be broken down into Reinforcement Bars (03 21 00) and Structural Concrete (03 31 00).

The breakdown continues further with the final two digits, for example: Plain Steel Reinforcement Bars (03 21 11) and Heavyweight Structural Concrete (03 31 13).

Use of MasterFormat allows professional and construction personnel alike the ability to use a common system to reference and group materials and equipment when utilizing specifications, pay applications, estimating programs, etc.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

MasterFormat Specifications

A

Construction specifications used in the United States typically conform to the guidelines of the Construction Specifications Institute (CSI), who have created a specifications index entitled MasterFormat. The MasterFormat index groups specification sections into easily identifiable disciplines using a six-digit system with digits in groups of two, such as: 01 24 30.

The first two digits denote the primary section (of which there are 48 sections). For example, all the items regarding concrete start with the digits 03.

The second two digits identify the main headings and subheadings. In this case, we look at main headings Concrete Reinforcing (03 20 00) and Cast-in-Place Concrete (03 30 00) which can be broken down into Reinforcement Bars (03 21 00) and Structural Concrete (03 31 00).

The breakdown continues further with the final two digits, for example: Plain Steel Reinforcement Bars (03 21 11) and Heavyweight Structural Concrete (03 31 13).

Use of MasterFormat allows professional and construction personnel alike the ability to use a common system to reference and group materials and equipment when utilizing specifications, pay applications, estimating programs, etc.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Master Format Divisions

A

MasterFormat was first released in 1975 and only had 16 Divisions until the new 50-Division MasterFormat 2004 was released in late 2004. Divisions that are not listed below are reserved for future use (including Division 49.)

Division 00 - Procurement and Contracting Requirements

Division 01 - General Requirements

Division 02 - Existing Conditions

Division 03 - Concrete

Division 04 - Masonry

Division 05 - Metals

Division 06 - Wood, Plastics, Composites

Division 07 - Thermal and Moisture Protection

Division 08 - Openings

Division 09 - Finishes

Division 10 - Specialties

Division 11 - Equipment

Division 12 - Furnishings

Division 13 - Special Construction

Division 14 - Conveying Equipment

Division 21 - Fire Suppression

Division 22 - Plumbing

Division 23 - Heating, Ventilating, and Air Conditioning (HVAC)

Division 25 - Integrated Automation

Division 26 - Electrical

Division 27 - Communications

Division 28 - Electronic Safety and Security

Division 31 - Earthwork

Division 32 - Exterior Improvements

Division 33 - Utilities

Division 34 - Transportation

Division 35 - Waterway and Marine Construction

Division 40 - Process Integration

Division 41 - Material Processing and Handling Equipment

Division 42 - Process Heating, Cooling, and Drying Equipment

Division 43 - Process Gas and Liquid Handling, Purification and Storage Equipment

Division 44 - Pollution and Waste Control Equipment

Division 45 - Industry-Specific Manufacturing Equipment

Division 46 - Water and Wastewater Equipment

Division 48 - Electrical Power Generation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Rules of Professional Conduct
(B) Competence

LARE Orientation Guide!!

A

(B) In designing a project, a registered landscape architect shall take into account all applicable state and
municipal building laws and regulations. While a registered landscape architect may rely on the advice of

other professionals, (e.g., attorneys, engineers and other qualified persons) as to the intent and meaning of

such regulations, once having obtained such advice, a registered landscape architect shall not knowingly

design a project in violation of such laws and regulations.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

Rules of Professional Conduct
(C) Competence

LARE Orientation Guide!!

A

(C) A registered landscape architect shall undertake to perform professional services only when he or
she, together with those whom the registered landscape architect may engage as consultants, is qualified by

education, training and experience in the specific technical areas involved.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

Rules of Professional Conduct
(D) Competence

LARE Orientation Guide!!

A

(D) No individual shall be permitted to engage in the practice of landscape architecture if, in the Board’s

judgment, such individual’s professional competence is substantially impaired by physical or mental

disabilities.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

Rules of Professional Conduct
(A) Conflict of Interest

LARE Orientation Guide!!

A

(A) A registered landscape architect shall not accept compensation for his or her services from more
than one party on a project unless the circumstances are fully disclosed to and agreed to by (such disclosure

and agreement to be in writing) all interested parties.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

Rules of Professional Conduct
(B) Conflict of Interest

LARE Orientation Guide!!

A

(B) If a registered landscape architect has any business association or direct or indirect financial interest
which is substantial enough to influence his or her judgment in connection with his or her performance of professional services, the registered landscape architect shall fully disclose in writing to his or her client or employer the nature of the business association or financial interest, and, if the client of the employer objects to such association or financial interest, the registered landscape architect will either terminate such association or interest or offer to give up the commission or employment.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

Rules of Professional Conduct
(C) Conflict of Interest

LARE Orientation Guide!!

A

(C) A registered landscape architect shall not solicit or accept compensation from material or equipment
suppliers in return for specifying or endorsing their products.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

Rules of Professional Conduct
(D) Conflict of Interest

LARE Orientation Guide!!

A

(D) When acting as the interpreter of building contract documents and the judge of contract
performance, a registered landscape architect shall render decisions impartially, favoring neither party to the
contract.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

Rules of Professional Conduct
(A) Full Disclosure

LARE Orientation Guide!!

A

(A) A registered landscape architect, making public statements on landscape architectural questions,
shall disclose when he or she is being compensated for making such statements

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

Rules of ProfessionalConduct
(B) Full Disclosure
LARE Orientation Guide!!

A

(B) A registered landscape architect shall accurately represent to a prospective or existing client or
employer his or her qualifications and the scope of his or her responsibility in connection with work for which
he or she is claiming credit.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
26
Q

Rules of Professional Conduct
(C) Full Disclosure

LARE Orientation Guide!!

A

(C) If, in the course of his or her work on a project, a registered landscape architect becomes aware of a
decision taken by his or her employer or client, against such registered landscape architect’s advice, which violates applicable state or municipal building laws and regulations and which will, in the registered landscape architect’s judgment, materially and adversely affect the safety to the public of the finished project, the registered landscape architect shall:

  1. report the decision to the local building inspector or other public official charged with the
    enforcement of the applicable state, provincial or municipal building laws and regulations;
  2. refuse to consent to the decision; and
  3. in circumstances where the registered landscape architect reasonably believes that other such
    decisions will be taken, notwithstanding his or her objections, terminate his or her services with respect to the project. In the case of a termination in accordance with this clause (3), the

registered landscape architect shall have no liability to his or her client or employer on account
of such termination.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
27
Q

Rules of ProfessionalConduct
(D) Full Disclosure
LARE Orientation Guide!!

A

(D) A registered landscape architect shall not deliberately make a materially false statement or
deliberately fail to disclose a material fact requested in connection with his or her application for a
registration or renewal thereof.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
28
Q

Rules of Professional Conduct
(E) Full Disclosure

LARE Orientation Guide!!

A

(E) A registered landscape architect shall not assist the application for a registration of an individual
known by the registered landscape architect to be unqualified in respect to education, training, experience or

character

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
29
Q

Rules of Professional Conduct (F) Full Disclosure

LARE Orientation Guide!!

A

(F) A registered landscape architect possessing knowledge of a violation of the provisions set forth in
these regulations by another registered landscape architect shall report such knowledge to the Board.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
30
Q

Rules of Professional Compliance with Laws

LARE Orientation Guide!!

A

(A) A registered landscape architect shall not, while engaging in the practice of landscape architecture,
knowingly violate any state, provincial or federal criminal law.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
31
Q

Rules of Professional Practice
Compliance with Laws
LARE Orientation Guide!!

A

(B) A registered landscape architect shall neither offer nor make any payment or gift to a government
official (whether elected or appointed) with the intent of influencing the official’s judgment in connection with a prospective or existing project in which the registered landscape architect is interested.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
32
Q

Rules of Professional Practice Compliance with Laws

LARE Orientation Guide!!

A

(C) A registered landscape architect shall comply with the registration laws and regulations governing his
or her professional practice in any jurisdiction.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
33
Q

Rules of Professional Practice
(A) Professional Conduct

LARE Orientation Guide!!

A

(A) Each office in a jurisdiction maintained for the preparation of drawings, specifications, reports or
other professional landscape architectural work shall have a registered landscape architect resident and regularly employed in that office having direct supervision of such work.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
34
Q

Rules of Professional Practice
(B) Professional Conduct

LARE Orientation Guide!!

A

(B) A registered landscape architect shall not sign or seal drawings, specifications, reports or other
professional work for which he or she does not have direct professional knowledge and direct supervisory control; provided, however, that in the case of the portions of such professional work prepared by the registered landscape architect’s consultants, registered in this jurisdiction, the registered landscape architect may sign or seal that portion of the professional work if the registered landscape architect has reviewed such
portion, has coordinated its preparation, and intends to be responsible for its adequacy.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
35
Q

Rules of Professional Practice (C) Professional Conduct
LARE Orientation Guide!!

A

(C) A registered landscape architect shall neither offer nor make any gifts, other than gifts of nominal
value (including, for example, reasonable entertainment and hospitality), with the intent of influencing the judgment of an existing or prospective client in connection with a project in which the registered landscape architect is interested.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
36
Q

Rules of Professional Practice (D) Professional Conduct
LARE Orientation Guide!!

A

(D) A registered landscape architect shall not engage in conduct involving fraud or wanton disregard of
the rights of others.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
37
Q

Acceleration Cost

A

Cost incurred by a contractor when the project is interfered with by the owner in such a way that the contractor must employ more manpower or work more hours. If the contractor contributes to the cause of its own delays, acceleration cost may not be granted.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
38
Q

Acceptance

A

Act of a person to whom a thing is offered by another and they receive it with the intention of retaining it (e.g. the acceptance of a contract).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
39
Q

Active Interference

A

Action by a party to a contract that causes the other party of the contract to not complete the work of the project on time or in the manner established by the contract writing.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
40
Q

Actual Damages (Actual Loss)

A

Damages resulting from a real and substantial loss, as opposed to those which are merely theoretical, estimated, or anticipated.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
41
Q

Addenda

A

Modifications to the contract documents issued during the bid period which become official parts of the contract documents.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
42
Q

Agent

A

A person authorized to act for a client who is employed to represent the client in business and legal dealings with third persons. There are 3 parties involved: a principal (client), an agent, and a third party. An agency relationship is established in writing with all 3 parties acknowledging the relationship. The agent cannot be self-serving or profit at the principal’s expense. Examples of agents include attorneys, brokers, auctioneers, and real estate agents.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
43
Q

Agency Agreement

A

Similar to contracts in that they must contain the same basic elements. The agent is authorized to do only what the principal wants. They can be placed in a position to exercise discretion, and can even enter into contracts that are binding on behalf of the principal. There are no limits on who can be an agent (e.g. an employee can be an agent - construction worker can be granted the authority to purchase tools and materials needed in the performance of work.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
44
Q

Agency Agreements, Exceptions

A

The agent can be empowered to do anything the principal can lawfully do, however, they can not perform acts that are personal in nature or must be personally performed, acts that are illegal, acts that are immoral, or acts that are opposed to public policy.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
45
Q

Agency Agreements, The Contractors part in

A

The Contractor should not be an agent in most cases as this would make the Principal liable for their actions, as such contractors should be made (through contract) independent. However, this also means that the Principal (owner) cannot take control away from the contractor and only specify the final result (i.e. can’t interfere with the methods and personnel hiring practices of the contractor). Also of note, the owner’s agents must focus on product quality and not methods when dealing with the contractors.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
46
Q

Agency Agreements, The Principals part in

A

The principal is liable for all contracts made by the agent while the agent is acting within the scope of the stated authority. A 3rd party who makes an agreement with the agent is held liable to the Principal and not the agent. If an act of the agent is unauthorized the Principal is not bound by it, however, if the Principal ratifies it then it will become binding.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
47
Q

Agency Agreements, Termination of

A

Agency agreements can be terminated at the expiration of the time period for the agreement, death of the principal or agent, destruction of the subject matter for which the agency was formed, fulfillment of the purpose of the agency, termination by the principal, termination by the agent, mutual consent between principal and agent to terminate, bankruptcy of either party, and a development which makes the subject matter illegal.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
48
Q

Agreement

A

The subject matter of the contract, the parties to the contract, the nature of the transaction, the time during which it will be performed, the fees to be charged, the manner of billing and the specification and deals where relevant.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
49
Q

Allowance

A

A sum of money set aside by the owner to remove a particular portion of work from competitive bidding. Typical of government subsidized institutions with work that is proprietary and must not be competitively bid on.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
50
Q

ALTA Survey

A

A land survey performed by a professionally licensed surveyor and conforms to the standards set by the American Land Title Association (ALTA).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
51
Q

Alternate

A

A material or method used in place of the base material or method specified for the project with equal cost or value.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
52
Q

Ambiguity

A

Doubtfulness of meaning of an expression used in a written instrument.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
53
Q

Anticipatory Breach (Anticipatory Repudiation)

A

When a contractor states that they will not or cannot perform the contract, the owner may terminate the contract immediately or after a waiting period to determine the contractor’s performance according to the contract writing. The owner MUST establish that the contractor’s statement is certain and unequivocal. If they terminate and the statement is found to be ambiguous, the owner will have wrongfully defaulted them.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
54
Q

Antitrust Laws

A

Federal and State statutes to protect trade and commerce from unlawful restraints and monopolies. Bid Rigging is considered a violation of antitrust laws.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
55
Q

Apparent Agency

A

An agency relationship created by an act of the parties.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
56
Q

Arbitration

A

Avenue of resolving conflicts that arise in practice with disputes being settled by an impartial board of experts or a disinterested 3rd party. Typically the parties must agree that by submitting to arbitration, they will accept the decision of the arbitrator and they waive their rights to report to a court of law if the arbitration decision is unfavorable.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
57
Q

Arbitration, Submission of

A

When a dispute arises in a contract containing an arbitration agreement, both parties must submit a written and signed dispute which should contain a definition of the scope or arbitration, definition of the award period, and a definition of the rules of procedure to be followed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
58
Q

Arbitration Agreement

A

This may be included in the contract, written as a supplement to the contract to cover all future disputes, or to address a specific controversy. The agreement should always be written and signed by both parties.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
59
Q

Arbitrator

A

Person or group of experts who have no stake in the matter who listen to all parties equally and make a decision outside of a court of law.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
60
Q

Architect’s Supplemental Instruction Form

A

This form can be used to correct errors or inconsistencies in a contract between the owner/client and the contractor after said contract has been signed. It can also be used to make minor alterations to other aspects of the contract and to make minor changes to the scope of work described in the contract provided that these changes do not alter the contract’s cost or project timeline.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
61
Q

Assignment

A

A legal action which allows a person who is not party to a contract to obtain the contract rights of a party who is. E.g. the LA can assign portions of the design of the project to it’s consulting engineers.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
62
Q

Attachment

A

Attachment

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
63
Q

Betterment

A

An improvement brought upon a property which enhances its value more than just repairing. It may be temporary or permanent. This also applies to public improvement such as widening of a street.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
64
Q

Bid

A

An offer to perform a contract for work and labor or for supplying materials at a specified price. In the construction industry, a bid is considered an offer by the contractor to the owner. A bid, as an offer, becomes a contract once the owner accepts the bidder’s offer with all other contractual requirements in order

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
65
Q

Bid, Public Works Project (Advertisements for)

A

This process is governed by law and must be followed a specific way (depending on municipality rules). Generally it follows the following procedure: 1. Notice must be given to interested and qualified members of the construction community in advance of the bidding. This notice must be placed in a publicly accessible place (newspaper, magazine, government website, trade publication, etc.) This is typically called the “Notice to Bidders” and contains the following: Type of project, Location, Type of Contract, Bonding requirements, Dates to perform work, Terms of payment, Estimated construction cost (some may exclude this), time/manner/place to submit bids, location to obtain bid documents, deposit required on bid docs, Owner’s right to reject any and all bids, req’s regarding wage rates. 2. The Invitation for bids must be posted in public places and distributed to the local construction community. 3. All bidders must be treated alike and be afforded an opportunity to bid under the same terms and conditions. 4. Prequalification may be required.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
66
Q

Bid, Prequalification

A

Prequalifying contractors allows for a select list of bidders (or short list) be available for various projects. It averts construction problems by limiting bidding to contractors who have the experience and financial stability to complete the project. It is more desirable to eliminate a contractor before bidding rather than show that a contractor is not qualified after that firm has submitted the low bid.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
67
Q

Bid, Regular

A

While not always the same, typically anything that would lead to bid rejection constitutes a “regular bid”. So bids without a bid security, bids that fail to acknowledge addendum, late bids, not dated or missing minor info, etc.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
68
Q

Acceleration Cost

A

Cost incurred by a contractor when the project is interfered with by the owner in such a way that the contractor must employ more manpower or work more hours. If the contractor contributes to the cause of its own delays, acceleration cost may not be granted.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
69
Q

Acceptance

A

Act of a person to whom a thing is offered by another and they receive it with the intention of retaining it (e.g. the acceptance of a contract).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
70
Q

Active Interference

A

Action by a party to a contract that causes the other party of the contract to not complete the work of the project on time or in the manner established by the contract writing.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
71
Q

Actual Damages (Actual Loss)

A

Damages resulting from a real and substantial loss, as opposed to those which are merely theoretical, estimated, or anticipated.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
72
Q

Addenda

A

Modifications to the contract documents issued during the bid period which become official parts of the contract documents.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
73
Q

Agent

A

A person authorized to act for a client who is employed to represent the client in business and legal dealings with third persons. There are 3 parties involved: a principal (client), an agent, and a third party. An agency relationship is established in writing with all 3 parties acknowledging the relationship. The agent cannot be self-serving or profit at the principal’s expense. Examples of agents include attorneys, brokers, auctioneers, and real estate agents.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
74
Q

Agency Agreement

A

Similar to contracts in that they must contain the same basic elements. The agent is authorized to do only what the principal wants. They can be placed in a position to exercise discretion, and can even enter into contracts that are binding on behalf of the principal. There are no limits on who can be an agent (e.g. an employee can be an agent - construction worker can be granted the authority to purchase tools and materials needed in the performance of work.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
75
Q

Agency Agreements, Exceptions

A

The agent can be empowered to do anything the principal can lawfully do, however, they can not perform acts that are personal in nature or must be personally performed, acts that are illegal, acts that are immoral, or acts that are opposed to public policy.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
76
Q

Agency Agreements, The Contractors part in

A

The Contractor should not be an agent in most cases as this would make the Principal liable for their actions, as such contractors should be made (through contract) independent. However, this also means that the Principal (owner) cannot take control away from the contractor and only specify the final result (i.e. can’t interfere with the methods and personnel hiring practices of the contractor). Also of note, the owner’s agents must focus on product quality and not methods when dealing with the contractors.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
77
Q

Agency Agreements, The Principals part in

A

The principal is liable for all contracts made by the agent while the agent is acting within the scope of the stated authority. A 3rd party who makes an agreement with the agent is held liable to the Principal and not the agent. If an act of the agent is unauthorized the Principal is not bound by it, however, if the Principal ratifies it then it will become binding.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
78
Q

Agency Agreements, Termination of

A

Agency agreements can be terminated at the expiration of the time period for the agreement, death of the principal or agent, destruction of the subject matter for which the agency was formed, fulfillment of the purpose of the agency, termination by the principal, termination by the agent, mutual consent between principal and agent to terminate, bankruptcy of either party, and a development which makes the subject matter illegal.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
79
Q

Agreement

A

The subject matter of the contract, the parties to the contract, the nature of the transaction, the time during which it will be performed, the fees to be charged, the manner of billing and the specification and deals where relevant.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
80
Q

Allowance

A

A sum of money set aside by the owner to remove a particular portion of work from competitive bidding. Typical of government subsidized institutions with work that is proprietary and must not be competitively bid on.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
81
Q

ALTA Survey

A

A land survey performed by a professionally licensed surveyor and conforms to the standards set by the American Land Title Association (ALTA).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
82
Q

Alternate

A

A material or method used in place of the base material or method specified for the project with equal cost or value.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
83
Q

Ambiguity

A

Doubtfulness of meaning of an expression used in a written instrument.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
84
Q

Anticipatory Breach (Anticipatory Repudiation)

A

When a contractor states that they will not or cannot perform the contract, the owner may terminate the contract immediately or after a waiting period to determine the contractor’s performance according to the contract writing. The owner MUST establish that the contractor’s statement is certain and unequivocal. If they terminate and the statement is found to be ambiguous, the owner will have wrongfully defaulted them.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
85
Q

Antitrust Laws

A

Federal and State statutes to protect trade and commerce from unlawful restraints and monopolies. Bid Rigging is considered a violation of antitrust laws.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
86
Q

Apparent Agency

A

An agency relationship created by an act of the parties.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
87
Q

Arbitration

A

Avenue of resolving conflicts that arise in practice with disputes being settled by an impartial board of experts or a disinterested 3rd party. Typically the parties must agree that by submitting to arbitration, they will accept the decision of the arbitrator and they waive their rights to report to a court of law if the arbitration decision is unfavorable.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
88
Q

Arbitration, Submission of

A

When a dispute arises in a contract containing an arbitration agreement, both parties must submit a written and signed dispute which should contain a definition of the scope or arbitration, definition of the award period, and a definition of the rules of procedure to be followed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
89
Q

Arbitration Agreement

A

This may be included in the contract, written as a supplement to the contract to cover all future disputes, or to address a specific controversy. The agreement should always be written and signed by both parties.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
90
Q

Arbitrator

A

Person or group of experts who have no stake in the matter who listen to all parties equally and make a decision outside of a court of law.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
91
Q

Architect’s Supplemental Instruction Form

A

This form can be used to correct errors or inconsistencies in a contract between the owner/client and the contractor after said contract has been signed. It can also be used to make minor alterations to other aspects of the contract and to make minor changes to the scope of work described in the contract provided that these changes do not alter the contract’s cost or project timeline.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
92
Q

Assignment

A

A legal action which allows a person who is not party to a contract to obtain the contract rights of a party who is. E.g. the LA can assign portions of the design of the project to it’s consulting engineers.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
93
Q

Attachment

A

A legal process by which a court of law designates a specific property owned by the debtor to be transferred to the creditor or sold for the benefit of the creditor.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
94
Q

Betterment

A

An improvement brought upon a property which enhances its value more than just repairing. It may be temporary or permanent. This also applies to public improvement such as widening of a street.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
95
Q

Bid

A

An offer to perform a contract for work and labor or for supplying materials at a specified price. In the construction industry, a bid is considered an offer by the contractor to the owner. A bid, as an offer, becomes a contract once the owner accepts the bidder’s offer with all other contractual requirements in order

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
96
Q

Bid, Public Works Project (Advertisements for)

A

This process is governed by law and must be followed a specific way (depending on municipality rules). Generally it follows the following procedure: 1. Notice must be given to interested and qualified members of the construction community in advance of the bidding. This notice must be placed in a publicly accessible place (newspaper, magazine, government website, trade publication, etc.) This is typically called the “Notice to Bidders” and contains the following: Type of project, Location, Type of Contract, Bonding requirements, Dates to perform work, Terms of payment, Estimated construction cost (some may exclude this), time/manner/place to submit bids, location to obtain bid documents, deposit required on bid docs, Owner’s right to reject any and all bids, req’s regarding wage rates. 2. The Invitation for bids must be posted in public places and distributed to the local construction community. 3. All bidders must be treated alike and be afforded an opportunity to bid under the same terms and conditions. 4. Prequalification may be required.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
97
Q

Bid, Prequalification

A

Prequalifying contractors allows for a select list of bidders (or short list) be available for various projects. It averts construction problems by limiting bidding to contractors who have the experience and financial stability to complete the project. It is more desirable to eliminate a contractor before bidding rather than show that a contractor is not qualified after that firm has submitted the low bid.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
98
Q

Bid, Regular

A

While not always the same, typically anything that would lead to bid rejection constitutes a “regular bid”. So bids without a bid security, bids that fail to acknowledge addendum, late bids, not dated or missing minor info, etc.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
99
Q

Bidding, Accuracy of

A

The owner is typically responsible for any errors in the bid documents, however, statements are often included which place direct responsibility for the info on the contractor.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
100
Q

Bidding, The Award of

A

While contract award is given to the lowest bidder, there are stipulations that make this not all about the final $ amount. A phrase like “lowest responsible bidder submitting a regular bid” might be used.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
101
Q

Bidding, The Award Phase

A

Proceeds in this manor generally: 1. Bids are opened; 2. Owner evaluates the bids; 3. Notice of Award is issued; 4. Contractor acquires the required bonds and insurance; 5. Owner conducts pre-construction conference; 6. Owner awards the construction contract; 7. Notice to proceed is issued/Contractor signs the contract; 8. First day of construction is counted… and construction begins

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
102
Q

Bidding (The Bid Form)

A

The form to be used by all bidders to submit their bids. It typically includes: Price (lump sum or unit price), Time of completion (if not given by owner), Bid Surety, Agreement to provide contract surety, acknowledgment of having reviewed addenda (list # of addenda reviewed), list of subs used in the bid, experience record/financial statement, plant & equipment inventory, Declaration regarding fraud and collusion, statement regarding site examination, signature.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
103
Q

Bidding (Notice to Proceed)

A

Issued by the owner and stating the contract start date. Note that the contract may not be signed by the contractor when the notice to proceed is issued, or to have the contract “clock” started without the contract docs having been fully executed. Generally the notice to proceed obligates the owner to the contract, so signed or not it is official once notice is provided to the contractor.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
104
Q

Bidding, Process of

A

After the design phase: 1. Advertisement for bidders; 2. Contractors acquire bid docs; 3. Contractor conducts quantity takeoff; 4. Addenda issued; 5. Contractor determines prices for all quantities (gets additional info from subs); 6. Contractor finalizes bid; 7. Contractor submits bid; 8. Bids are opened

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
105
Q

Bidders, Instructions to

A

The rules by which the project will be bid include: 1. Instructions relative to the procedure for writing and submitting the bid (forms, items to be priced, alternatives only allowed where called for, etc.); 2. Contractor may be required to submit an experience record (used for post qualification); 3. Listing of all documents that are in the bid docs (dwg’s, specs, alternates, instructions, etc.); 4. The construction time period; 5. Indication of who is responsible for subsoil data, test borings, errors in the plans, etc. and if a site visit is required; 6. The req’s of the bid guarantee; 7. The insurance to be provided; 8. Bonding req’s; 9. Conditions for handling bid irregularities; 10. Where and when to deliver the bids; 11. Closed or public opening of the bids stated; 12. Prebid conference may be described.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
106
Q

Bidders, Responsible

A

This issue involves post qualification and allows the owner to look at more than just the $ amount submitted. It allows them to review the contractors work history, if they are over extended on other projects, underfinanced, or simply inexperienced. The endorsement of a contractor by a surety is often deemed sufficient to satisfy this criteria.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
107
Q

Bidders, Responsive

A

One who has submitted a bid under a competitive sealed bid which conformed in all respects to the invitation for bids so that all bidders may stand on equal footing. One is responsive if one replies to the specific questions set forth.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
108
Q

Bid (Design-Bid-Build Process)

A

Design completed before Bid, Bid completed before build. Advantages of this process include: 1. Owner benefits from competitive marketplace; 2. owner has the appearance of being impartial; 3. process fully embraces free market system; 4. may be the only viable method available for some gov. agencies. Disadvantages include: 1. Accurate costs cannot be known until the design is completed; 2. bids that exceed the owner’s budget cannot be constructed without jeopardizing the project; 3. various parties tend to be adversarial under this process; 4. Errors or Omissions in the design may lead to costly change orders.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
109
Q

Bid Depository

A

A local for subcontractors to submit their bids for a particular project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
110
Q

Bid Rejection

A

The act of not allowing a bid to be included because of an impropriety in the process of submission or as a result of the owner’s arbitrary decision to reject the bid (which they reserve the right to do in a typical contract). However, in rejecting a bid, they run the risk of interfering with the bidder’s right to do work or of defamation of character.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
111
Q

Bid Rigging

A

Scheme in which businesses collude so that a competing business can secure a contact for good or services at a pre-determined price.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
112
Q

Board of Contract Appeals

A

An independent administration to decide all public (not private) contract disputes used to help relieve the courts from the backlog of cases related to public contracts.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
113
Q

Boiler Plate

A

A term used to represent standard legal conditions inserted at the ‘front end’ of a construction contract and are usually titles “General Conditions”, “Supplemental Conditions”, and/or “Special Conditions”. The benefits include the fact that many or all parties will likely already be familiar with the language used, because it is less expansive than having such language be drafted by an attorney and because this language has been properly vetted through the court system (i.e. all parties understand the legal ramifications of the language contained).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
114
Q

Bond

A

A legal instrument through which one party guarantees the capabilities of another party. It describes a legal relationship that is termed a ‘suretyship’.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
115
Q

Bond vs. Insurance, difference between

A

An insurance policy is a 2 party instrument between the insurance company and the insured that protects the insured against a specified type of loss. In a surety agreement, the contractor is not providing the guarantee for him/herself, but for the owner (a 3rd party).; Insurance premiums are based on actuarial rates while Surety premiums are structured on a set fee (they assume that no losses will occur).; By assuming no losses, the Surety is more like a bank than an insurance company in that if the principal defaults, the surety can go after them to recoup the money. As such they can also go after anyone that caused the default (i.e. subs, owners, suppliers, etc.); Insurance covers specific losses, while a surety bond is for losses of any kind under the type of bond provided; Insurance transfers risk while a surety agreement does not; The underwriter of an insurance policy often has the ability to cancel the policy during the policy period, however, a bond can not be cancelled once issued… even if the premium has not been paid.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
116
Q

Bond, Bid

A

Guarantees that a bid has been made in good faith and that the bidder will enter the contract if the bid is accepted. If the contractor chooses to withdraw from a project after being awarded a contract, the most typical outcome is forfeiture of money in the amount of the difference between their bid and that of the next lowest bidder, up to the face value of the bid bond. In some instances, the contractor may have to forfeit the face value of the bid bond outright. Generally 5% of the contract amount, but could range from 5%-20%.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
117
Q

Bond, Maintenance

A

This guarantees that the contractor will rectify defects in workmanship or materials for a specified time after project completion (i.e. a Warranty). A 1-year maintenance bond is normally included in the performance bond without any additional charge.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
118
Q

Bond, Payment

A

Guarantees that all bills and obligations incurred by the contractor will be paid ($ to subs and material suppliers). In private projects this prevents liens, in public projects this prevents stop notices from being filed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
119
Q

Bond, Performance

A

Guarantees that the contract will be performed in accordance with the terms. It is valid for the life of the contract. This protection period extends through to final acceptance by the owner, and generally extends through the one-year warranty period. If the contractor defaults on the project, the Surety can (at its digression) take over the management of the project. They can provide financial support to the contractor to help them finish the job or take more direct involvement in project completion. To recoup the money paid if a default occurs, the Surety may use any defense that would have ben valid for the contractor (e.g. the owner not making payment, owner interference, unforeseen subsurface conditions, etc.)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
120
Q

Bonding Capacity (Bonding Limits for a Contractor)

A

This is the maximum value of work a contractor can take on. It is based on the “3 c’s” of underwriting : Character, Capacity, and Capital. This dictates the size of a project the contractor can take on. If the project would cause the contractor to exceed its bonding capacity then the project is not worth taking on.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
121
Q

Brokerage

A

The general contractor subcontracts all work on a project. This is generally not beneficial to the owner since the GC’s bid includes profit for both the sub’s work and the GC’s work. Typically contracts should state a minimum of work expected of the GC (25%, 50%, etc.)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
122
Q

Builder

A

Synonymous with ‘Contractor’, or a person whose occupation is the construction of structures, the controlling and direction of construction, or the remodeling of building and other structures.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
123
Q

Building Code

A

Regulations that govern the manner of construction, height and material specified in a project. These codes are intended to provide a minimum standard that protect the public health and safety

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
124
Q

Building Codes, Form Standard Codes

A

Codes that specify a result, and are the common type that dictate the manner of construction materials, etc.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
125
Q

Building Codes, Performance Standards

A

Codes that specify the manner in which a design must work.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
126
Q

Capacity

A

The ability of a person or an organization to do something, necessary for parties entering into a contract.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
127
Q

Case Law

A

Law established by following judicial decisions given in earlier cases.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
128
Q

Caveat

A

A caution or a warning to an individual or entity to use care before proceeding.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
129
Q

Certificate

A

A written and signed document establishing that a fact is true.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
130
Q

Certificate of Occupancy

A

Document issued by the building inspector certifying that the project conforms to all relevant code section and is safe for use.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
131
Q

Certificate of Payment

A

Document issued by the LA in which they certify that the contractor has adequately performed. This is given to the owner for payment to the contractor.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
132
Q

Certificate of Substantial Completion

A

Document issued by the LA when the project, or a portion thereof, is complete to the degree that the owner can use it.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
133
Q

Change, Cardinal

A

A change that is not within the scope of services defined in the contract. It is usually contingent on 2 factors: 1) a cardinal change is assumed if the essential identity of the project is altered; 2) the method or manner of the anticipated performance is so drastically changed that essentially a new agreement is made.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
134
Q

Change Clauses

A

Items in contracts that refer to how changes will be handled usually include elements like: The owner has the right to make changes within the general scope of the contract; The contractor is obligated to perform the work necessitated by the change; The change must be in written form and must be signed; An adjustment to the contact price and/or contract duration will be assessed by some means, or can be predetermined.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
135
Q

Change Order

A

Document issued directing the contractor to erect some portion of the project in a manner different than described in the original plans and spec’s. This change MUST have an effect on the price and/or time of the contract, otherwise is considered a field order or minor change.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
136
Q

Charrette

A

A meeting/workshop devoted to solve a problem or plan the design of something. This could take place over several days.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
137
Q

Chart, Bar (a.k.a. Gantt Chart)

A

Consists of a list of tasks along the left side of a page. Horizontal bars along the right side indicate the scheduled start and finish dates for each task. Drawbacks include that they do not show the interrelationship among tasks nor do they indicate which activities are most crucial for completing the entire project on schedule.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
138
Q

Chart, Critical Path Method (CPM)

A

A highly mathematical system in which task interrelationships are defined and task schedules analyzed. It is frequently used by contractors to schedule construction sequences and projects. It shows which parts must be started first (critical activities), which parts can’t be started till others are done, and which can be done in parallel (noncritical activities).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
139
Q

Chart, Milestone

A

A simple scheduling method that consists of identifying the target completion date for each activity, and may include the name of the person responsible for the task and later can have the actual completion dates. Drawbacks include that is only shows completion dates which may result in uncertainty about when activities should begin to be completed on time.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
140
Q

Civil vs. Criminal suits

A

Civil suits relate to disputes concerning contract matters and torts while Criminal suits relate to violations of the law.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
141
Q

Claim

A

An written action initiated by one of the parties of a contract against the other party.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
142
Q

Collusion

A

An agreement between 2 or more persons to defraud another

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
143
Q

Competitive Bidding

A

A process whereby sealed proposal are submitted to the owner for consideration. This is mandatory on public works projects. A private owner may use competitive bidding but is not legally bound by the process.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
144
Q

Completion Phase (End of Project)

A

Once major construction work items are completed, the Punch List is prepared and the project is considered to be substantially complete (i.e. the owner may begin to occupy the premises and warranty’s begin). Next Punch list items are addressed, Final inspection is conducted, Final completion is defined and the Project is accepted. Only then can the Release of retainage be requested and final payment made to the contractor.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
145
Q

Consideration

A

An agreement that one party will provide compensation for another parties performance (an essential element for the formation of a contract).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
146
Q

Constitution

A

Written document agreed upon by the people of the US or of a particular state as the absolute rule of action.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
147
Q

Construction Management

A

A process of professional management applied to a construction program from conception to completion for the purpose of controlling time, cost and quality.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
148
Q

Construction Specification Institute Format (CSI)

A

ASLA’s adopted construction specification format. It provides for a system for organizing the specs. CSI has also developed a Uniform System that provides a data filing system and a cost accounting system that is based on the CSI format. There are 16 divisions of the CSI Uniform System 1. General Requirements 2. Site Work 3. Concrete 4. Masonry 5. Metals 6. Wood & Plastics 7. Thermal & Moisture Protection 8. Doors & Windows 9. Finishes 10. Specialties 11. Equipment 12. Furnishings 13. Special Construction 14. Conveying Systems 15. Mechanical 16. Electrical

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
149
Q

Constructive

A

Possession or knowledge of something which gives ownership to the object or deed. Examples: A person possesses a key to a safe-deposit box which gives them power and control of the contents; a burglar gains constructive breaking into a house when they gain admittance through threat, fraud or conspiracy; Constructive fraud is a contract or act though not intended to be evil in design but as it is misleading or deceiving it is prohibited by law.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
150
Q

Consultancy (Consultant)

A

An individual or group of individuals may advise design professionals or land owners in a more specialized form of LA service (e.g. urban design, environmental impact, research, etc.)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
151
Q

Contingent Liability

A

A contingent liability is a liability or a potential loss that may occur in the future depending on the outcome of a specific event.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
152
Q

Continuous Treatment

A

An uninterrupted, unbroken series of activities or events. E.g. the statute of limitation starts at completion of the project, however, the contractor is required to repair defects in the work and renders continuous treatment to the work, thus can extend the start of the statute of limitation period.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
153
Q

Contract

A

An agreement enforceable by law which is binding upon only those individual who are party to it (can be oral or implied). It is always best to be in writing stating scope of services, consideration that will be given for performance and the time in which performance is to take place. Though contract law varies from state to state, they generally fall under the law of the place where the contract was made or where it was enforced.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
154
Q

Contract (Adversarial Relationship)

A

Typically contracts have an adversarial relationship between the 2 parties (i.e. your risk vs. my risk).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
155
Q

Contract, Assignment

A

Assignment = to transfer; Refers to the transfer of rights or obligations to another party unless expressly prohibited by the terms of the agreement. E.g. the performance of personal services or personal skills of one of the parties are part of the consideration. A general rule is that the 2nd party to the contract cannot be placed in a worse position that would have been the case if the assignment has not been made.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
156
Q

Contract, Breach of

A

An action arising due to a failure on the part of one or more parties of the contract to perform to the terms of the contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
157
Q

Contract, Consideration

A

Consideration is something of value and the primary reason or main cause for a person to enter a contract. It is NOT regarded as consideration unless it is accepted by BOTH parties. This can be in the form of an object, money, or even an act (early completion of a project at the expense of acceleration).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
158
Q

Contract, Competent Parties

A

Competent parties are those persons legally and mentally capable of entering into agreements that are enforceable by law. Some persons, such as minors, persons under the influence of alcohol and other drugs, and mentally ill persons not declared insane, have only a limited capacity to contract.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
159
Q

Contract, Estoppel or Promissory Estoppel

A

Estoppel = prevented; A legal principle that a promise is binding in spite of the fact that no formal agreement was made between parties. i.e. a contract may be created by what a party does or says without a written document, and that party is then “estopped” from denying that a contract exists.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
160
Q

Contract, Executed or Executory

A

A contract that has been “executed” has been fully completed. All work performed and all payments made. A contract that is executory has some portion that remains to be done (e.g. work is done but owner has not submitted final payment). Note: that this is different from the phrase “execute a contract” which simply means that it has been signed by both parties.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
161
Q

Contract, Intent

A

A vague concept, but it is the presumption of what one party wanted to have done when entering the contract. E.g. a house is moved from one location to another and the contract says ‘the house is to appear new and like it did in it’s original location’, however, another portion of the contract specifically states ‘exterior to be painted and interior to receive touchup paint where needed’. This exact painting specification would be contrary to the “intent” of making the house ‘appear new’.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
162
Q

Contract, Lawful Subject Matter

A

The Subject must be definite and clearly defined, conform to the common law, cannot be contrary to public policy (any act that tends to promote breach of the law), and state or federal statues

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
163
Q

Contract, Lump Sum (also Fixed-Price)

A

A contract where the project will be completed for a fixed price and no more. The primary benefit is that all parties have agreed to a predetermined budget for a defined scope of services. While the total budget for a project can be altered by mechanisms such as change orders, the lump sum contract reduces the potential for significant cost overruns. According, and unlike unit price contracts, fixed-price contracts do not require precise measurements of in-place quantities to determine payment. Payments on a Lump Sum contract is based on a cost breakdown for the work performed during the period of payment (e.g. 1 month) and verified by the owner or Architect for reasonableness.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
164
Q

Contract, Meeting of the Minds

A

The parties of a contract agree on the basic meaning and legal implications of the contract on a basis of fact. Errors of fact (which can nullify a contract) can be unintentional, a misrepresentation, fraud, or by one party causing duress to the other (forcing consent to an agreement).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
165
Q

Contract, Offer and Acceptance

A

Evidence that an offer was made and that acceptance was definite, unqualified and unconditional (signed contract by both parties, or even the payment of a retainer noted in the contract is an act of qualifying acceptance)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
166
Q

Contract, Complacent w/ Provisions of Law

A

Certain types of contract must be in written form (may not be oral contracts) include the sale of land, lease or rental of land by more than one year’s duration, and any contract which will not be performed within one year from the date of the contract.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
167
Q

Contracts, Cost Plus

A

The contractor is reimbursed for most of the direct expenditures associated with a particular project PLUS an allowance for overhead and profit (usually a percentage). This can also have a guaranteed maximum so that the owner has a ‘not-to-exceed’ price on the total project (something that is difficult to do on this type of contract). This type of contract doesn’t lend itself to competitive bidding and is almost exclusively used in the private sector. Also this type of contract doesn’t place the owner and contractor in adversarial relationship (like most other contracts), however, the contractor must be trustworthy. Payments on a Cost-Plus contract is based on actual expenditures made on a project during the payment period (e.g. 1 month).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
168
Q

Contracts, Job Order

A

This type of contract is more for long term work, routine and/or unscheduled maintenance and repairs. The contractor will be ‘on call’ for any task to be done. The various types of work to be done will have a set price already determined, so there isn’t any need to negotiate every time a task comes up.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
169
Q

Contracts, Unit Price

A

The primary feature is that pricing for the various units of work is determined before the start of construction. The owner estimates the number of units for each element of work (e.g. excavation 2,500 cu.yd., concrete 2,000 cu.yd. etc.) then the contractor determines the unit price for the various items in the contract. The contractor must be careful in figuring the unit price as things like overhead and profit must be built into the price. Also, if forming is required for the concrete, the cost of that needs to be included as well. Unit Price contracts are appropriate when the project is fairly well defined, but the actual quantities are hard to estimate until after construction has started. Note that some Unit Price contracts may have a maximum quantity before the unit price must be renegotiated (e.g. 20-25%). After this point the owner can, if stated in the contract, adjust the unit price to lower his/her end costs. Payments for a Unit Price Contract are based on actual in-place field quantities.

170
Q

Contracts, Unit Price (Balanced & Unbalanced Bids)

A

The difference between balanced and unbalanced is not in the total price, but in the unit price of each item. For example, a bid may be for 3 items and total $120,000. The contractor may determine that most of the work will be at the start of the project, and therefore increase the unit price of the first item while lowering the unit price of the others. The result will still be a bid for $120,000, but there will be more money made at the start then at the middle or end. This will cover mobilization or other things that might not be an itemized part of the contract. This can hurt the owner in cases where this unbalancing is more extreme to an area where the contractor thinks the owner miscalculated the quantities. If the actual quantity is much higher than the owner expected, the higher unit price charged by the contractor leads to a much higher end cost.

171
Q

Contract Documents (General Conditions)

A

Sometimes referred to as the ‘boilerplate’, augment the construction contract and outline the rules under which the project will be built. They establish the rights, authority, and obligations of the contracting parties: the owner, the owner’s rep, and the contractor. It is preferred to use standard general conditions (AIA, etc.) so the language is familiar to all parties. This saves time and have often been court-tested so that the legal interpretation is known. (note this is typically non-technical information)

172
Q

Contract Documents (Project Manual)

A

Consists of the bidding documents, general conditions, supplementary provisions, and the technical specifications. This is usually a single binder or “book”, and can now be done online as well.

173
Q

Contract Documents (Specifications)

A

Broad term used to include all of the contract documents, with the exception of the drawings. This would include: Invitation to bid, Instructions to bidders, General conditions, Supplementary conditions, Bid proposal form, Bid bond form, Contract bond form, List of prevailing wages, Noncollusion affidavit, and Technical specs.

174
Q

Contract Documents (Supplemental Conditions)

A

When an organization has standard, general conditions for inclusion in specifications, supplemental conditions are used to modify the general conditions to make them project specific. (e.g. which materials the owner will provide, start date of construction, job schedule requirements, traffic control requirements, etc.) It is possible for a supplemental condition to become a general conditions or part of the boilerplate once that item is no longer unique to one project.

175
Q

Contracting Method, Design-Build

A

Owner has a single contract for both design and construction (a.k.a. turnkey construction). This has the advantage of having the construction firm as a part of the design which helps to lessen design time and permit plans have a higher degree of constructability (minimal need for clarity or an RFI system). This may be done by either a single firm with all in-house people, or by a partnership between a design firm and a construction firm.

176
Q

Contracting Method, General Contract

A

Contract method where the owner has a contract with the design professional, and then another contract with the Contractor. While the Designer will represent the owner during the construction process, they do not act as an agent and will not be a part of the bidding process.

177
Q

Contracting Method, General Contract (Public Projects)

A

Follows a more formal procedure to contract with a contractor: Public Ad which explains the project and the bid date; at a designated time, sealed bids are submitted at the location and manner specified in the ad; bids are opened and read to all in attendance; contract is awarded to lowest bidder. (a.k.a. Design - Bid - Build approach)

178
Q

Contracting Method, Professional Construction Management

A

Owner hires a firm with construction expertise to perform management services on the owner’s behalf. They are hired before the design starts and sometimes help with picking the designer. This allows the owner to have a knowledgeable agent who can review plans during the design phase, and perform value engineering to limit monetary commitments down the road. NOTE: the Construction Manager does NOT take on the risk, i.e. does not guarantee the construction cost, time or quality of the work.

179
Q

Contracting Method, Construction Management at risk

A

Same as Professional Construction Management (above) but the Construction Manager takes on ‘risk’ of construction time and cost. The CM must compensate the owner when the construction does not meet up with the terms in the contract. Usually performed under a cost plus fixed fee with a Guaranteed Maximum Price (GMP) or not-to-exceed fee.

180
Q

Contracting Method, Self-Performance

A

The owner does most of all or the work (possibly including design) in-house. This is usually only appropriate for small jobs with limited scope, however, it benefits from not requiring some or all contracts which keeps costs down (no profit/overhead paid to a GC).

181
Q

Contracting Method, Separate Contracts

A

This is where the Owner is actually the General Contractor and will hire the designer, and then sub’s all themselves. Typically the Owner must be licensed as a GC or there will be complications when trying to pull permits. Usually only advisable if the owner has a competent construction manager to admin the project.

182
Q

Contractor

A

Anyone who contracts to provide the labor and services necessary to complete a project. When hired by an owner, they are considered the “prime contractor” but when hired by another contractor they are considered a “sub contractor”.

183
Q

Contractual Duty (Contractual Obligation)

A

The obligation which arises from a contract or agreement.

184
Q

Contribution

A

The sharing of a loss or payment among several debtors, or the act of one or several co-debtors in reimbursing one of their number which has paid the whole debt or suffered the whole liability to the extent of their proportionate share.

185
Q

Corporation

A

A legal entity that is formed by individuals for the purpose of conducting business. Once formed, it exists independently of the individuals that formed it and can carry on beyond the lives of those individuals. It also provides limited protection from liability (depending on state laws).

186
Q

Custom

A

A usage or practice of people which by common adoption or habit has become compulsory and has acquired the force of law. E.g. the custom of using a trowel to finish a concrete slab; the custom of a LA to monitor the construction phase of work unless the written contract has a clause deleting that requirement.

187
Q

Damages

A

Compensation which may be recovered in the courts by any person who has suffered loss, detriment, or injury, whether to their person, property, or rights through the unlawful act, omission, or negligence of another.

188
Q

Damages, Actual

A

Real, substantial, and just damages, or the amount awarded to a complainant in compensation for actual and real loss or injury.

189
Q

Damages, Compensatory

A

Repair or replacement of the loss caused by the wrong or injury and nothing more.

190
Q

Damages, Consequential

A

Damages that can be proven to have occurred because of the failure of one party to meet a contractual obligation. They go beyond the contract itself and into the actions garnished from the failure to fulfill.

191
Q

Damages, Delay

A

Loss suffered as a result of extended time from the original time stipulated in the contract. E.g. Owner agrees to not pay bank loan for 1 year during construction, construction runs longer and owner is forced to pay.

192
Q

Damages, Liquidated

A

Damages agreed to in the contract to be collected as compensation upon a specific breach (e.g. late performance)

193
Q

Damages, Punitive

A

Monetary compensation awarded to an injured party that goes beyond that which is necessary to compensate the individual for losses and that is intended to punch the wrongdoer.

194
Q

Dedication

A

Mutual Agreement; Granting by the owner the use of private property for public use (highway, street, park, school, etc.). If the public has been grated this right for a long period of time, the owner will not be able to deny continued use. However, if that public use stops, the private owner has free use of the property again. With dedication, the land remains under the ownership of the private citizen (no transfer of title).

195
Q

Default

A

An omission of that which ought to be done or a failure to perform a legal duty.

196
Q

Demurrer

A

An allegation of a defendant which, admitting the matters of fact alleged by the bill to be true, shows that they are insufficient for the plaintiff to proceed upon or to oblige the defendant to answer.

197
Q

Design Documents, Ownership of

A

Ownership should be established in the contract, however, if NOT listed there then the Designer retains ownership. EXCEPT in Public Works projects.

198
Q

Deviation

A

A change made in the progress of work from the original terms, design, or method agreed upon.

199
Q

“Differing Site Conditions” Clause (Changes Conditions)

A

In the event that the physical conditions at the site of the work vary materially from those in the design or reasonably anticipated and in a manner which increases the time or cost of performance, the contractor is entitled to additional compensation or extension of time.

200
Q

Disclaimer

A

Any statement intended to specify or delimit the scope of rights and obligations that may be exercised and enforced by parties in a legally recognized relationship.

201
Q

Disclosure

A

The process of revealing evidence held by one party to an action.

202
Q

Discovery

A

The efforts of a party to a lawsuit to obtain information before a trial through demands for production of documents, depositions of parties, written interrogatories, written requests for admission of fact, examination of the scene, etc.

203
Q

Document, Documentation

A

Instruments which record matter which may be evidentially used; deeds, agreement, title papers, letters, receipts, and other written instruments used to prove facts.

204
Q

Drawings, As-Built and Record Set

A

As-Built drawings represent changes to the design based on actual site conditions. The Record Set is the original set of plans on which the bid was made. The record set is useful in litigation as it will be used to compare what was actually constructed with what the contractor originally anticipated.

205
Q

Duty

A

An obligation that a Landscape Architect is bound or required to perform

206
Q

Duty, Protection of Public Health

A

An obligation to not manipulate the environment to causes conditions that endanger the health of the public (not just the client, but anyone)

207
Q

Duty, Protection of Public Safety

A

An obligation to provide sufficiently sound construction design that can support the use intended

208
Q

Duty, Protection of Public Welfare

A

An obligation to preserve the economic value and natural resources of land

209
Q

Economic Loss

A

Additional cost incurred by an individual other than property damage or personal injury.

210
Q

Eminent Domain

A

The right of the government or public agency to take possession of private property for public use. The property can only be taken after the landowner has proper notice and been give time to make a case against the seizure of the property. Also, the landowner must receive fair compensation for the seized land, the quantification of which must be determined through judicial proceedings.

211
Q

Engineer

A

A person with a particular expertise in a limited area of design and may specialize in structural, mechanical, electrical, civil, or plumbing design. Typically the only deal with a small subset of the project, while a LA may deal with the broad scope. In some cases the role may be reversed (such as industrial or municipal work (e.g. roadway)) in that the engineer will be the prime and the LA will be the sub.

212
Q

Equitable Doctrine

A

Equity = Fairness and Doctrine = a legal rule or principle

213
Q

Equity, Court of

A

Originally separate from courts of law, but handled lawsuits and petition requesting remedies other than damages such as writs, injunctions and specific performance. The Bankruptcy court is an example of a court of equity.

214
Q

Estimating Cost of Construction

A

While performing this task, existing site conditions, the scope of work related to the proposed design, the project schedule, and the anticipated cost of materials all have an impact.

215
Q

Exclusivity of Contract Provisions

A

Part of a contract that restricts the signer from buying , selling, promoting, using portions of design, or even working for anyone other than the person or company listed in that contract. Typically used to state that the design used on a project may not be reused elsewhere.

216
Q

Exculpatory Language

A

Clause in which a party who may suffer a loss agrees not to institute legal action against the party who may cause the loss. Indemnification clauses and disclaimer clauses are examples. E.g. No-Damage-for-Delay Clauses state that if anyone causes a delay for the contractor (other than the contractor themselves) only a time extension of that lost time will be recouped, the contractor can’t seek damages.

217
Q

Expert Witness

A

A person processing special or particular knowledge acquired from practical experience.

218
Q

Expressed Warranty

A

A promise created that clearly stated either verbally or in writing what is to be covered by the warranty.

219
Q

Fast Track Method

A

A way of organizing a design program which allows the contractor to begin construction on earlier phases of the project before the plans are completed for the entire project. As changes may result when going from phase to phase, provisions must be included in the contract to compensate the contractor for additional work.

220
Q

Fiduciary

A

A person or organization who is responsible for managing money or property for another person or organization.

221
Q

Field Engineer

A

An engineer assigned to a project during the construction phase and located at the project on a full-time basis.

222
Q

Field Order

A

A document issued by the LA directing the contractor to perform in a manner different from that described in the plans and specifications. It is issued when the modification will not affect the money and/or time spent on the project.

223
Q

Finality of Decision

A

A contract provision or legally recognized process which states that the decision rendered in the settlement of a dispute is final. E.g. an arbitration decision is final.

224
Q

“Flow-Down” Clause

A

In a contract between a sub and the prime contractors, the performance of the sub will be tied to the prime in the same manner as the prime’s performance is tied to the owner. Where a sub might perform a greater duty than the prime, the sub has the same contractual requirements as the prime has to the owner.

225
Q

Foreign Corporation

A

An organization not incorporated in the state or jurisdiction in which it is performing work. A contractor must meet the legal requirements of the state in which it is performing work (i.e. they may be required to obtain a license for work in that state).

226
Q

Four-Corner Rule

A

(being replaced by parol evidence rule) states that a contract that is complete and unambiguous on its face must be interpreted according to the terms of the written agreement itself. In a court of law a person may not state oral or implied evidence that contradicts what is written in the contract.

227
Q

Fraud, Fraudulent

A

The description of a willful act commenced with the Specific Intent to deceive or cheat, in order to cause some financial detriment to another and to engender personal financial gain.

228
Q

General Contractor

A

The builder of the portion of the building which is considered the general portion not to be confused with the ‘prime’ contractor.

229
Q

Guarantee

A

A promise to answer for payment of debt or performance of an obligation if the liable person fails to make payment or perform the obligation.

230
Q

“Hold-Harmless” Clause

A

A promise to pay any costs or claims which may result from an agreement. i.e. an unknown lawsuit stems from the situation and the owner agrees to cover the costs

231
Q

Immunity

A

Exemption from performing duties which the law generally requires others to perform.

232
Q

Implied

A

Where the intention is not by an explicit and direct word but is gathered by deduction from the circumstances.

233
Q

Implied Agency

A

An agency relationship created by an act of the parties and deduced from proof of other facts.

234
Q

Implied Contractual Provisions

A

Items that a court will assume are intended to be included in a contract, even though they are not expressly stated. Typically to rely on a court’s interpretation of ‘implied’ terms is not desired, as such contracts are usually very lengthy.

235
Q

Impossibility of Performance

A

An ‘out’ in a contract when a task is physically impossible to perform. 3 factors must be true: 1) the impossibility must be in the act itself and not just because of the way the contract is worded 2) it must not have been foreseeable before starting the project 3) the person seeking to be excused from the act must not be responsible for the impossibility

236
Q

Impracticability, Commercial

A

The doctrine that recognized that in some cases contract performance may become so costly that its impracticability makes it the equivalent of impossibility.

237
Q

Imputed Knowledge

A

The understanding charged to a person because the fact in issue were open to discovery and it was that person’s duty to know them. E.g. a stores stairway is broken and a patron gets injured by walking on them, it was the owners duty to know that their own stairway was safe so that knowledge of the defect is imputed to the store owner.

238
Q

Incorporated Papers

A

When one contract refers to another instrument where the terms and conditions of that become a part of the original contract, the 2 in combination become the agreement of the parties.

239
Q

Indemnification

A

A process of one party compensating another party for losses that they have incurred or will incur as related to a specific incident.

240
Q

Independent Contractor, Principle of

A

Client enters into a contract with a contractor for construction of a project, contract doesn’t state how the contractor does his/her job but the specific results that they must produce. The contractor is thus independent of the client in the means utilized to produce the specified result.

241
Q

Independent Contractor, Relevance of Independence

A

The LA as agent for the client must refrain from exercising control over the means that a contractor uses to product the result. So telling a contractor that they are doing something wrong and letting them handle the means to fix that issue rather than talking directly to their sub-contractors or workers. Doing the latter may change the status of the Contractor from Independent to Employee making the Client responsible for carelessness and injury rather than the ‘Independent Contractor’

242
Q

Injunction

A

An order written by a court forbidding a person or company from performing some act.

243
Q

Inspection Team

A

The inspectors assigned to a project for the purpose of carrying out the quality control plan.

244
Q

Insurance

A

A contract where for a stipulated instance, the insurer or underwriter will compensate the insured for loss.

245
Q

Insurance, Builder’s Risk

A

During construction, damage to a structure (caused by fire or some other means) is covered through builder’s risk insurance and not insurance obtained by the owner. It is the General Contractors (not the owner’s) responsibility to obtain this insurance.

246
Q

Insurance, General Liability

A

A type of insurance that provides protection from third-party lawsuits including property damage and bodily injury. This does not, however, protect the contractor’s own property. There are 2 types of coverage: 1) Occurrence-based which provides for claims that arise during the policy period regardless of when the claim is actually filed (e.g. you breath in toxins while the policy is active, but the effects do not manifest till 2 years later once the policy has already expired. You can still claim since the damage occurred during the policy). 2) Claim-made which provides protection only for claims that are filed during the period when the policy is in effect. This is obviously a cheaper type of insurance to purchase.

247
Q

Insurance, Retrospective Rating Plan (Cost-Plus)

A

Usually only an attractive type of coverage for very large firms. The firm will pay a premium estimated at the beginning of the year (‘cost’). The estimate will be based on # of employees, hours worked, etc. Then at the end of the year, the total of actual claims will be figured and an amount will be paid (‘plus’) to cover this. On a year with very little claims, this can be a very cheap type of policy, however, on years with lots of claims this can end up costing the contractor more then a regular policy.

248
Q

Insurance, Umbrella Excess Liability

A

Coverage that extends the limits of liability coverage. It is essentially a separate insurance policy that uses the limits of the basic liability policy as the deductible amount.

249
Q

Insurance, Workers’ Compensation

A

Enacted in all 50 states, compensation is granted for disability and medical treatment for injuries resulting from accidents occurring as a result of employment, regardless of fault. However, compensation does not provide blanket coverage. So if a worker is intoxicated or guilty of willful misconduct, they will not be covered.

250
Q

Insurance Terms - Certificate of Insurance

A

A means by which a contractor can demonstrate to the owner that specific forms of insurance have been obtained.

251
Q

Insurance Terms - Direct and Indirect Funds

A

Direct funds are visible or readily identified as being related to insurance. So a contractor may get a large dividend check for the year from their insurance company, and believe it’s loss prevention program must be working for them to get such a large check. However, they may be failing to notice the Indirect expenditures of their insurance premium (since they have simply gotten used to it as something they pay without thought (i.e. a necessary evil)). This premium might add up to 10 times the amount of the supposed “large dividend check” but since the premium is an Indirect fund this issue might not be noticed.

252
Q

Insurance Terms - Dividends

A

If an Insurance company takes in a lot of premiums but does not have to pay out much during the year, they would be left with a surplus of cash. They may opt to return portions of this surplus to clients with relatively low losses. This return is called a dividend and are usually paid on an annual basis if the company offers this feature. However, note that even if they offer this feature in their policy’s, they are under no obligation to pay and if they have a bad year will not pay anything generally.

253
Q

Insurance Terms - Loss Ratio

A

A ratio between the costs for handling the insured’s claims divided by the total insurance premium paid by that company. An insurance company will be reluctant to provide insurance coverage to a client whose loss ratio is 1.00 or higher.

254
Q

Insurance Terms - Premiums

A

The money paid for an insurance policy, payment of which guarantees that the policy will be effective for a stated period of time.

255
Q

Insurance Terms - Reserves

A

An estimated amount of money set aside to pay for claims that may extend into the future with unknown cost impacts. E.g. someone gets hurt and it takes months for them to heal with an unknown amount of doctor visits, etc.

256
Q

Insurance Terms - Self-Insurance

A

If available in their profession or allowed in their state, a company can act as its own insurance company. Laws stipulate that to qualify for self-insurance, a firm must meet certain minimum standards, particularly in the area of financial stability (a careful investigation must be conducted to demonstrate this stability).

257
Q

Insurance Terms - Subrogation

A

Means the substitution of one person for another in claiming a lawful right or debt. So if the insurance company pays on a claim, it gains the insured’s right to sue. E.g. Insurance company pays a contractor for damages caused by a sub-contractor, through subrogation the Insurance Company now has the right to sue the Sub-contractor for recovery of the money paid out to the contractor.

258
Q

Interference

A

The act of hampering the affairs of others. If the acts of an LA or owner interrupts work of a contractor, they may file suit for interference. However, the court will most likely require that the interference be intentional and not merely negligent.

259
Q

Invitation to Bid

A

A solicitation for competitive offers on behalf of contractors to a procuring agency or owner. The invitation is not an offer to contract, but is simply a request for offers.

260
Q

Joint-Venture

A

An agreement whereby individuals act in concert to provide a specific goal for profit that is limited in duration (e.g. LA and Civil work together on a parking lot)

261
Q

judicial

A

Belonging to the office of a judge, as in a judicial authority, a court of justice, a judicial writ, or a judicial determination.

262
Q

Judiciary

A

Pertaining or relating to the courts of justice, to the judicial department of government, or to the administration of justice

263
Q

Landscape Architect

A

The person or organization licensed by the state, hired by the owner to design the project whose duties consist primarily of the production of the plans and specifications from which the project will be constructed. The LA may also preside at the bid opening, monitor the construction process to assure the owner’s interests, and approve payments to the contractor. The LA’s relationship to the owner is that of an independent contractor.

264
Q

Latent

A

Hidden or not apparent. E.g. a latent defect would be a fault that could not have been discovered by a reasonably through inspection.

265
Q

Liability

A

Responsible or answerable in law; legally obligated. If you are liable for a fault, you are responsible.

266
Q

Libel

A

The intentional injury to the name and reputation of another through WRITTEN communication (May be grounds for a lawsuit). NOTE: Must be intent to injure, it must be untrue, it must be told to another person, and there must be injury

267
Q

License

A

Certificate or document which gives permission to do some act

268
Q

Lien

A

A legal claim placed on property giving the party filing the lien the right to retain possession of the property until a debt payable is satisfied.

269
Q

Lien, Mechanic’s

A

Liens designed to protect workmen, materials, supplies, contractors, subcontractors and LAs. They arise out of failure to pay for the work done to increase the value of the property through design, labor, services performed, or materials incorporated into. NOTE: In some states a professional can’t claim a lien for professional services since these are not defined as labor.

270
Q

Lien, Partial Waiver of (partial release of)

A

A document used to certify that a portion of the total amount due to a subcontractor has been paid and there-fore can not be used as a basis for a lien against the property.

271
Q

Lien, Process of obtaining release of lien rights

A

Sub supplies material/labor -> Sub issues Notice to Owner to secure lien rights -> Owner pays GC for labor and materials… at this point either the GC pays the Sub or the Lien process can begin -> IF sub is paid, then sub signs a waiver of liens (partial or full release) for owner

272
Q

Lien, Tax

A

The right of the government to retain possession of property until the tax on it has been paid. If not paid when sold, the lien transfers to the new owner. If the debt remains unpaid, the government can force the sale of the property in order to collect the tax.

273
Q

Lien, Waiver

A

A document issued upon completion of work signifying that all monies have been paid and that the right to lien against the property is removed.

274
Q

Lien (variant - Stop Notice)

A

A stop notice permits a works, materials supplier, or subcontractor to notify the owner when a general contractor has failed to make payments for labor and/or materials. Upon receipt, the owner will make no further payment to the GC until the claimant has been paid. This is typically used for public property projects where the land only has value to the city and can’t be sold to recoup damages (i.e. no one is going to buy a Library to satisfy a lien)

275
Q

Litigation

A

Avenue of resolving conflicts that arise in practice with disputes being settled in a court of law.

276
Q

Malpractice

A

An action initiated by the client arising due to an alleged failure on the part of the LA to competently provide the services of the profession.

277
Q

Malfeasance

A

It is not a distinct crime or tort but may be used to generally describe any act that is criminal or wrongful.

278
Q

Mandamus

A

A writ or order that is issued from a court of superior jurisdiction that commands a lower court, corporation, or individual to perform or not perform a particular act, the performance or mission of which is required by law as an obligation. E.g. a public body is withholding the execution of a contract, a writ of mandamus may be applied to compel that body to act.

279
Q

Mandate

A

A judicial order (written or oral) from a court; or a direction that a court has the authority to give and an individual is bound to obey. Alternately it can be used synonymously with the term Power of Attorney in which it is an act which one individual empowers another to conduct transactions in that person’s name.

280
Q

Mandatory Clauses (Mandatory Provisions)

A

Clauses which must appear in the contract writing due to their legal status as a federal, state, or local law.

281
Q

Master Plan

A

A long-term planning document that provides a conceptual layout to guild future growth and development.

282
Q

Material Variance

A

A deviation from that which was specified in the original contract documents. In a bid process a material variance is one that gives a bidder a substantial advantage or benefit over other bidders.

283
Q

Mediation

A

A nonbinding method of dispute resolution that contains elements of negotiation and arbitration. However, unlike arbitration if the mediation fails, the fight can still go to court.

284
Q

Meeting of Minds

A

A phrase in contract law used to describe the intentions of the parties forming the contract. In particular, it refers to the situation where there is a common understanding in the formation of a contract, i.e. nothing is kept secret by one party

285
Q

Merchantability

A

The warranty of merchantability is implied, unless expressly disclaimed by name or the sale is identified with the phrase “as is”. To be merchantable, the goods must reasonably conform to an ordinary buyer’s expectations, i.e. they are what they say they are.

286
Q

Misrepresentation

A

An assertion by words or conduct that is not in keeping with the facts and is a tort or civil wrong that can create civil liability if it results in loss. E.g. a real estate agent owns swampland but advertises it as commercial property. If a person buys it while relying on the professionals statement that it is in fact commercially valuable, the buyer may sue for monetary losses resulting from the purchase.

287
Q

Mutuality of Assent

A

An acting by two parties to perform a duty toward each other. E.g. in a contract mutual assent is often established by showing an offer and acceptance (signing of the contract).

288
Q

Negligence

A

A failure on the part of one person to exercise sufficient care or precaution to protect the health and safety of another person. This can be in the performing of an act or even the performing of an act that is not reasonable to perform.

289
Q

No Damage for Delay

A

A clause in a contract which grants a party an extension of time but does not reimburse that party for any additional costs suffered during that time.

290
Q

Nuisance

A

A wrong committed against the real property (i.e. land) or personal property owned by another that does NOT involve entry upon the land, but causes physical discomfort to the landowner (e.g. noise levels due to a design on an adjacent property)

291
Q

Null and Void

A

Of no validity or effect. E.g. a contract can be considered voided if a professional is not licensed to perform in a certain state, then they do not have the capacity to execute the contract in that state which makes it null and void.

292
Q

Nullity

A

An act which the opposite party may treat as though it had not taken place or which has absolutely no legal force or effect.

293
Q

Offer

A

An act on the part of one party whereby it gives to another the legal power of creating the obligation called a contract. A request for a proposal is not an offer, but the proposal submitted in response is. A request for bids is not an offer, but the proposal submitted in response is. There must be a clear acceptance of the offer by the other party.

294
Q

Option

A

A choice, usually in construction it is presented to the building contractor in the form of materials and/or methods which it may choose in order to meet other requirements of the contract. It has no effect on the cost to the owner.

295
Q

O.S.H.A. (Occupational Safety and Health Act)

A

A federal act creating an agency responsibly for safety and health in the work place.

296
Q

Overhead

A

The costs associated with operating and maintaining an office. E.g. office supplies, leasing an office space, in-house printing, new telephones, etc.

297
Q

Owner

A

The party that will take title to the property when it is completed.

298
Q

Parol Evidence

A

Verbal evidence, e.g. testimony of a witness at trial.

299
Q

Parol Evidence Rule

A

If an agreement between two parties is made in writing, the parties may not present evidence in court of any oral or implied agreement that contradicts what is written down.

300
Q

Partnership

A

A relationship whereby two or more individuals agree to provide services in business for profit. They must have a common business purpose, share in profits and loses, they will share in the legal liability of partners for business decisions of partners, can share ownership of property, and has unlimited liability to creditors. NOTE: While the owners must pay income tax, the partnership itself does not.

301
Q

Partnership, Dissolving of

A

A partnership can be dissolved by any of several means: The death of a partner constitutes automatic dissolution unless provisions are made that the surviving partners will purchase that partners interest in the company; Bankruptcy; a duration provision in the articles of partnership; the mutual agreement of the partners; if one of the partners is judged to be insane; if one of the partners decides to withdraw; a court decree; a change in the partnership which will dissolve the original partnership; or expulsion of a partner for just cause.

302
Q

Partnership, Dissolving of (disbursement of funds)

A

Priority of disbursement is as follows: 1. Outside creditors are paid first, if the partnership doesn’t have enough money to cover, the partners must cover the rest out of pocket. 2. The repayment of loans or advances to the partnership made by any of the partners (beyond the initial capital to startup the company). 3. Each partner’s capital investment. 4. Anything left is split between the partners unless otherwise specified in the partnership agreement.

303
Q

Partnership, General

A

Each partner is an agent of the partnership, has the power to enter in binding contracts in the name of the partnership, and may be used to regulate some aspect of the powers available to each partner.

304
Q

Partnership, Limited

A

A limited partner generally contributes some tangible asset to the partnership (cash or real estate) and shares in the profits and losses of the business. However, unlike in a general partnership, a limited partner provides no services, has no management role, and their liability is limited generally to no amount greater than the amount of the investment made in the firm.

305
Q

Partnership, Silent

A

A silent partner is a person who is a partner in a firm but remains unknown to the public. They are not active in the management of the regular business affairs of the company and will remain anonymous.

306
Q

Patent/Latent Test

A

Determines weather the danger which caused the damage was latent (hidden) and beyond the control of the observer. E.g. At the time of building turnover to the owner, if the danger can be observed but the owner doesn’t make the contractor aware, the owner will be held responsible for any future damage, however, if the danger is latent and not observable by the owner, then the contract will be held responsibly for any future damage.

307
Q

Plaintiff

A

A person or organization which brings action or which complains or sues.

308
Q

Plans vs Specifications

A

On a private project, unless stipulated otherwise in a contract, the information shown in the specifications should prevail over that shown in the plans when conflicts arise between the 2 documents. However, during a public project, the majority of the contracts dictate that plan information should prevail over that shown in the specifications.

309
Q

Post-Construction Evaluation

A

Evaluations used to determine if the design as it was built meets the needs of the owner and site users. As such, they can provide the design team with valuable feedback and help them understand what aspects of their design were successful and what aspects could be improved in the future.

310
Q

Practice, Private

A

Application of the skills, knowledge and abilities of the LA on behalf of a private client that is generally operating for financial profit.

311
Q

Practice, Public

A

Services are delivered through employment by a unit of government. May be administration, design, analysis, or policy formulation.

312
Q

Practice Laws

A

Laws which prohibit non-licensed individuals from providing or advertising the services of a LA.

313
Q

Precedent

A

A principle of law actually presented to a court of authority for consideration has been declared to serve as a rule for future guidance in the same or similar cases. Matters that only appear in the record and are not directly decided are NOT a part of this.

314
Q

Prescription

A

A hostile acquisition; The acquisition of property that has been used by the public for a certain period of time (falls under state law so time frame differs from state to state). E.g. a private road is being used for 7 years by the public, proceedings can be followed to acquire the road as public property after that amount of time.

315
Q

Prime Contractor

A

The party signing a contract with another party to directly perform the work required by that contract.

316
Q

Privity

A

relationship of 2 parties to a particular transaction. E.g. a contractual relationship between the owner and design professional and the owner and the contract constitute privity, however, there is NO privity between the design professional and the contractor.

317
Q

Privity (No Privity Rule)

A

A rule from the 1800’s which left a 3rd party out from a lawsuit because there was no privity between them and the contracting parties. Has more recently given way to the notion of third party liability.

318
Q

Project

A

A unique set of activities planned with consideration to limited resources, expecially time and budget, and executed in order to produce a defined outcome that can be assessed against the original scope.

319
Q

Project Closeout

A

The primary goal of project closeout is to ensure the quality of the completed project, despite the contractor’s desire to closeout as fast as possible.

320
Q

Project Management

A

A system of organizing a construction project from conception to the completion of the project and includes management of the preparation of the contract documents, the bid process, and the construction phase. Has the ability to improve communication and the working relationship between all Major parties of a contract (Owner, Desiger, Contractor).

321
Q

Project Management (Ramroth Info)

A

5 Phases of a Project: Start - Planning - Design - Production - Clouseout 6 Activities of Project Management: Defining - Planning - Directing - Coordinating - Monitoring - Learning

322
Q

Project Work Plan

A

Consists of Project Objectives, Project Team, Project Schedule, Project Task and Budget, Quality Control Procedures

323
Q

Proprietorship, Sole

A

A proprietorship is owned by an individual, require no formal documents for its establishment and can be discontinued at will at any time.

324
Q

Protest

A

A formal declaration whereby a person expresses a personal objection or disapproval of an act. It is usually made to save some right that would be waived unless they stated their negative opinion formally.

325
Q

Quality Assurance

A

Policy in regard to assuring that quality will be achieved on a project.

326
Q

Quality Assurance Plan

A

A plan to implement the policies stated in the quality assurance statement of an organization.

327
Q

Quality Control

A

The implementation of the quality assurance plan, usually during the construction phase.

328
Q

Quality Control Group

A

A group of personnel assigned to implement quality control during the construction phase.

329
Q

Quality Control Plan

A

An implementation plan for application of the quality assurance policies during the construction phase.

330
Q

Quasi-Judicial

A

The action taken and discretion exercised by public administrative agencies or bodies that are obligated to investigate or ascertain facts and draw conclusions from them as the foundation for official actions. A LA may act in a quasi-judicial role when settling a dispute between the owner and contractor. In this role, that designer is granted immunity.

331
Q

Reciprocity

A

The practice of exchanging things with others for mutual benefit, especially privileges granted by one country or organization to another.

332
Q

Recovery

A

The acquisition of something of value through the judgement of a court, as the result of a lawsuit initiated for that purpose. E.g. you might obtain recovery in the form of damages for an injury. Also can describe the amount collected itself.

333
Q

Redress

A

receiving satisfaction for any injury sustained; compensation for injuries sustained.

334
Q

Regulation

A

A rule or order prescribed for management or government, they must be adhered to or a citation will be issued for their violation upon detection.

335
Q

Reject Any and All Bids

A

A provision of most invitations to bid for both public and private works that allows the owner or contracting agency the right to reject any and all bids. Some states require just cause while others do not require any reason for rejection.

336
Q

Representative

A

One who stands in the place of another, usually as executor or administrator but not as an agent.

337
Q

Retainage

A

An amount of money established by a fixed percentage agreed to in the contract that is withheld by one party from the other as a means of security and/or assurance of performance. E.g. the owner may withhold 10% of the amount paid on the progress payments until 50% of the work is completed. Then they discontinue withholding the retainage.

338
Q

Right-Of-Way

A

A right-of-way (ROW) is a tract of land usually consisting of a series of connected parcels of property that is used for the operation of a road or public utility. General rule is that all parcels must be adjacent and that no gaps may exist in the tract. While ROW generally consists of an actual transfer of land title, an alternate for it is an “easement” which states the limited and specific use of a piece of property (e.g. underground sewer line - once in place above ground activities are not affected).

339
Q

Rights of Lateral and Sub-Adjacent Support

A

The right of an owner to have land supported by adjacent lands (i.e. the grades on your property can not be altered to cause damage to adjacent property). E.g. retaining wall on an adjacent property collapses because you excavate on your property and cause the subgrade to be washed out.

340
Q

Riparian Rights

A

The rights of ownership of land adjacent to both banks of a non-navigable stream. The owner of land adjacent to a stream has a right to the reasonable use of water flowing past the land.

341
Q

Risk-Shifting Techniques

A

Indemnification clauses, surety requirements (bonds), “no damage for delay” clauses, etc. Anything that minimizes risk to a party. E.g. the prime contractor can have a clause with their subs to only pay them once they have been paid from the owner.

342
Q

Schedule, Construction

A

After award of the contract and prior to starting work, the Contractor shall submit to the Owner a progress schedule or critical path schedule which shows the proposed sequence of work, and how the Contractor will complete the items of work within the number of working days set up in the contract. Contractor will confer with the Owner at regular intervals about the progression of work in accordance with the critical path schedule.

343
Q

Schedule of Values

A

Used as a management tool in monthly pay app processing and can be used to evaluate a projects progress as a completion percentage.

344
Q

Scope of Services, Programming

A

An analysis of needs of a project

345
Q

Scope of Services, Land Use Planning

A

Resource analysis, market studies, and feasibility studies

346
Q

Scope of Services, Master Planning

A

Generalized plan illustrating the major organization of a specific site plus other aspects such as general financing, market feasibility, phasing, location of major physical elements, etc. (e.g. a diagram depicting locations for commercial, mixed-use, residential areas on a proposed site)

347
Q

Scope of Services, Specific Studies

A

Studies which involve consultation on specific factors relevant to site inventories such as climate, soils, geology, hydrology

348
Q

Scope of Services, Management

A

Advising, organizing, and supervising of design teams (i.e. client designer relationship)

349
Q

Security

A

Protection against failure of performance, terms usually applied to an obligation. E.g. a bond is considered security against default.

350
Q

Service Contract

A

A contract that shows what specific items will be performed by a consultant (e.g. surveyor performing a survey, what info should be on the plan). Note that if once the survey is complete, if basic items are missing and they were NOT defined in the service contract, then a contract for Additional Services would have to be created to provide that info even if it was ‘assumed’ to have been part of the scope.

351
Q

Site Maintenance Plan

A

A document that takes into account current and future needs and addresses a variety of resource issues includeing things like maintenance budget, site energy and water use, the needs of the site users, future site uses, methods of dealing with invasive species, and even plant replacements.

352
Q

Site Plan

A

May show building footprint, travel ways, parking, drainage facilities, sanitary sewer lines, water line, trails, lighting, and landscape elements. Includes general specifications.

353
Q

Slander

A

The intentional injury to the name and reputation of another through VERBAL communication (May be grounds for a lawsuit). NOTE: Must be intent to injure, it must be untrue, it must be told to another person, and there must be injury

354
Q

Specifications

A

Written instructions to a contractor that supplement drawings. They define the standards of materials and workmanship that a contractor must produce, define the physical, technical, and operational aspects of a constructed design, they are given greater legal significance than drawings in the event of a conflict between spec’s and drawings. Together the specification and drawings form the technical requirements of a job.

355
Q

Specifications, All-Inclusive (To Be Avoided)

A

These items state something to the effect of “The intent of this spec is to provide…”. This means that the Architects ‘intent’ is to be construed from the drawings and specs, so a contractor is being asked to include items that were not shown because the Architect ‘intended’ for them to be there.

356
Q

Specifications, Incentive/Disincentive

A

The idea in which an owner will accept material of differing quality by paying more for higher quality work and less for lower quality work. E.g. compaction of subgrade, if the contract says an average of 90% compaction is sufficient the owner will pay the contract amount for that work. However, if the contractor goes further and does a 95% level of compaction, this would warrant a small increase to the payment per square footage of area done, while only doing an 85% compaction would result in a small decrease in payment per square foot. Then anything less than 80% would not be acceptable.

357
Q

Specifications, Closed

A

This spec ensures that only a specific type of item or system is used and does not have any flexibility to use an ‘equal’ item. As such this is generally only allowed in private construction as public projects require competition (i.e. an “or equal” standard). It can be either a performance or design spec. To be used in a public works project, a min. of 3 manufactures must be named which makes it an ‘open spec’, however, still restrictive.

358
Q

Specifications, Construction Standards

A

SEE CONSTRUCTION SPECIFICATION INSTITUTE FORMAT (CSI)

359
Q

Specifications, General Information about

A

For a spec to serve its purpose it must satisfy some basic criteria including: Technical accuracy and adequacy; Definite and clear stipulations; Fair and equitable requirements; a format that is easy to use during bidding and construction and legal enforceability

360
Q

Specifications, Open

A

Nonrestrictive in that they allow a wide variety of choices. This spec gives the contractor the widest opportunity to get the lowest prices for delivering the project.

361
Q

Specifications, “Or Equal”

A

A proprietary specification that has the words “or equal” after it. This should be avoided without showing what the ‘equal’ brands/models include. If this is used, there should be time allowed for contractor to submit products for approval before the bidding is finished.

362
Q

Specifications, “Or Approved Equal”

A

A more open spec in the it allows for all acceptable products an opportunity to be considered. This places the determination of the acceptability of the substitution directly with the Architect or Engineer.

363
Q

Specifications, Performance

A

A document that specifies the operational requirements of a component or installation, i.e. it must tell the contractor what the final installed product must be capable of doing, but not how to accomplish the task of meeting that standard. E.g. the installation of a pump for irrigation that must have a pumping rate of X, a pressure of Y, the temperature will be between A and B, and with a pH of Z; or the strength of concrete shall be 3,000 psi but NOT its finish or general workmanship.

364
Q

Specifications, Performance and Design (To Be Avoided)

A

Combing both a performance and design spec into one is generally a bad idea, as if the contractor follows the procedures as specified, they will not be bond by the performance portion of the spec. (e.g. the wall shall consist of 2x4’s spaced at 24” o.c. and shall support a vertical load of 500 lbs per lin.ft. - i.e. if 2x4’s 24” o.c. only supports 250 lbs/lin.ft. that’s not the contractors problem as they followed the design spec)

365
Q

Specifications, Proprietary

A

Spec’s that require the use of a single approved product type and are often used where there is existing equipment or installations already on site. AE’s typically avoid this spec due to it leading to the perception of favoritism toward a certain manufacturer and may eliminate competition during the bid phase, which may increase the project cost. This is a ‘closed’ type specification.

366
Q

Specifications, Prescriptive (Design Specs)

A

Provides a much more detailed explanation of the materials that the contractor must use and the means of installing those materials. These spec’s sit more of the project design control onto the shoulders of the AE and away from the contractor, and it provides more certainty regarding the final product composition than the performance spec. It will typically be formatted into 3 sections: 1) General - contains reference to national standards, design requirements, a list of submittals from the contractor to the Arch, quality control requirements and product handling requirements. 2) Products - describes in detail the various products required for the task along with the individual structural and performance requirements of each product. 3) Execution - explains how to prepare the materials and conduct the installation, including the testing requirements to be followed. NOTE: A contractor that follows the design spec’s to the letter, but the item being constructed fails, is NOT at fault. The owner must assume responsibility.

367
Q

Specifications, Reference

A

These are found in technical specifications and make items, established tests, or formal procedures a part of the contractor documents by reference. E.g. “this item to conform to ASTM-#”. Ref specs not only specify quality, they also set up a standard procedure by which the acceptability of the finished product can be determined.

368
Q

Specifications, Standard

A

An entire set of technical specs that have been developed by an owner. Once developed, they can be used for many similar projects and will apply to the entire industry (e.g. for building a highway, bridge, etc.)

369
Q

Specifications, Technical

A

These cover information that is not easily shown on the drawings, or if shown would clutter the plans with a great deal of text. These are to cover such topics like: quality of concrete, quality of workmanship, preparation of soil, compaction requirements, etc. They will follow the CSI format in many cases, and be shown in a standard format: General - which stipulates the ground rules for the work to be performed and defines the scope of work to be performed within the spec section; Product(s) - which describes the materials, equipment, accessories, components, fixtures, etc. and the development and manufacturing process to be used in producing them; Execution - which describes the preparation, workmanship, installation, erection, and application procedures to be employed along with quality requirements and performance criteria that must be satisfied.

370
Q

Specifications, Technical (Organization of)

A

They will be in a single binder (or 2-3 if too much material for just 1) and of this the technical spec will be in the later portion (can be more than half of the book). They typically follow a general order of the construction process starting with site-type items and conclude with the finish items.

371
Q

Standard

A

General recognition and conformity to established practice; a ‘standard’ of practice.

372
Q

Standard of Performance (Standard of Care)

A

Standard which a professional must exercise to the degree of care and expertise which a reasonably competent professional of the same discipline would exercise under the circumstances. The standard is established by the professionals working in the same geographic area.

373
Q

Statement of Probable Construction Costs

A

Term introduced by the A.I.A. in 1963 to help minimize the responsibility of guaranteeing the cost estimate. Prior to that time, ‘cost estimate’ was used.

374
Q

Statute

A

An act of legislature declaring or prohibiting something, these laws must be adhered to by all parties within that jurisdiction.

375
Q

Statute of Frauds

A

A statute that requires certain kinds of contracts to be put in writing or it may not be substantiated as legally binding in a court of law. However, certain aspects of oral agreements are legally binding within certain parameters established by the Uniform Commercial Code.

376
Q

Statute of Limitation ( See Also Warranty Issues)

A

Refers to the time to file a lawsuit for latent defects after it has been discovered. State specific and ranges from 1 year to 3 years.

377
Q

Statute of Repose (See Also Warranty Issues)

A

Generally a longer period of time than a statue of limitation, and it stipulates the time that the owner has to discover any latent defect after the completion of the project. This is state specific and can vary from a 4 year to 15 year time frame.

378
Q

Strict Liability

A

Absolute legal responsibility for an injury that can be imposed on the wrongdoer without proof of carelessness or fault. E.g. Owner of an animal that gets lose and causes damage to property. The owner can be held liable due to it being their responsibility to have keep control over the animal at all times.

379
Q

Subcontractor

A

A party which takes over portions of a contract from the principal (prime) contractor or another subcontractor. Most subcontractor contracts hold them to the same terms and conditions which are established in the prime contractor’s contract. Generally subs specialize in a specific building trade and as specialists they are licensed by the state in which they operate.

380
Q

Submittals

A

A way for contractors to submit information to the owner for their approval. This can be by way of cut sheets, working drawings, shop drawings, descriptive data, certifications, methods, calculations, material samples, test data, photos, and manufacturer’s instructions. The contractor must be certain that the product/method being submitted satisfies the spec’s, even owner’s approval will not release the contractor from liability for using that material.

381
Q

Substantial Performance

A

Where there has been no willful departure from the terms of the contract and no omission in essential points; only slight variances from the exact terms and/or unimportant omissions or minor defects. A simple test is whether the omission or defect can be compensated for with money. E.g. owner buys 80 acres but survey after the fact shows only 79.2 acres of land was sold. As long as this difference isn’t crucial to the sale (i.e. site plan was contingent on having 80 acres to work with) then it is considered ‘close enough’.

382
Q

Surety

A

A relationship where a party guarantees to pay the debts of another party. (e.g. a bond)

383
Q

“Suspension of Work” Clause

A

Clause in a construction contract which provides for the contractor should delays and interruptions in the contracted work be caused by the acts, or failure to act, of the contracting officer.

384
Q

Sweat Equity

A

A term that means ‘mutual help’. E.g. government provides housing for the Indians on a reservation and the Indians must contribute to the construction by giving their manual labor toward the project.

385
Q

Task

A

Defined by establishing an objective for the task, a timeline for the task’s completion, and the level of effort required to complete the task.

386
Q

Termination

A

To put an end to.

387
Q

Termination for Default

A

Specific provisions itemizing events of default, however, even if not itemized, delay in performance resulting in failure to complete the contract in a timely fashion is universally recognized as a breach of contract.

388
Q

Third Party

A

A party which is not a part of the contract but may be bound or benefited through a written or implied legal relationship.

389
Q

Third-Party Beneficiary

A

Someone who obtains a benefit as the result of a contract between 2 other parties. The contract must appear to be made and intended for the benefit and not just merely incidental.

390
Q

Third-Party Liability

A

A condition whereby a party to a contract may be held liable to a 3rd party by its negligent or fraudulent activity in performance of the contract. The 3rd party may recover damages where the circumstances are such that the transaction was intended to affect them and injury was foreseeable.

391
Q

Title Laws

A

Laws that prohibit a non-licensed individual from utilizing the title “Landscape Architect”

392
Q

Tort

A

A private or civil wrong or injury that occurs independent of a contract and are not criminal in nature. Because they do not involve contracts and are not explicitly criminal acts, they are often settled through common law interpretation. Torts generally result from a specific action or failure to act and, in this sense, violate social norms. For a tort to occur, four general conditions must be met: One party (usually the defendant) must owe another party a duty (generally the plaintiff), there must be a breach of performance of that duty, someone must be harmed by this breach of performance and there must be a clear relationship between the harm suffered and the breach of performance.

393
Q

Tort, Examples of a

A

Defamation of character through libel or slander; Unlawful entry onto another’s premises; Unwarranted seizure, alteration, or destruction of another’s property; Unauthorized use of another’s patents, trademarks, or copyrights; Violation of another’s freedom through nuisance and negligence; Failure to exercise care in the exercise of one’s duty to another.

394
Q

Tort Feasor

A

A wrongdoer; the one who commits or is guilty of a tort.

395
Q

Treble Damages

A

A recovery of three times the amount of actual financial losses suffered which is provided by stature for certain kinds of cases.

396
Q

Trespass

A

A wrong committed against the real property (i.e. land) or personal property owned by another that involves a physical entry upon the land without permission and causing damage (can be a person, or diverted water, or physical objects left on land, etc.)

397
Q

Turnkey Contract

A

A method of organizing a building project in which a contractor and a designer agree to provide a finished building at an agreed-upon price. Upon completion of the project, all the owner has to do is “turn the key” in the door. Most turnkey projects are built for the Department of Housing and Urban Development (HUD).

398
Q

Uncertainty

A

A state or quality of being unknown or vague; such vagueness in a written instrument (a contract) as to render it unintelligible to those who are called upon to execute or interpret it so that no definite meaning can be extracted from it.

399
Q

Unconstitutional

A

That which is contrary to the constitution. It can be used in 2 different senses; 1) that legislation conflicts with some recognized general principle or conflicts with a generally accepted policy. 2) legislation conflicts with some provision of the written constitution which it is beyond the power of the legislature to change.

400
Q

Unified Bid

A

In a multiple prime construction contract, solicitation for bids is presented to the bidders in several separate prime contract packages. The bidders are permitted to bid on either one or as many of the bid packages as are presented.

401
Q

Uniform Commercial Code

A

A body of laws which governs the sale of goods in almost every state in the US. Its use is rare in the construction industry except in the area of shipping, handling, and purchasing of materials for the project.

402
Q

Unjust Enrichment

A

Doctrine stating that persons shall not be allowed to profit or to enrich themselves inequitably at another’s expense. A typical example of this is when an owner withholds payment to a contractor for work already performed claiming that work is not acceptable. The value of the performed work far exceeds that portion which the owner considers unacceptable.

403
Q

Utilization Rate

A

the percentage of time a person spends doing billable work (NOT the billing rate)

404
Q

Waiver

A

The intentional or voluntary relinquishment of a known right. E.g. a change is made during construction that the LA approved and the owner agreed was needed, this action waives the requirement of a signature.

405
Q

Warranty

A

A promise that a proposition of fact is true.

406
Q

Warranty, Implied

A

According to the Uniform Commercial Code, a party who sells goods to another implicitly (without expressly saying so in writing) warrants that the particular product is fit for the particular purpose intended. This does not mean that a contractor has to guarantee that the completed project will be suitable for its intended purpose (i.e. they built what they were contracted to build by use of the plans provided by the owner). However, if the implied warranty is, for example, that a house built by the contractor will be habitable by the owner and then fails to be such… the implied warranty would require the contractor to fix this issue. HOWEVER… this does not generally apply directly to a designer. Warranties of professional services states that the work performed by the professional is consistent with the standards of the profession. Failure of the product (e.g. glass in a window, a concrete brick, an asphalt driveway) will NOT generally result in a liability for the professional if the work is consistent with the standards of the profession.

407
Q

Warranty, timing of

A

The warranty period can begin at substantial completion, final acceptance by the owner, or in some cases at the completion of work. It should be clearly defined in the contract which it is. E.g. a welder finished his work in June 2010 and the project is complete on December of 2010. Say there was a 5 year limit of liability on the welders work, but the contract said “at completion of work”. In November 2015 owner wants to file suit on the welders work, but court says the 5 years ended in June of 2015 not December.

408
Q

Warranty Issues - Latent Defects

A

Defects that cannot be readily observed, even through intensive inspection procedures. It is often only through destructive testing that such defects might be discovered. Since these are difficult to identify at the time of project acceptance, they continue to be the responsibility of contractors after the owner has begun occupancy. E.g. Soil subsidence (settling or sinking of the ground surface), improperly installed waterproofing that leads to water intrusion, etc.

409
Q

Warranty Issues - Patent Defects

A

Deficiencies that are clearly able to be observed or can be detected with a reasonably through investigation. They can generally be identified without doing any destructive work. E.g. door that is too high off the threshold, paint that is the wrong shade, concrete slab with improper slope, sidewalk that isn’t the right width, etc. Once the owner accepts the work by the contractor, it is generally assumed that the contractor has no further obligations for correcting patent defects.

410
Q

Warranty of Specifications

A

The owner’s implied warranty, when providing the plans and spec’s to a contractor, that they are possible to perform and are adequate for their intended purpose and free from defect. This is NOT overcome with the usual clauses requiring bidders to visit the site, check the plans, or generally inform themselves of the requirements of the work.

411
Q

Work Breakdown Structure (WBS)

A

It visually defines the scope into manageable chunks that a project team can understand, as each level of the work breakdown structure provides further definition and detail. Top level is the project itself, then the next level might be Internal work (Electrical, etc.) - Foundation Work (Excavation, Conc. Pour, etc.) - External Work (Masonry, etc.), then each lower level will be the parts of that work (so all the examples shown in the parentheses above). NOTE: It generally outlines an overall work plan for the project and may include things like financial/budgetary info, feedback and monitoring information.

412
Q

Work Plan

A

A document that outlines the plan used to complete a project with a set timeline and budget. Generally done before coming up with the actual Construction Budget.

413
Q

Zoning or Zoning Ordinances

A

Specify locations for various land uses or established instances in which different land uses must occur. Can establish the relationship between various land uses and publish right of way, etc. May also control design details such as planting, signage, color, and style of design. NOTE: Innovations in zoning in some states approach land use regulation based upon environmental considerations rather than use factors

414
Q

During the problem definition stage of a project, the landscape architect should accomplish which of the following? Choose all that apply.

A

a. Define the client and the user.
b. Ensure the designer’s values take precedence in the event of client-user conflict.
c. Establish a problem definition that will not vary.
d. Determine the type of solution expected.

415
Q

When writing a grant proposal to a governmental agency, which of the following should

be the initial step?

A

The initial step in writing a grant proposal to a govt agency should be:

b. Review of relevant literature.

416
Q

A contractor will most often be given compensation for which of the following? Choose all
that apply.

A

A contractor will most often be given compensation for:

NO - a.. A cause that neither the owner nor the contractor have any control.

Yes -b. An increase in the scope of work.

Yes - c. A delay in decision making on the part of the owner.

Yes - d. A delay due to a defect in the plans and specifications.

417
Q

Registered landscape architects shall limit their services to

A

ALL OF THESE ITEMS

a. those aspects of the profession for which they have expertise.
b. areas defined in the licensing law.
c. areas addressed in their education.
d. areas that are practiced by registered landscape architects in the region.

418
Q

Six project management goals

A

1) To reach the end of the project
2) To reach the end on budget

3) To reach the end on time
4) To reach the end safely
5) To reach the end error free
6) To reach the end meeting everyone’s expectations

419
Q

5 basic phases Project Management

A

1) Start
2) Planning

3) Design
4) Production
5) Closeout

420
Q

Six fundamental project management activities

A

1) Defining
2) Planning

3) Directing
4) Coordinating
5) Monitoring
6) Learning