L8 Flashcards

1
Q

What is resource levelling?

A

When activity start and finish dates are adjusted based on resource constraints.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is an impact of resource levelling on the critical path and why?

A

Usually it increases in length because it’s more realistic

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Why do we need to load resources onto a project as and when they’re needed?

A

Otherwise you waste money

If people are idle it’s bad for team morale.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Why hire someone with multiple skills over the best technical person?

A

It helps with uncertainty in projects. They can adapt and solve problems when things go wrong.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Why hire people slowly and fire people quickly?

A

Make sure it’s the right person otherwise they’ll be a dead weight and bring down the whole productivity.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What are the main 6 challenges in resource allocation?

A
  • there may be a mismatch between resource needs and availability.
  • start/end dates might need adjusting
  • actual/estimated costs may differ
  • domino effect
  • cost to expedite project
  • project scope may be challenging to fit exactly
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What are 7 rationale for how to allocate resources?

A
  1. asap (first come first serve)
  2. As late as possible
  3. Shortest task first
  4. Most resources first
  5. Minimum slack first
  6. Most critical followers
  7. Most successors
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Reasons to adopt an as soon as possible approach to resource allocation?

A
  • critical chain
  • future is uncertain: money, resources
  • optimism at the start
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Reasons to adopt an as late as possible approach to resource allocation?

A
  • rainy day
  • break-downs
  • flexibility
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Reasons to adopt a shortest task first approach to resource allocation?

A
  • progress and morale
  • release resources
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Reasons to adopt a most resources first approach to resource allocation?

A
  • black cloud, free
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Reasons to adopt a critical chain approach to resource allocation?

A
  • minimum slack first
  • most critical followers
  • most successors
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

How do you go about creating a resource schedule?

A
  • do CPM/PERT analysis as a baseline
  • move activities around to level up resources
  • use 1+ priority rules
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Why is it good to use priority rules?

A

It’s transparent and easy to communicate

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Benefit of using optimising software to find the best resource allocation schedule:

A
  • finds the best solution
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Drawbacks of using optimising software to do resource allocation?

A
  • not all projects can be optimised
  • untransparent
  • sensitive to inputs (needs redoing if something changes)
  • Inflexible
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Advantages of resource levelling:

A
  • less hands-on management is required
  • improves morale: consistency
  • helps manage schedule effectiveness
18
Q

Why do we do risk management?

A
  • there is uncertainty in all projects
19
Q

What are the two types of uncertainty?

A

Risk (-)

Opportunities (+)

20
Q

What is meant by risk?

A

Undesired effects or significant losses

21
Q

What is meant by uncertainty?

A

Limited knowledge (lack of certainty) about current/future outcomes.

22
Q

How do we go about risk management? (Steps)

A
  1. identify risks
  2. assess risks (how likely, impact, prioritise)
  • mitigate risks
    3. Risk response development (strategy to reduce possible damage/ contingency)
    4. Risk response control (implement risk strategy, monitor and adjust plan for new risks, change management)
23
Q

What is an example of uncertainty of current state?

A

What your rivals are working on right now.

24
Q

What’s an example of a recent global opportunities?

A

Investing in renewables after war

Work from home = resilience

25
Q

When do you do risk management?

A

Before you select a project.

26
Q

Junior PMs don’t have prior risk experience, so who do they go to to learn from the past?

A

The PMO

27
Q

What model can we use for risk management?

A

Stage gate model

PESTEL & MODeST (to come up with risks)

28
Q

What are some examples of risks?

A
  1. Technology (phone catches fire)
  2. Geographically dispersed team (language barrier, time zone)
  3. Lack of detail (first-timer projects)
  4. Limited options
29
Q

Does risk increase or decrease as the project goes on?

A

It decreases but the cost of the risk increases!

30
Q

What are the 2 types of risk?

A

Variability risk

Ambiguity risk

31
Q

What is a variability risk?

A

It happens so often that you can assign a probability to their likelihood of happening. Eg a machine breaking down.

32
Q

What is an ambiguity risk?

A

You cannot assign a probability to the risk. Eg what are competitors doing?

33
Q

How can we mitigate when a risk is ambiguous?

A

Think of the worst case scenario and have some contingency plans.

Hire specialist consultants.

34
Q

What part of the project would risk response control be used?

A

In the execution stage of the project.

35
Q

What gets affected by risk?

A

Time (misestimation, unavailable staff)
Cost (over budget, price increases)
Scope (changing/ vague scope)
Health and safety
Legal

36
Q

Where can you go to to find project risks?

A
  • internal: PMO
  • external: other similar companies
  • retailers: might have extra knowledge
  • do a risk workshop
  • industry specific checklist
  • cause-effect diagrams, WBS
  • modified SWOT analysis
37
Q

What happens in a risk workshop?

A
  • group brainstorm, ask each to find 5 risk factors
  • pre-mortem analysis: tell ppl project has failed, ask them what the cause of the failure is?
38
Q

What is a cause-effect diagram? AKA fishbone diagram

A

Look at different categories eg tech, machine, workers… and find things that could go wrong

39
Q

How would you use SWOT analysis for risk identification?

A

Weaknesses
Threats
Strengths - how can they be compromised?

40
Q

Where do you document the risks you find?

A

In a risk register

41
Q

When do you update a risk register?

A

Update regularly after status meetings!