L6 Flashcards
1
Q
What is finish to start activity predecessors?
FS
A
Activity B can start when activity A has finished.
2
Q
What is finish to finish activity predecessors?
FF
A
Activity B can finish after activity A is finished.
3
Q
What is start to finish activity predecessors?
SF
A
Activity B can finish after starting activity A.
4
Q
What is start to start activity predecessors?
SS
A
Activity B can start after starting activity A.
5
Q
What do we use Microsoft project for?
A
- project plans
- schedules
- manage resources
- time tracking
- Gantt
6
Q
Std. Rate
A
Per hour wage
7
Q
Ovt. Rate
A
Per hour wage for overtime work
8
Q
Cost/use
A
Some resources have a cost per use
9
Q
Accrue at
A
Time of allocating cost of the resource