L6 Flashcards

1
Q

What is finish to start activity predecessors?

FS

A

Activity B can start when activity A has finished.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is finish to finish activity predecessors?

FF

A

Activity B can finish after activity A is finished.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is start to finish activity predecessors?

SF

A

Activity B can finish after starting activity A.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is start to start activity predecessors?

SS

A

Activity B can start after starting activity A.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What do we use Microsoft project for?

A
  • project plans
  • schedules
  • manage resources
  • time tracking
  • Gantt
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Std. Rate

A

Per hour wage

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Ovt. Rate

A

Per hour wage for overtime work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Cost/use

A

Some resources have a cost per use

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Accrue at

A

Time of allocating cost of the resource

How well did you know this?
1
Not at all
2
3
4
5
Perfectly