L&RC Questions Flashcards
What are the Building Regulations?
The Building Regulations are statutory instruments that detail minimum performance standards for the design and construction of buildings
When were the Building Regulations introduced?
Established under the Building Act 1984. Amended by the Building Regulations 2010.
What is the main purpose the of the Building Act?
The Building Act 1984 sets out the legislative framework for the building control system.
What is deemed to constitute Building Work under the Act?
- The erection or extension of a building.
- The provision or extension of a controlled service or fitting in or in connection with a building
- The material alteration of a building, or a controlled service or fitting
- Work required by regulation 6 (requirements relating to material change of use)
- The insertion of insulating material into the cavity wall of a building
- Work involving the underpinning of a building
Who is responsible for ensuring compliance with the Building Regulations?
With all building work, the owner of the property (or land) in question is ultimately responsible.
When are consequential improvements triggered for non domestic buildings under part L of the , Building Regulations?
Where an existing building has a total useful floor area over 1000m² and it is intended to;
1. Build an extension.
2. Install the initial provision of any fixed building service (other than a renewable energy generator).
3. Increase the installed capacity of any fixed building services (other than a renewable energy generator).
Then it may be necessary to undertake additional works to the existing building as well as the new work. These works are referred to as Consequential Improvements.
What are dilapidations?
Refers to breaches of lease obligations either implied or expressed.
What is contaminated land?
Defined in the Environmental Protection Act 1990 as ‘Any land which appears to the , local authority to be in such condition that significant harm is/possibly being caused , or pollution of controlled waters (fresh/brown waters) is/likely to occur
Are there any forms of incentives to develop contaminated land?
150% tax relief for remediating contaminated land. Only the cost over & above that , expected for normal site preparation.
What statutory consents must be obtained before commencing demolition?
A Section 80 demolition notice must be submitted to the Local Authority for approval and no demolition work can be carried out until the authority has issued a counter notice under Section 81 of the Building Act which outlines the conditions that must be applied with when carrying out the works. This process can take up to six weeks.
What key pieces of guidance would you refer to when undertaking a refurbishment project involving electrical systems?
The Electrical Safety at Work Regulations 1989, BS 7671
What are the three instances in which the Party Wall Act may be triggered?
Work on an existing wall or structure shared with another property (Section 3), building a free standing wall up to astride the boundary (Section 1) or excavating near a neighbouring building or structure (Section 6)
How is the party wall etc act 1996 applied?
Excavating adjacent to a building or structure, cutting in or repair, new wall on or astride boundary line
Section 1 - line of junction notice (New structure on party wall line - 1 month notice)
Section 3 - party structure notice (Works to exist. wall - 2 months notice)
Section 6 - notice of adjacent excavation (3m or 6m at 45 degree rule - 1 month notice)
What is Jarvis v Harris?
Clause in a lease or tenancy agreement which allows the landlord to serve a notice on a tenant to carry out repairs. Where a tenant fails to do so, the landlord may enter, carry out the works itself and recover the costs from the tenant as a debt.
How long after the serving of a party wall award is the process for disputing an award?
14 days
What options are available for obtaining access to neighbouring land to undertake specific elements of work?
Option 1: enforcing rights of access in your title deeds
Option 2: Access to Neighbouring Land Act 1992
When is work notifiable to the HSE?
Works lasting longer than 30 days and have more than 20 workers working simultaneously at any point in the project or where they exceed 500 person days
What are the key components of the CDM Regulations 2015? ICHGG
(Construction Design and Management Regulations 2015)
Part 1 - Introduction
Part 2 - Client Duties
Part 3 - Health and safety duties and roles
Part 4 - General requirements for all construction sites
Part 5 - General
What are the main changes introduced in CDM 2015?
Removal of CDM coordinator, amendment to when project is notifiable, CPP required for all projects and not just notifiable ones
What are the various dutyholders listed under CDM?
Commercial clients, Domestic clients, Designers, Principal designers, Principal contractors, Contractors, Workers
What are the duties of the Principal Designer under CDM 2015?
Manage health and safety risks during the pre construction phase of the project, assist the client in complying with their duties under the regulations
What are the key duties of a client under the CDM regulations?
Make suitable arrangements for managing a project, including making sure:
- other dutyholders are appointed as appropriate
- sufficient time and resources are allocated
Make sure:
- relevant information is prepared and provided to other dutyholders
- the principal designer and principal contractor carry out their duties
- welfare facilities are provided
What are the key duties of a designer under the CDM regulations?
- Make the client aware of their duties under CDM regs before starting design work
- Take steps to control or reduce risks
- Take account of the PCI provided by client (and PD if involved)
- Eliminate h&s risks where possible
When can works be carried out under permitted development? Are there restrictions specific to local authorities?
Town and Country Planning (General Permitted Development) Order 1995. Certain works can be carried out without the need for planning. Not applicable to listed or buildings in conservation zones.