Key Terms E-K Flashcards

1
Q

early finish

A

The earliest date an activity may finish as logically constrained by the network diagram

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

early start

A

The earliest date an activity may start as logically constrained by the network
diagram.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

earned value (EV)

A

The value of the work completed to date as it compares to the budgeted
amount for the work component

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

earned value measurement (EVM)

A

EVM is a tool and technique of the Cost Control process that compares what you ’ re received or produced as of the measurement date to what you’ve spent. The three measurements needed to perform earned value measurement are planned value (PV), actual cost (AC), and earned value (EV).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

economic model

A

A type of benefit measurement method. It is a series of financial calculations that provide data on the overall financials of the project and is generally used as a project selection technique.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

enterprise project

A

A project that will be used by users throughout the enterprise

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

equipment

A

(a) Resources such as servers, specialized test equipment, or additional PCs that are required for a project. (b) One of the categories of project resources. It includes test
tools, servers, PCs, or other related items required to complete the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

estimate at completion (EAC)

A

A forecast of the total cost of the project based on both current project performance and the remaining work. The formula is EAC = AC + ETC.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

executing

A

This project process group is where the work of the project is performed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

expert judgment

A

A technique used in project selection, determining estimates, and determining other related project information that relies on the knowledge of those with expertise on the requested subject matter. Expert judgment can come from stakeholders, other departments, consultants, team members, vendors, or industry groups

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

external dependency

A

A type of dependency where a relationship between a project task and a factor outside the project, such as weather conditions, drives the scheduling of that task.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

extinction

A

This is a type of project ending that occurs when the project is completed and
accepted by the stakeholders.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

failure costs

A

The cost if the product fails, including downtime, user support, rework, and
scrapping the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

fast - tracking

A

A schedule compression technique where two activities that were previously scheduled to start sequentially start at the same time. Fast - tracking reduces schedule duration.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

feasibility study

A

A formal endeavor that is undertaken to determine whether the project is a viable project, the probability of project success, and the viability of the product of the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

finish - to - finish

A

A project task relationship in which the finish of the successor task is
dependent on the finish of the predecessor task.

17
Q

finish - to - start

A

A project task relationship in which the successor task cannot begin until
the predecessor task has completed

18
Q

fixed - price contracts

A

A contract that states a fixed fee for the work that the vendor will perform.

19
Q

float time

A

The amount of time the early start of a task may be delayed without delaying the finish date of the project. Also known as slack time .

20
Q

flowchart

A

A diagram that shows the logical steps that must be performed in order to accomplish an objective. It can also show how the individual elements of a system interrelate.

21
Q

forcing

A

This is a conflict - resolution technique where one party forces their solution on the
others. This is an example of a win - lose conflict resolution technique

22
Q

formal communications

A

Planned communications such as project kickoff meetings, team
status meetings, written status reports, or team - building sessions.

23
Q

forward pass

A

The process of working from the left to the right of a network diagram in order to calculate early start and early finish dates for each activity.

24
Q

functional organization

A

A form of organizational structure. Functional organizations are traditional organizations with hierarchical reporting structures.

25
Q

functional requirements

A

These define what the product of the project will do by focusing on how the end user will interact with the product

26
Q

high - level requirements

A

These explain the major characteristics of the product and describe the relationship between the business need and the product requested. This is also referred to as a product description

27
Q

human resources

A

The people with the background and skills to complete the tasks on the project schedule

28
Q

human resources planning

A

Defining team member roles and responsibilities, establishing an appropriate structure for team reporting, securing the right team members, and bringing them on the project as needed for the appropriate length of time.

29
Q

impact

A

The consequences imposed if a risk event occurs on the project.

30
Q

informal communications

A

Unplanned or ad hoc communications, including phone calls,emails, conversations in the hallway, or impromptu meetings.

31
Q

information distribution

A

Providing stakeholders with information regarding the project in a timely manner via status reports, project meetings, review meetings, email, and so on. The communications management plan is put into action during this process.

32
Q

initiating

A

The first process in a project life cycle and the first of the five project process
groups. This is the formal acknowledgment that the project should begin. The primary
result of this process is the project charter.

33
Q

inspection

A

A quality control technique that includes examining, measuring, or testing work results.

34
Q

integrated change control

A

A process that influences the factors that cause change, determines that a change is needed or has happened, and manages and monitors change. All other change control processes are integrated with this process.

35
Q

integration

A

A type of project ending where the resources of the project are reassigned or redeployed to other projects or other activities within the organization.

36
Q

internal rate of return (IRR)

A

The discount rate when the present value of the cash inflows equals the original investment. Projects with higher IRR values are generally considered better than projects with lower IRR values. Assumes that cash inflows are reinvested at the
IRR value.

37
Q

Ishikawa diagram

A

A Quality Control technique that shows the relationship between the effects of problems and their causes. This is also known as a cause - and - effect diagram and
fishbone diagram

38
Q

iterative process

A

Any process that is repeated more than once. The five process groups
are repeated throughout the project ’ s life because of change requests, responses to change,
corrective action, and so on.

39
Q

key performance indicators (KPIs)

A

Help you determine whether the project is on track and progressing as planned by monitoring the project against predetermined criteria.