Name the formula for TCPI.

A

The formula is TCPI = (BAC – EV) / (BAC – AC).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Name the formula for EAC.

A

The formula is EAC = AC + ETC.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Name the formula to calculate the lines of communication.

A

The formula is n (n – 1) / 2.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Name the formula for CPI.

A

The formula is CPI = EV / AC.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Name the formula for CV.

A

The formula is CV = EV – AC.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Name the formula for SV.

A

The formula is SV = EV – PV

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Name the formula for SPI.

A

The formula is SPI = EV / PV.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Define EV.

A

EV (earned value) is the value of the work completed to date as it compares to the budgeted amount (PV). This is a figure used in EVM formulas and is also referred to as the budgeted cost of work performed (BCWP).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Name the formula for VAC.

A

The formula is VAC = BAC – EAC.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Define ETC.

A

ETC is estimate to complete and is the forecast of the cost of all the remaining project work. This figure is usually provided by the project team members.