Formulas Flashcards
Name the formula for TCPI.
The formula is TCPI = (BAC – EV) / (BAC – AC).
Name the formula for EAC.
The formula is EAC = AC + ETC.
Name the formula to calculate the lines of communication.
The formula is n (n – 1) / 2.
Name the formula for CPI.
The formula is CPI = EV / AC.
Name the formula for CV.
The formula is CV = EV – AC.
Name the formula for SV.
The formula is SV = EV – PV
Name the formula for SPI.
The formula is SPI = EV / PV.
Define EV.
EV (earned value) is the value of the work completed to date as it compares to the budgeted amount (PV). This is a figure used in EVM formulas and is also referred to as the budgeted cost of work performed (BCWP).
Name the formula for VAC.
The formula is VAC = BAC – EAC.
Define ETC.
ETC is estimate to complete and is the forecast of the cost of all the remaining project work. This figure is usually provided by the project team members.