Key Issue 2 - Case Study Flashcards

1
Q

How would you deal with calling upon a materials off-site bond?

A
  • Notifying the bondsman
  • Notifying Skanska legal team
  • If it were a matter of insolvency, Skanska would make contact with the administrators.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What were the risks with each option considered and what did you advice?

A
  • Option 1 = Increased risk of Sub-Contractor failure, this was not a good way to manage them.
  • Option 2 = Passed on the cash flow issue onto us, this was not ideal and was bad management of project finances
  • Option 3 = We did increase the risk of on-site damage, however we felt we could manage this efficiently.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is the JCT definition of materials?

A
  • …all unfixed materials and goods delivered to and placed on or adjacent to the Works which are intended for incorporation therein’,
  • Off site materials are called ‘listed items’
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is a vesting certificate?

A

• It’s a tripartite agreement between the sub-contractor, contractor and employer in which the sub-contractor is require to specify that the materials pass to the employer as soon as payment is received from the contractor.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Who owns the materials?

A
  • In this scenario, clause 2.15.3, Unfixed materials and Goods. The materials will be owned by the Contractor if paid in an interim valuation, if they are then paid by the Employer, they would be their possession.
  • However, under the sub-contract we state that the Sub-Contractors must continue to insure the works until fixed in there final position.
  • Our all risks insurances would also cover any materials on site as additional protection.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What would on site materials be owned by if Skanska went bust?

A
  • Transfer of materials to the Employer when paid in interim valuation.
  • Clause 2.21 “Materials and goods - on site”. Amendment to the main contract: deleting second paragraph of cl. 2.21. Employers’ property. However, on default or termination of the Contractor materials become Employer’s property if paid, or to be included on the final valuation
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Was the Sub-Contractor not just administrating their Sub-Contract by asking for materials off-site?

A

• The contractor has entire discretion on payment for materials off site based on the provisions in the main contract.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

How does a bond provide Skanska protection?

A

• In the event materials are not delivered the bond will provide financial cover to the value of the materials.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What clause in the JCT D&B Sub-Contract relates to Listed items?

A

• 4.11 ‘Listed Items’ – (Section 4 Payments)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Where in the JCT Sub-Contract does it state that a bond is required for any listed items?

A

• Sub-Contract particulars, item 10.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What requirements are there under the sub-contract to incorporate materials as a listed item?

A
  • The item must be in accordance with the Sub-Contract
  • The listed item is insured for any loss or damage for its full value protecting the interests of the employer, until delivered too or adjacent the main contract works.

At the premises the listed items require clear identification of:
• The contractor and the employer
• The main contract works as its destination
• Each item must be clearly set apart and viably marked, individually.

If the Sub-contract particulars (Item 10) state a bond is required, the sub-contractor must provide a bond in favour of the contractor or employer from a suitable approved bondsman.

• They must allow for the value of the works as well as the terms set out in part 1 of schedule 3.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Where are ‘listed items referenced within the Sub-Contract?

A
  • In the Sub-Contract Particulars No.10 (In the Sub-Con Agreement) OR:
  • Subject to clause 4.11 of the Sub-Contract (Listed Items).
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Where would you find standard wording as a schedule to the material off site bond?

A

• Schedule 3 of the JCT D&B Sub-Contract.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

How is a material off site bond underwritten?

A

• As a deed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Why would they be required to update their insurances??

A

• It is prudent to have the sub-contractor name the employer on the policy in respect of their materials, or, have some form of ‘step in clauses’. A vesting certificate may give some form of rights, but I would consult a legal expert.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is a bond?

A

• An arrangement where a contractual duty is backed up by a third party, usually financial institution, or bank.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

What is the different between on-demand bonds and condition bonds?

A
  • A bondsman can only refuse make payment on a regular demand for payment if the demand is clearly made fraudulently or dishonestly.
  • A “conditional” bond the bondsman is only required to pay out if the contractor is in default under the underlying construction contract.
18
Q

What other bonds could you consider?

A

• Advanced payment bond

19
Q

Is it a risk that you have materials off site in your sub-contract but not in your main contract?

A
  • Not necessarily, the sub-contract materials off site provision is at the Contractor discretion.
  • As a last resort we would still use this but would have to absorb the cost impact on ourselves (which isn’t ideal).
20
Q

Whose risk is material delays and shortages?

A

• The sub-contractors, and/ or Skanska. We have a relevant event in place if issues are because of Brexit and can be proven to be.

21
Q

What must a bond be?

A

• In writing, common to be a deed
• Contains a duration and financial limit
Names of the protected parties

22
Q

What is a listed item in the JCT?

A

• Materials, goods and or items prefabricated for the inclusion in the works.

23
Q

What does the listed items clause in the JCT Main-Contract say?

A
  • Listed items clause 4.15 (Payment).

* Listed items are scheduled out and annexed to the employers requirements (in the main contract!)

24
Q

Do you hold retention on the listed items?

A

• Yes retention is held on listed items.

25
Q

Who owns the materials off-site?

A

• The Employer if it’s been paid for. Contract will detail who under possession.

26
Q

What would you do if you had paid materials off site and the sub-contractor went insolvent?

A
  • Inform bondsman
  • Inform insurance companies if applicable
  • Inform client
  • Serve notice to the Sub-Contractor
  • Arrange collection of materials
27
Q

Whose risk is material damage on site?

A
  • Damages and security of materials on site remain a Sub-Contractors risk.
  • Sub-Contractors required to insure all works, including any listed items paid for by the Contractor.
28
Q

What would you do if the materials got damaged on site?

A
  • Take images and record damage
  • Inform sub-Contractor of damaged materials.
  • Inform Insurance company
  • Complete a claims form online through Skanska internal processes
29
Q

What Insurance option do you have In the JCT at Norwood?

A

• Option A – All Risks insurance by the Contractor.

30
Q

How does the JCT Sub-Contract deal with material price increases and fluctuations?

A
  • Fluctuations are item (8) in the contract particulars (if it applied).
  • The JCT has fluctuation options detailed in the Schedules.
  • In our contract, fluctuations do not apply. (Placed on a fixed price lump sum).
31
Q

Where in the Sub-Contract does it state the contractual start on-site date?

A
  • The periods for commencement are contained within the Sub-Contract particulars specifically (Item 5).
  • Notices to commence are in section 2 ‘Carrying out the Sub-Contract works’. - CLAUSE 2.3
32
Q

How much do bonds cost?

A
  • There is usually a typical flat fee and a % between 1-8% of the bond value.
  • Depends on contractors’ financial stability, risk etc.
33
Q

What insurance do you have in place at Norwood to protect the materials?

A
  • (Schedule 3) Insurance option A – New Buildings All Risk Insurance of the Works by the Contractor.
  • A joint policy in both names for all risks
  • There is a clause (6.8) in the Contract which defines the related definitions.
  • A % for professional fees (15%).
34
Q

If the start on site date was outside of the contract, would be liable for any costs?

A

• Yes, the Sub-Contractor could apply for the direct loss and or expense occurred by postponement of the works being executed.

35
Q

What are the fluctuation options in the JCT?

A

Option A - tax, levies and contributions that a Contractor has to pay in respect of their employees.

Option B - allows for the adjustment of the contract sum in respect of changes in the price of labour, material cost and, tax fluctuations. (If materials fall the cost is reimbursed)

Option C - Formula adjustment (based on specific set of costs in the contract), will include a formula for calculating fees.

36
Q

How does the contract deal with insurances of the listed item on site?

A

Sub-Contractor who would provide insurances with the Employer as a named person. On site All risks insurance by the Sub_Contractor, but Skanska also have cover.

Insurance of works through all risk cover in section 6 of the sub-contract

37
Q

What is the Sub-Contractors level of All-risks insurance?

A

£3.5m

38
Q

What is Skanska’s main all risks insurance policy and level of cover?

A

Skanska have £50m all risks cover
Used Skanska annual policy with the Employer named for this specific project.
15% to cover professional fees

39
Q

If you wanted to call upon a materials offsite bond what would you do? And what are the steps you would take?

A

Serve a notice of demand

Request the demanded sum to be paid within 5 days

40
Q

What clause is insolvency termination under the sub-contract?

A

Insolvency of a sub contractor = 7.5