Key Concepts Flashcards

1
Q

How to interpret SPI and CPI results

A
  • less trhan 1 is bad (behind schedule, and funds deficit - over budget)
  • Greater than 1 is good (ahead of schedule and surplus of funds - under budget)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

When and how are contingency reserves vs management reserves applied?

A
  • Contingency reserves
    • applied for known-unknowns - risks you planned for
    • Applied at activity and/or WBS level
    • included in cost baseline
  • Management reserves
    • applied to unknown-unknowns - risks you did not foresee or plan for
    • applied at project level
    • not part of cost baseline, but is part of project budget
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Difference between critical path mothod and critical chain methods

A
  • Critical path does not account for resources
  • Critical Chain method alloows the placement of buffers on any task to account for limited resources and project uncertainties “Duration buffers” where necessary - duration buffers include:
    • Feeding Buffer (activity level)
    • Projct Buffer (project Level
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Cost of Quality includes:

A
  • Both Prevention Costs (cost to make sure you have quality) and Faliure Costs (cost resulting when you don’t comply with quality standards)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Key concepts for Critical Path Method

A
  • Float
    • for tasks on the critical path are always 0
    • for tasks not on the critical path,
      • calculated by critical path - path duration
      • same for all activities on that path
    • if a float already is applied, do not overwrite it
  • Early Start/Early Finish/Late Statrt/Late Finish
    • ES/EF calculated by forward pass (top of activity)
    • LS/LF calucated by backward pass (bottom of activity)
    • First task on schedule is always ES of 1
    • The LF of the last activity is the same as the EF
    • EF of any task is its ES+Duration-1
    • LS of any activity is its LF-Duration+1
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

7 Quality Tools

(7QT)

A
  1. Fishbone or Ishikawa Diagrams (cause and effect, or problem statement)
  2. Histogram (statistical distribution)
  3. Pareto Diagram (bar chart + key causes)
  4. Scatter Diagrams (correlation)
  5. Checksheets
  6. Control Charts (in or out of control, within or out of variance, standard deviation)
  7. Flowchart (process, anticipate quality problems)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

3 Terms for Failure Costs

A
  1. Failure Costs
  2. Costs of non-compliance
  3. Costs of Poor Quality
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

General technique for interpreting comparisons and performance ratios

A
  • Lower number is bad
  • Higher number is good
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Opportunity Cost Considerations

A
  • When dealing with NPV or otherwise, opportunity costs don’t matter
  • Sunk costs never factor into a decision
  • Opportunity cost is very simple - the value of the next best item on the list of choices
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

ITTO Key Things to Remember

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly