Interim Valuations and Payment Provisions Flashcards
What is the purpose of a valuation?
To provide advice to the certifier on value to allow them to issue their interim certificate
Regarding valuations how is ’The Housing Grants, Construction and Regeneration Act 1996’ relevant?
It contains statutory requirements relating to interval and procedure for contracts that have a duration of over 45 days
Specifically stating that a party to a construction contract is entitled to interim or stage payments coming from interim valuations or pre-determined amounts at project milestones or specified dates.
Relevant to valuation what happens if a contract does not contain the provisions required by the Construction Act?
The Scheme for Construction Contracts will apply to fill the gaps
What are the main elements of a valuation?
(7 main elements)
a) Preliminaries
b) Measured work
c) Variations
d) Materials on site
e) Materials off site
f) Loss and expense
g) Retention
What are the six steps to a valuation set out within Interim Valuations and Payment, 1st edition (August 2015) ?
- Planning
- Pre-Valuation
- Valuation
- Valuation Document
- Issue Valuation
- Post Valuation
Why is it important to visit site as part of a valuation?
In order to conduct a fair assessment to ascertain a valuation - going to site allows you to objectively and accurately determine what has been done and what has not. It also allows you question the contractor face to face about any disparities you may imminently see.
Which two pieces of legislation impact valuations?
- ’The Housing Grants, Construction and Regeneration Act 1996’
- ‘The Local Democracy, Economic Development and Construction (LDEDC) Act 2009’
What year did ’The Housing Grants, Construction and Regeneration Act’ take effect?
1996
What year did ‘The Local Democracy, Economic Development and Construction (LDEDC) Act’ take effect?
2009
Regarding valuations, written in legislation how many days after a due date must an employer issue a notified sum (payment notice)?
5 Days
Regarding valuations, if an employer fails to issue a payment notice will the contractor be entitled to payment?
Yes, legislation states that if the employer hasn’t issued a payment notice within 5 days of the due date the payee can issue their own notice providing that there is a basis to which the sum is calculated.
Regarding valuations, when must an employer pay the amount on the payment certificate?
The employer must pay the contractor on or before the final date for payment unless a pay less notice has been issued - in which case they would pay the amount on that.
What must a pay less notice have?
A basis of calculation.
e.g. a breakdown of costs, this could be by using a CSA
If an employer fails to submit a payment notice and the payee gives their own notice, can the employer still submit a pay less notice?
Yes
So long as they base the pay less notice on the payee’s notice.
Regarding interim valuations, how many days before a final payment can a pay less notice be issued?
It depends on the contract. in JCT it is typically 5 but this can be changed on agreement. If there is no agreement on this within the contract then the Scheme for Construction Contracts will take president and it would be fixed at 7 days.