Extension of time and Liquidated Damages Flashcards
What is an extension of time?
A mechanism in the contract that allows an employer to extend the time in the contract by which the contractor is required to complete works.
What is EOT short for?
Extension of time
What type of construction contracts have EOTs
The JCT suite
There are conditions that can triger EOTs. What is this term called?
Relevant Events
What is a relevant event?
A defined event set out in a JCT contract that will trigger an EOT
When is an extension of time triggered?
when a relevant event happens
Under JCT when is a contractor bound to advise the client of a relevant events impact and effect?
Whenever reasonable and apparent - though its uncelar what recourse is available if they dont.
What would happen if a relevant event happened (a delay not that isnt the contracts fault or owned risk) and there was no extension of time facility within the contract?
The completion date would change to time at large
What is time at large?
Completion within reasonable time
What are the impacts of a contract completion date becomeing time at large
The client is no longer entitield to liquidated damages and delay damages become more ambiguous with no specific date of completion.
Who confirms an EOT after the contractor sends notification?
The CA or EA - as soon as possible and absoloutly within 12 weeks.
Can the CA/EA retrospectivly bring a previously extened completion date back so that it was sooner?
Yes, they would do this to allow the client to claim more liquidated damages when there is a leitimate reason to bring it forward..
What happens if a contractor disagrees with a CA/EAs decision surrounding an EOT
Dispute
What are liquidated damages?
liquidated damages are pre-determined damages, calculated before damage has been incurred, that may not represent the true damage but does provide certainty of what the damages will be.
Where does the language behind liquidated damages come from?
Liquidare – to make clear or certain
A latin word