Change Procedure & Valuing Change Flashcards

1
Q

What are variations?

A

Alterations or modifications to the design, quality or quantity of the contract works, to the site access or working conditions

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Why might variations arise?

A

A variance between the needs of the employer, and the scope of the contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What form must architects instructions take?

A
  • They must be in writing
  • The QS cannot make additions to the contract sum for AIs that are not written
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

How should a contractor deal with an oral arcitect instructions?

A
  • The contractor has 7 days to write to the architect asking for the AI to be confirmed
  • If the architect does not respond in a further 7 days it is taken as being an AI
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Can the contractor object to a variation?

A

They can make ‘reasonable’ objections in writing for variations relating to those described in 5.1.2 (working conditions / access / working hours etc)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

How soon does a contractor have to comply with an architects instruction?

A

Forthwith - without delay

As soon as possible

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What can the architect do if a contractor doesnt comply with a variation?

A
  • He can issue a compliance notice
  • If there is still no action by the contractor within 7 days, others can be employed to carry out that work and the additional cost charged to the contractor
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What 3 methods are there of obtaining a cost for variations?

A
  • Agreement between the employer and contractor
  • A schedule 2 quotation
  • Valuation by the QS under the valuation rules
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What are the time periods for Schedule 2 quotations?

A
  • The architect should request one in the AI
  • The contractor has 7 days to notify that they will not provide one
  • If not, they have 21 days to provide the quotation
  • The architect then has 7 days to confirm in writing the acceptance or rejection
  • The acceptance is called the ‘confirmed acceptance’
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What costs does the quotation contain when quoting a variation?

A
  • Value of the work
  • Any adjustment of time
  • Money in lieu of direct loss and expense
  • The fair and reasonable cost of preparing the quotation
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What costs is the contractor entitled to if the quote for a variation is rejected?

A

The fair and reasonable cost of preparing the quote, as long as the quote itself was fair

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What are the valuation rules?

A

There are three rules for measurable work:
* If it is of a similar character, quantity and in the same conditions as existing work, then the bill rates should be used
* If it is of a similar character, but different quantity or conditions, the bill rates should be used as a basis but a fair allowance should be made to take account of the difference
* If it is not of a similar character, fair rates and prices should be used

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

How are non-measurable work valued?

A

Should be valued by dayworks

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is a star rate?

A

A rate that is based on the bill rates but includes a fair allowance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What are ‘fair rates and prices’?

A

A market rate, or price based on actual costs, on in line with current cost data e.g. SPONS

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is dayworks?

A

The prime (actual) cost of all the materials, labour and plant used in carrying out the work, along with the % additions to each category as set out in the contract

17
Q

What document should the prime cost be calculated in accordance with?

A

Should be calculated in accordance with the ‘Definition of the Prime Cost of daywork carried out under Building Contracts’ published by the RICS

18
Q

What information is necessary to be able to assess dayworks?

A
  • Vouchers showing the amount of time spent on each activity (dayworks sheets)
  • Names of the workmen
  • Plant used
  • This information should be given to the architect at the end of the week following that in which the work was carried out for verification
19
Q

Can the QS alter hours which he considers to be excessive on a dayworks sheet that is authorised by the architect?

A

No

20
Q

What would you do if the contractor submitted 10 dayworks sheets to you for payment?

A
  • Verify with the architect that a relevant variations has occurred and is on an AI
  • Ensure there is no other contractual method of valuing the variation
  • Verify the hours and materials are correct and authorised by the architect
21
Q

Regarding a valuation if you and the contractor’s QS could not agree on something how would you resolve it?

A
  • Discuss with partner and client to try and seek a resolution with the contractor
  • Your valuation stands for the purposes of payment
  • The contractor could take the dispute to adjudication if necessary but should try and resolve so it doesn’t come to this
22
Q

Give an example of where quantum meruit might be used

A

If the employer and contractor come to a separate agreement on acceleration, the costs of this may be based on a ‘fair and reasonable’ basis

23
Q

When dealing with variations/changes what happens if client/contractor do not reach an agreement regarding cost?

A

The clients QS valuation will be imposed

if the contractor still disagrees then they would have to take it D.R.

24
Q

What 3 methods are there of obtaining a cost for variations?

A

Agreement between the employer and contractor
A schedule 2 quotation
Valuation by the QS under the valuation rules

25
Q

When quoting for a variations, what costs does the quotation contain?

A
  • Value of the work
  • Any adjustment of time
  • Money in lieu of direct loss and expense
  • The fair and reasonable cost of preparing the quotation
26
Q

When quoting for variations what costs is the contractor entitled to if the quote is rejected?

A

The fair and reasonable cost of preparing the quote, as long as the quote itself was fair

27
Q

What is a star rate?

A

A rate that is based on the bill rates but includes a fair allowance

28
Q

What are ‘fair rates and prices’?

A

A market rate, or price based on actual costs, on in line with current cost data e.g. SPONS