Installing a Single-Phase Meter Flashcards

1
Q

All Steps 1-11

A
  1. Inspect meter
  2. Don PPE
  3. Inspect meter socket
  4. Verify customer main is open if applicable
  5. Test the tester if a reading of 0 is obtained
  6. Find the neutral
  7. Test the meter fitting
  8. Install meter
  9. Test meter if possible
  10. Install meter ring and seal
  11. Close customer’s main if applicable
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q
  1. Inspect meter
A

for cracked glass, loose wiring, and proper voltage rating

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q
  1. Don PPE
A

Gloves, face protection, hard hat, vest, boots, clothing

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q
  1. Inspect meter socket
A

for damaged clips, loose screws, foreign matter, broken parts

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q
  1. If applicable, verify
A

Verify customer main is open

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q
  1. If reading of 0 volts
A

Test the tester on a known live source

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q
  1. Find the neutral
A

Continuity test
- phase to ground should be no light
-neutral to ground should light
-phase to ground should be no light

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q
  1. Test meter fitting for proper voltage
A

Test 1 - source voltage - line side to neutral should be 120V, then line side to line side should read 240V
Test 2 - backfeed - load side terminals to ground source, should read 0 volts
Test 3 - load side - phase to ground fault, test from line to load side, should read 0 volts
** verify continuity of jumper if applicable
Test 4 - load side - phase to phase fault, install jumper from one load side to neutral, then test from line to load side, should read 0 volts. Remove temporary jumper.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q
  1. Install meter
A
  • Put meter load side prongs into load side clips
  • Take care to keep meter straight
  • Press line side prongs into the line side clips firmly
  • Keep meter straight
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q
  1. Test…
A

…load side for proper voltage if possible

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q
  1. Install…
A

… Meter ring and meter seal

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q
  1. Close…
A

… Customer’s main, if applicable
***Before any of these steps ensure customer’s main panel is connected properly and safe to liven up if possible to enter