Inspection Flashcards

1
Q

Tell me about when you have prepared a detailed Building Survey reportfor a client containing detailed information, conclusions andrecommendations.

A

I recently prepared a building survey report on a water damaged ground floor property within a block of flats. I was instructed to comment on the damage, determine a cause and make recommendations for remedial works. I included detailed nifromation on the construction of the property, cavity walls, dry lined, no insulation or foil, concrete floors. I concluded that damp was primarily coming from the leaking bathroom fittings but also condensation. I recommended that all of the bathroom fittings, floor covering and dry lining be removed and the substrate allowed to dry. I also recommended that a intrusive investigation of the cavity is completed to assess damage to wall ties and also to understand potential for CWI.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Prestwick Road SubsidenceWhat advice did you give to your client?

A

I advised the client that the approach suggested by the loss adjuster to repair the superstructure of the building only solving the immediate problems was concerning. I advised that further investigations should be completed to make a concerted effort for a claim to remove more of the trees. I also suggested that the resident should be removed from the property and a schedule of repairs should be developed to present to the loss adjuster.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Prestwick Road SubsidenceWhat were the recommendations you made regarding remedial work internally and externally.

A

Internally I recommended that existing poorly filled cracks with cement are removed. The cracks would then need to be repaired appropriately and decorations completed inside. Externally we recommended that the property was underpinned the full length of the wall that was being affected by subsidence.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Prestwick Road SubsidenceWhat made you consider it was subsidence

A

Previous reports were compelted by other surveyors which concluded that the damage was caused by shrinkage. From site there were significant BRE Cat 3 cracks that had opened up, with some doors not fitting within frames. From a desktop study, monitroing had shown further movmeent during summer months, this cyclical movement removed possibility of drainage issues. There was also a trial pit report where tree roots were found in the soil.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Prestwick Road SubsidenceWhat did you advise about the potential for damage after tree removal?

A

If more of the trees were removed to the rear of the property this could result in heave as moisture would not be removed from the ground from the trees, this can take several years. To avoid the potential damage of heave, the underpinning should be installe dto more than 2m.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Emma Rothschild Condition ReportWhat was the life expectancy for the roof covering compared to the photovoltaic panels

A

The remaining life expectancy of the concrete roof tile covering was approximately 30 years. Photovoltaic panels have a life expectancy of 40 to 50 years. However, we advised that by the end of the life expectancy of roof covering the technology of the panels would likely be obsolete/redundant and the panels could be renewed at teh same time.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Emma Rothschild Condition ReportWhat were the significant details founds?

A

The defects found on the roof were all related to mainteance i.e. cracked or slipped concrete tiles. There was a poorly installed boiler flue which had penetrated the underfelt and not patched repaired. We recommended that a pacth repair was conducted.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Emma Rothschild Condition ReportWhat was your advice to the client about the roof covering.

A

I advised that the roof covering had approximately 30 years of life expectancy remaining. There were no significant defects other than maintenance issues. There was also evidence of any issues a being addressed through the maintenance.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Cladding Surveys, LondonWhat RICS guidance did you follow?

A

Before undertaking my surveys I reivewed the cladding for surveyors supplementary guidance.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Carlton Vale Estate condition surveyWhat defects did you look for in the concrete frame?

A

I was looking for cracking and any spalling that may be related to carbonation of the steel reinforcement.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Carlton Vale Estate condition survey?Did you consider the use of HAC in the building?

A

The buildings of the estate are of the correct age for the concrete frame to be of HAC. However, when asking for the pre-survey information from the client it included test reports indicating the concrete was not HAC.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Carlton Vae Estate condition surveyWhat deleterious materials did you find

A

Considering the age of the property I was looking out for potential ACM. The reports provided by the client did however confirmed no presence.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Carlton Vale Estate condition surveyHow did you deal with inaccessible areas during your survey?

A

I comminicated the client before the survey to ensure that I was able to gain access on to all of the roofs of each of the blocks. I inspected the condition of gable walls and rear elevations from ground floor level with binoculars. When reporting on the condition of windows and doors, I included a discalimer in my report that my recommendations were based on a sample of flats that I gained entry into.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Carlton Vale Estate condition surveyWhen inspecting the flats what additional legislation did you need to take into considetration that did not apply to the communal areas

A

During my inspection of the flats I was sure to consider S11 of the landlord and tennant act to ensure the structure of the property was maintained and that no water was penetrating the property. I was also careful to check if all homes were fit for habitation.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Carlton Vale Estate condition surveyDid you make any recommendations to your client about the inspection of elements above ground level.

A

Yes, I did make recommendations for the refurbishment of the steel double glazed windows. From my inspections of a sample of flats I found that the double glazing seals had been comproimsed throughout. I recommended that a full survey of all windows should be completed to determine the level of refurbishment and potential replacement required. I also recommended the replacement of some of the flat roof covering due to issues with leaking, I also included in my recommednation for the introduction of isnulation to meet building regulatiosn and also to aid in energy perfroamcne and condesnation within the property.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Carlton Vale Estate condition surveyHow has the verdict of Ryb V Conway Chartered Surveyors altered what you inspect when surveying a property?

A

The result of the case has not altered what I survey during a property but has reitterated to me the requirement to be thorough when completing my inspections and ensure that my CPD and training is inkeeping with current market trends and the tasks I am completing.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

What is a dilapidation survey?

A

Dilapidation refers to a property falling into disrepairA dilapidation survey is usually carried out at start or end of tenancyInvolves the recording of the condition of the propertySurveyor will compare the condition of the property with the details of the tenancy agrement and advise on any potential breaches of agreementThe survey should also provide, where relevant, quantiteis of repair required and method

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

What is a scott schedule?

A

Document included alleged breaches of tennancyCost of remedy worksDefendants comment on tehe costsDefendant can provide estimate costDispute can be decided by a judge

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

What are the contracted and implied covenants in a tenancy agreement?

A

Express or contracted items are included within the contract. Implied terms are not included in the tenancy but implied by law.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

What were the 2018 ammendments to Approved Document B?

A

Following Hackitt review of guidance due to Grenfell. The us of plain English in approved docuemtn B. Properties over 18m that have rooms of residency should only have materials of limited combustibility, minimum euroclass A2. An assessment of extenral wall system should not be used in lieu of on site testing.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

Cladding Surveys, LondonWhat do you mean approved document B height?

A

Checkin ghte hight of property is under 18m. This is from the first floor to top of ceiling. This would determine the classification of risk in the building.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

Cladding Surveys, London What were the materials you were most concerned to find on your inspections?

A

External wall insulationAluminium composite materialsHigh pressure laminatesThese materials all had a high chance of becoming combustible?

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

Cladding Surveys, LondonWhat was the process of completing the cladding surveys to fulfill the requirements of the approved document B ammendment?

A

Phase 1 report to determine height and external materialsProvided to fire engeineer for reviewPhase 2 report of on site testing was required due to material classification or building heightPhase 3 report from fire engineer if ESW1 option A could not be awarded.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

Cladding Surveys, LondonHow did you identify areas fro intrusive inspections?

A

The primary reason for the survyes was to determine the external wall system suitability. This meant locating compartment lines, horizontally and vertically. Areas requiring closure i.e. around windows also needed to be determined.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

Emma Rothschilde Condition ReportHow did you preprea for the condition survey of the roof?

A

Requested any drawings on file.Asked the client for any details of roof instllation like guarunteesCompleted a reivew from google earth of roof spcesArranged access to the loft spaces to determine quality of the membrane.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
26
Q

Emma Rothschilde Condition Reporthow did you present your information on the condition of the roofs to the client?

A

Used a map and colour coding to differentiate the different roof apces. Completed schedule of condition to all of the roof spaces and elements. Advised on any major defects or issues within the main body of the report.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
27
Q

Emma Rothschilde Condition Reporthow did you advise your client on the installation of the photovoltaic panels at Emma Rothschild?

A

The pitched roofs had a potential life span of 60 years with 40 years remaining. Flat roof covering had the potential life span of 30 years with 20 to 25 years remianing. The PV panels would have a life span of 30 years but technology would likely be outdated before then. Panels could be installed wihtout the requirement to replace the roof covering before they needed to be replaced. The panels should have been installed on the south slopes of the roofs, subject to a consultation with a structural engineer.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
28
Q

What are photovoltaic panels?

A

Photovoltaic panels turn solar energy from the sun into electrical energy, helping to reduce the carbon consumption of properties. IN order to maximise efficiency they should be installed facing south.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
29
Q

What is the defintion of subsidence?

A

Movement of the ground not caused by the imposition of building or foundation loads i.e. mining subsidence, from desacation of ground.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
30
Q

What is the defintion of settlement?

A

Downward movement of the ground or any structure on it due to the load applied by the structure.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
31
Q

How can buildings potenteillay subject to foundation movement be investigated?

A

A walk over study to check the surrounding areas, i.e. topography of area, watercourse, active or recent building worksDesk top study, check of geological gata, surrounding place names i.e. bog lane, plans with planning or building controlBelow ground, trial pits to determine composition of soil and whether there is any vegetationABove ground monitoriing wiht the use of tell tales to monitor cracks over time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
32
Q

How do you measyre and classify the widths of cracks?

A

Using BRE digest 251 crack classification:0: Hairline cracks less than 0.1mm1: Up to 1mm2: Crack width up to 5mm3: Crack from 5 to 15mm or several of 5mm4: Extensive damage 15mm to 25mm5: Structural damage, cracks greater than 25mm

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
33
Q

What are the repair methods specified in the BRE digest 251?

A

0: No action required1: Fine cracks can be treated using normal decoration?2: Cracks easily filled. Recurring cracks must be masked by suitable lining3: Cracks require opening up and repair by mason. Extrenal repointing required and some bricks may need to be replaced.4: Extensive damage that will require breaking out and replacing sections of walls especially over doors and windows.5: Major repair job required, structural engineer advice should be procured.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
34
Q

Preswick Road SubsidenceWhy had you been appointed to advise on works to prevent further strucrual damage and not diagnose the defect?

A

Our client was completing an insurance claim against the neighbouring proprety. From earlier inspections a tree had been removed, partial underpinning and repairs to the superstructure of the building had been completed.Our client appointed us to insect and advise on whether the remedials had prevented further damage and advise on whether the property was safe for occupance or required further remedials.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
35
Q

Preswick Road SubsidenceWhat did you advie the client to prevent further structural damage?

A

Cracks internally had re-opened internally over the summer months indicating trees were still desacting the surrounding clay soil.I advised that further soil investigations hould be completed in an attempt to find roots from the other trees.Underpinning should be completed to the entire flank wall, as the partial underpinning was excacerbating the damage.This method was expensive, and as an alternative a root barrier could be installed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
36
Q

Preswick Road SubsidenceWhat did you advise the client on the habitation of the property?

A

The property was not a dange to health or safety from collapse. However, the cracks within the ground floor flat were allowing a draugh an infestiation. We advised the resident should be decanted until repairs were complete?

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
37
Q

What is the life expetancy of concrete roof covering?

A

Expected 50.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
38
Q

What is the life expectancy of bitumen flat roof covering?

A

25 years.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
39
Q

What are the typical defects expected from a concrete roof covering?

A

Overloading of roof structureDiscolouration of tilesEfllourescence, salts being drawn to surface of tilesDelaminiation of tilesSlipped and broken tiles

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
40
Q

What are the typical defects expected from a bitumen flet covering?

A

Loss of surface protectoin - ballast or paintPoor joints - worn or poor intial bondProblems at eaves - lack of sufficient curb allowing wind underneathProblems at verge - no curb allows for water to drain

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
41
Q

What RICS guidance would you follow for party wall issues?

A

Party wall legislation and procedure 7th edition.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
42
Q

How would assess the age of the building?

A

BY reviewing construction materials, techniques and design choices and comparing them against period standards.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
43
Q

What would a desktop study include?

A

A descktop study would include a review of the building in question from google maps, to understand in principle the construciton, layour and access issues. A review of any previous information such as FRA or O&M manuals.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
44
Q

How would inspect for a fire risk assessment?

A

I would not conduct a fire risk assessment as this is outside my qualifications and my companies public indemity insurance policy.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
45
Q

How would you inspect to complete a schedule of condition?

A

In a logical manner. Externally each element would be divided i.e. roof, walls, gutter,windows. Internally inspection would be done room by room and follow the same component basis.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
46
Q

Explain the limitations of using a borescope?

A

Directing a borescope can be hard to get inspect the area/ element you need to view. They can also be confusing to navigate and require destruction/drilling of elements to allow access.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
47
Q

Explain the limiatations of thermography in leak detection/?

A

High initial investmenet to buy equipment, sometimes imaging can be difficult to interpret and can be rednered in accurate by emissions or reflections.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
48
Q

Explain a key issue that RICS surveying safely raises?

A

It raises the issue that members and firms should be aware of the hazards they are exposing themselves to and have the appropriate training in order to minimse the risk.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
49
Q

Tell me about the basic construction of a byuilding you have recently inspected.

A

Recently I inspected a proprty of early 20th century construction. Cavity brickwork walls, slate DPC, steel wall tiles. Windows were timber sash and casement. The roof strcuture was a gabled with concrete tile construction.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
50
Q

What is an easement?

A

The non-possessory right to use or enter onto the property of another without posessing it.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
51
Q

How might you find out abuiot an easement?

A

Completing a land registry check.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
52
Q

How can you tell if a property is cavity wall construction?

A

Flemish bond brick workWeep holesThicknes of walls

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
53
Q

What is the size of a brick?

A

215x 102.5 x 65

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
54
Q

What is deleterious material?

A

A material that is prohibited from use within constrction, for reasons of health and safety performance etc

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
55
Q

What is a hazourdous material?

A

Materials that when exposed to could cause signifcant health effects.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
56
Q

Give me 3 examples of deleterious materials?

A

Asbestos or ACMLead containing materials i.e. lead paintPolyurethane foamSilica dust

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
57
Q

Give me 3 examples of hazardous materials?

A

Flowers/fruit/vegetation that can cause dermatitis Dusty and fumesProlonged contact with cement.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
58
Q

How would you identify dry rot?

A

Musky mushroom smellCuboidal cracking to timbersHollow sound when tappedMycellium (cotton wool strangs) beneath surface seeking foodFruiting body are creamy pancases with dark edges20 degrees optimal tempearture20-30% optimal temperature

59
Q

What is the cycle for dry rot?

A

Spore on timberSpreads mycelliumOnce established = fruiting bodiesFruiting bodies prodce sporesSearching for celluse

60
Q

How would you identify wet rot?

A

High humidity

61
Q

How would you detect Japanese Knotweed?

A

Leaf is green and sheild shapedLeaf stem zig zaggedBamboo like hollow stemsFlower white small and 5 petals

62
Q

How would you treat Japanese Knotweed

A

Excavation (8 week timescale)Root BarriersHerbicide control

63
Q

What is rising damp?

A

Rising damp is the rising of water up through porous materials of a building via capillary action.

64
Q

What is the RICS guidance for Japenese Knotweed?

A

Japenese knotweed and residential property guidance note 2022

65
Q

What is the issue with Japenese knotweed?

A

It is a dominate plant that has a hardy bamboo nature which can disprut light structures, paths and standalone walls.

66
Q

What is structural movement?

A

Structural movement is the movement or failing of a structural element of a property that effects other elemetns of the proeprty.

67
Q

What does section 11 of the landlord and tenant act say about repairs?

A

It omplies an absolute non esxluding obligation upon landlords to carry out basic repairs to the main structure and exterior of the building.

68
Q

What are the three levels of survey?

A

Level 1 is a condition survey of specific iteemLevel 2 is home buyers, all elements viibily and easily accessibleLevel 3 bespoke report to property and covers all accesible areas.

69
Q

Grove view condition surveyWhat type of property was the report on?

A

Grove view was a converted church into 14 independent flats. The church had been converted approximately 20 years before, using facade retention and installing a steel frame internally.

70
Q

Grove view condition surveyHow many storeys was the building?

A

The building was a total of 5 storeys, with two storyes in side of the roof space.

71
Q

Grove view condition surveyWhat was the prupose of the survey and report?

A

I was instructed to carry out a condition survey of the external and communal areas of the property, identifying repairs that should be picked up.I would then present the repairs within a report with budget estimations to allow for a mainteance project to be developed and for leasholders to be consulted on the s20 process.

72
Q

Grove view condition surveyHow did you record defects and their quantities?

A

Before attending site I requested the as built drawings from the client. I then developed a grid system on the drawings. While on site I used the grid reference system to map any defects that I found on the property with photographs and sketching on the drawings. I would measure each of the repairs and quanitfy them in my survey notes to allow them to be costed and a budget allowance made before issuing the report.

73
Q

Grove view condition surveyWhat did you include in your report?

A

NAME?

74
Q

Grove view condition surveyWhat advice did you give on the signficant defects?

A

The two main significant defects related to a flat roof covering and boundary wall.The flat roof deck was spongey and from the conversion of the church, the covering was now reaching the end of lifes expectancy. Although there were no signs of leaking internally, I advised it would be prudent to replace the roof covering while carrying out other mainteance works. I also advised that this would be subject to thermal improvements as per building regulations part L.There was a boundary wall that was suffering from subsidence, likely from a nearby tree. I advised that the client should rebuild the section of wall that had been most severly effected. I also advised in order to build a claim and determine the cause of damage trial pits should be compelted.

75
Q

Grove view condition surveyHow did you develop the budget estimations?

A

For the typical items I used BCIS and other similar projects to determine budget estimations.There were a signifacnt amount of specialist stone repairs requried, which I apporached a contractor to provide a schedule of rate.

76
Q

Emma Rothschild condition reportWhat was the purpose of the condition report?

A

To identify any signficant defects of the roof covering and structure and assesss whether it would be suitable for the installation of photovoltaic panels.

77
Q

Emma Rothschild condition reportWhat assessment did you make to determien the best approach for installing the PV panels?

A

My primary objective was to understand whether it would make economic sense to install PV panels now or when the roof covering would require replacement.I therefore completed a thorough condition inspection of all the roof covering of the property to understand their remaining life expectancy and any significant defect. I then contacted some PV Panel manufactures to understand the life expectancy of the technology.The concrete roof coverings had approximately 30 years left, while PV panels would last 40. However, I advised that the technology would likely be obsolete in 30 years and it would make economoical sense to replace the PV panels when the covering required replacing. I advised they should contact a structrural engineer to determine if there would be any requirement to reinforce the existing roof structure to bear the weight of the PV panels and fixing system.

78
Q

Emma Rothschild Condition reportWhat significant defects did you identify in your report?

A

Generally the roof and their coverings were in good condition.The signifcant defects included slipping and cracked concrete roof tiles. There was also a creudly installed boiler flue, where the bitumen felt had not been repaired after its installation.

79
Q

Emma Rothschild Contion ReportWhat challenges did you face when completing the report?

A

The main challege was maintaining my safety while inspecting the roof coverings. In order to do so I compelted a desk top study and requested access details before attending. I then completed insepctions from the roof only where I maintainted a safe distance from the edge. Where possible I completed inspections from the ground floor.

80
Q

Emma Rothschild Condition reportWhat techniques did you use to assess the condition of the roof coverings?

A

I used my understanding of concrete coverings and flat roof coverings.I completed a detailed inspection to understand the defects of the types of covering and recored them in a schedule of condition.I aslo had information from the client on when the roof coverings were installed so I was able to estimate whether the coverings were in good or bad condition in comparison to their age. There was also evidence of on going repairs being completed, which eluded to the fact that the roof were well looked after.

81
Q

Emma Rothschild Condition reportWhat methods did you use did you use to present your findings?

A

NAME?

82
Q

Pre-acquisition surveys sunburyWhat type of pre-acquisition surveys did you carry out?

A

I carried out level 2 surveys to the propertys or home buyers reports.

83
Q

Pre-acquisition surveys, SunburyHow many properties did you survey in Sunbury

A

3

84
Q

Pre-acquisition surveys, SunburyWhat were the external, communal and internal elements of the buildings you inspected?

A

I inspected all elements of the property as outlined in the RICS home buyers report i.e. chimney stacks roof coverings, roof space and structure, services like electiccity gas and oil, grounds and garages.

85
Q

Pre-acquisition surveys, SunburyDid you identify any significant defects?

A

Yes, some of the more apparent ones were missing sections of soffit and blown glazing to windows.

86
Q

What are the main RICS guidance docs regarding inspection ?

A
  • Home Survey Standard - PS - 1st Ed 2019| * Surveying assets in the building environment - GN - 1st Ed 2017
87
Q

What are the keys changes introduced into the Home Survey Standard ?

A

Introduced in March 2021 to update and standardised previous guidance regarding residential inspections.This provides clarity on which survey best suits the property and responsibility in recommendation of the right one (Hart V Large)

88
Q

What do you understand by the phrase “plaster wicking’ in respect to low level damp in masonry walls ?

A

The same term used for rising damp - The unwanted ingress of water that rising through capillary action

89
Q

How would you identify Japanese knotweed ?

A
  • Shield or heart flat shape leaf* Small red/purple spears* Leaves on zig zag stems
90
Q

What are Dilapidations ?

A

Dilapidations are breaches of leases due to the condition of the property being leased. This may result from mistreatment of the property or poor or absent maintenance or repairs that are required by the lease. Further work may also be required at the end of a lease to reinstate alterations that have been made to the property by the tenant. Interim schedule – claims during the term. Terminal schedule – claims near or at the end of the term. Final Schedule - issued after expiry of the lease.

91
Q

What are you initial actions when dealing with a dilapidations claim ?

A

Check within the lease regarding various partied obligations such as internal only, external etc.

92
Q

What are dilapidations ?

A

Dilapidation represent the claim for exit cost or end of lease costs atrited to restoring the property ack into the state prior to the letting.

93
Q

What is Scott schedule ?

A

A Scott Schedule is an extended version of the Schedule of Dilapidations which enables the tenant (or their surveyor) to respond to the content of the Quantified Demand and/ or the Schedule of Dilapidations.

94
Q

What legislation does it fall under ?

A

The landlord and Tenant Act 1927

95
Q

What is a schedule of works?

A

A SOW is a single document that concisely lists what is to be done, where, how and to what quality.

96
Q

The main differences between a condition report and a schedule of condition?

A
  • Schedule of Condition is purely a record of the condition of the building to be appended to an agreement.* Condition report shows the condition of the building but identify works required, usually with costs to assist in planning maintenance.
97
Q

Can you tell me some of the heading sight a home buyers report

A
  • A Introduction to the report* B About the inspection* C Overall opinion and summary of the condition ratings* D About the property* E Outside the property* F Inside the property* G Services* H Grounds (including shared areas for flats)* I Issues for your legal advisers* J Risks* K Valuation* L Surveyor’s declaration* What to do now* Description of the RICS Homebuyer (Survey & Valuation)* Service Typical house diagram
98
Q

How would you assess damage to a building?

A
Referring to BRE Digest 251; Classification of viable damage•	0 – hairline crack•	1 – fine crack 1mm•	2 – cracks easily filled 5mm•	3 – crack 5-15mm; patch work•	4- crack 15-25mm; replace section•	5- ≥25mm structural damage; S.Engineer
99
Q

What is a protometer ?

A

Protimeter is a premium range of professional moisture measuring instruments. Protimeter is a premium range of professional moisture measuring instruments.

100
Q

What are the limitation of a protometer ?

A

An electronic moisture meter is suitable to detect moisture in timber by sending electrical waves between the two prongs. The sonar is used to detect the depth. which in turn can pick up hidden services behind the surface finish material. The tool may also give false reading base don foil backed plasterboard and black ash mortar.

101
Q

What else could you use to test for dampness ?

A

Speedy Carbide test and a gravimetric test

102
Q

What is the safe person concept?

A

The person assumes personal responsibility for their own and colleagues and others health and safety while at work. This is contained within the RICS Surveying Safely Document.

103
Q

What qualification do you need to take asbestos samples?

A

P402 Surveying and sampling for asbestos in buildings

104
Q

What is the most important thing to do prior to inspection ?

A

Health and Safety Risk Assessment

105
Q

What is the most logical inspection methodology ?

A
  • Surrounding area* External* Internal* Top down
106
Q

How would you check the age of a property ?

A
  • Architects plans* Historic maps* Planning or building regulations history* Record of practical completion* Lease* Speak to landlord etc.* Date plaque or similar
107
Q

What is a latent defect ?

A

Something that could not have been discovered by a reasonable inspection

108
Q

What is a patent defect ?

A

Patent defects are those which can be discovered by reasonable inspection

109
Q

What RICS document is relevant to inspections

A
  • Surveying safely: health and safety principles for property professionals 2nd edition, November 2018* Surveying assets in the built environment 1st edition, March 2017* Home survey standard 1st edition, November 2019
110
Q

What is a Level 1,2 & 3 Residential Survey ?

A

RICS surveyors offer three ‘levels’ of survey: a Condition Report (level one), Homebuyer Report (level two) and Building Survey (level three).* Condition Report (Level one) The property’s condition, including any risks, potential legal issues and urgent defects. Standard properties and relatively new homes in good condition. £400-£950 * Homebuyer Report/ Home Condition Survey (Level two) Includes all the features of a Condition Report, plus defects that might affect the property, and advice on repairs and maintenance. It can also include a market valuation and how much it would cost to rebuild the property. Standard properties in reasonable condition. £450-£1,000* Building Survey (Level three) An in-depth look at the property’s condition, with advice on defects, repairs and how to maintain the property. For larger or older (50+ years) properties, unusual homes, renovation projects and properties in poor condition. £600-£1,500

111
Q

How might you assess a concrete defect?

A
  • Visual first* Tap test* Phenolphthalein test* Core sample
112
Q

If you identify movement in a building, what further investigations might you wish to undertake?

A
  • Environmental matters, i.e. trees in close proximity* Neighbouring dwellings* Engineers structural survey* CCTV Drainage survey
113
Q

Explain how you can use thermal imaging to identify heat loss in a building.

A

Inspection involves scanning the house using the infrared thermographic camera. The camera has a screen that will clearly show heat differences. On the camera, leaking insulation will show as a jet of warm air. Since the air is warmer than the surroundings, it will appear with a different color on the camera’s screen.

114
Q

Outline the key changes introduced in the latest version of the RICS Home Survey Standard.

A

New RICS Home survey standard which aims to ensure consistency and improve the home buying and selling process. It protects buyers and sellers and emphasises the importance of making sure the consumer understands the benefits of a home survey. The new standard will create consistency, transparency and competency across residential surveying.

115
Q

Using an example, explain the extent of the inspection when preparing a schedule of condition for a party wall job.

A

Candidate specific

116
Q

Using an example where you have completed a snagging inspection, explain the methodology you followed during that inspection.

A

I follow the specification of works to the letter, I inspect each location and identify the works or remedy required, I identify omissions that require rectifying

117
Q

What format might you follow?

A

The RICS produce templates for the standard formats for reports such as L1, 2 and 3 surveys which can be purchased with an iSurve account. On the survey, I prefer to start on the outside and then move internally working my way from top to bottom. If there is anything I note additionally internally, I will check outside again in that area to confirm what may cause the defects.

118
Q

What might you include in your desktop investigations?

A

Review of alterations carried out, check on planning authority, if the building is listed, check its listed status on historic England and English heritage. I will ask the client to provide me with any plans or brochures of the property and ask them generic safety questions to ensure that it is safe to survey.

119
Q

What specialist investigation are you aware of?

A
  • Speedy carbide test* Thermographic testing* Drone surveys* Ground investigation* Asbestos investigation
120
Q

How do you carry out a hammer test?

A

I identified at ground level that there was some cracking to the render and when I tapped this, it sounded hollow, I took a look at higher level and noticed that there was sporadic cracking throughout but as this was too high to check safely, I advised the client that I should carry out a hammer test with the use of the cherry picker so that we can make an educated estimate of the amount of work required to allow for. This involved lightly knocking on the render and listening where there was a hollow sound and made a note on the elevation drawings.

121
Q

What do you need to consider before going to site to carry out an inspection?

A
  • Am I competent to undertake the inspection* Am I properly insured* Has an agreement been signed* What are the risks involved* What kind of survey is it,* Review all relevant existing building information, leases.* What equipment will be required to carry out the survey
122
Q

How does a disto work? How can you check its accuracy? When is it least accurate?

A
  • A disto sends out a laser beam and measures the time taken for it to reflect which gives it a distance.* We check all distos before use by measuring a known distance in the office.* It become less accurate the longer the distance and it is very difficult to use outside over long distances because it is difficult to aim and see the laser.
123
Q

Have you heard of a theodolite? How does this work?

A
  • An optical instrument consisting of a small mounted telescope rotatable in horizontal and vertical planes, used to measure angles in the horizontal and vertical planes. * Mounted on a tripod with adjustable legs, the theodolite is used in the field to obtain precise angular measurements for triangulation. * Levelling is accomplished with the aid of a spirit level; crosshairs in the telescope permit accurate alignment with the object sighted
124
Q

What is an Anemometer?

A
  • This is used to measure the air movement within buildings to establish ventilation requirements where condensation is a problem.* Air movement around ducts, grilles, windows and doors is checked.* Wind speed to external faces of buildings can also be checked to establish higher levels of exposure to driving rain due to the location of a property
125
Q

What are the key building elements you would look to survey?

A
  • Roofs* Walls & Cladding* Rainwater Goods * Windows, Doors and Joinery* Structural Frame* Substructure / basements* Floors* Finishes* Internal Walls, Partitions* Staircases* Sanitary Fittings* Building Services* Out Buildings
126
Q

What are some key valuable sources of occupiers information you would normally look to obtain prior to the survey?

A
  • Structural alteration drawings* Guarantees in respect of the premises or its services* Flooding or boundary documentation* Items of fixed equipment likely to be removed by the occupiers* Records of service agreements on items of plant* Records of testing of life safety systems* Water Hygiene and legionella reports* Planning and building control applications and approvals* Operation and maintenance manuals* Asbestos registers * Radon tests and high alumina cement tests
127
Q

What equipment would you take with you during a survey?

A
  • Mirror,* Disto* Measuring tape/rod* Moisture meter* Camera* Phone
128
Q

What do you need to consider before going to a site to carry out an inspection?

A
  • If I am competent to undertake the inspection* Am I insured?* Is there a formal letter of engagement* What are the risks? * What type of survey am I carrying out? * Have I been provided with the relevant documents
129
Q

How do you undertake an inspection?

A

Generally top down starting on the outside and then on the inside

130
Q

What precautions would you take if you were surveying a flat roof with a stepped ladder on your own?

A

I would prepare RAMS beforehand. I would consider the height and if I have a suitable ladder or if I needed alternative access arrangements. I would consider what condition the roof is in and if it was suitable to work on. Stepped ladders must be placed at approximately 70 degrees and tall enough that the top four rungs don’t need to be used.

131
Q

What would you look for when inspecting a slated pitched roof covering?

A
  • Are these original coverings? * What alterations have been carried out to the structure? * What are the weatherproofing details like? * What is the age? * Flashing? * Gutters?* Is the underside lined?
132
Q

What advice would you give if slates were to be replaced by concrete tiles? What implications are there?

A
  • If the roof pitch is suitable.* If the change is in keeping with planning guidelines?* Is it a listed building? * Can the existing joists support heavier concrete tiles? * What thermal improvements need to be made in compliance with Part L whereby any refurbishment over 50% of the roof requires you to upgrade the roof as close as possible to current regs.
133
Q

How can you tell if timbers have been structurally affected by fire?

A

I am not a qualified engineer to determine if the sound timber that remains is suitable.

134
Q

A hedge on clay ground has been cut back recently, what would you expect to happen?

A

Potential for flooding and heave.

135
Q

What is Radon Gas?

A

Produced during the decay of Radium which occurs naturally through the presence of uranium in most rocks, soil, bricks and concrete.

136
Q

Is radon gas dangerous?

A

Not particularly if breathed in and immediately exhaled. The issue is when the decaying product attach themselves to dust and moisture which can get stuck in your lungs

137
Q

Why is radon gas an issue within buildings?

A

Radon disperses externally. Internally, it may potentially build up to harmful levels. The amount of gas released depends on the area in the UK but is more concentrated with areas of high concentrations of granite and limestone.

138
Q

What does the RICS guidance note on surveying safely cover?

A
  • Personal and corporate responsibility* Legal considerations and duties* Assessing hazards and risks* Property professionals places of work* Occupational health* Visiting premises and sites.
139
Q

What is a hazard?

A

Something with the potential to cause harm to someone. The harm could be an injury or ill health.

140
Q

What is a risk?

A

A combination of the likelihood of the harm being realized and the severity of the harm if realised.

141
Q

What is a PPM Survey ?

A
  • Planned Preventative Maintenance (PPM) surveys are an essential tool that enable building owners/occupiers to proactively maintain, manage and improve their properties over a period of years. * Planned preventative maintenance (PPM) and stock condition surveys are an essential tool that enable clients to monitor and control costs, as well as optimise the value of their property portfolios over a determined timeframe.
142
Q

How might you inspect a cavity within an external cavity wall ?

A

Airbricks, borescope, in loft space

143
Q

Explain the range of readings you might get when using a moisture meter.

A

0-40% moisture content

144
Q

What are the disadvantages/limitations of using a borescope to inspect wall ties compared with the removal of a brick ?

A

Limited inspection, not a full picture