The first Canadian province to enact boiler and pressure vessel legislation was a) Ontario b) Alberta c) Quebec d) Manitoba e) Newfoundland
c) Quebec
A body which was formed in 1919 for the promotion of safety
and uniformity in the construction, installation, and
inspection of boilers and pressure vessels was the
a) National Board of Boiler and Pressure Vessel Inspectors
b) Underwriter Laboratories Canada
c) ASME
d) CSA
e) NFPA
a) National Board of Boiler and Pressure Vessel Inspectors
The purpose of the Safety Codes Act and Engineer’s
Regulations is to
a) help control the power plant personnel
b) help plants operating at high efficiency
c) ensure safe installation and operation of power plants
d) ensure optimum performance of any boiler operating
e) ensure proper examinations are conducted
c) ensure safe installation and operation of power plants
The main purpose of the Safety Codes Act is
a) the promotion of efficient combustion
b) the promotion for safety of life and property
c) the prevention of air pollution
d) to promote efficient boiler operation
e) to promote qualified training for operators
b) the promotion for safety of life and property
The Act and Regulations do not apply to
a) a heating plant having a boiler rating of 20 kW or more
b) a power plant having a boiler rating of 20 kW or less
c) a heating plant having a rating of 2,500 kW or more
d) a heating plant having a boiler rating of 30 kW or less
e) a power plant having a boiler rating of 10 kW or less
e) a power plant having a boiler rating of 10 kW or less
The code that regulates mechanical refrigeration is
a) ASME Section I
b) ASME Section VII
c) ASME Section IV
d) CSA B-51
e) CSA B-52
e) CSA B-52
Relative to boilers and pressure vessels, a code which has not been adopted by all the provinces is a) ASME I through IX b) CSA B51 c) NFPA d) ANSI B.31.5 e) CSA B52
c) NFPA
When a fitting is to be registered within a jurisdiction
a) an application must be made to the Chief Inspector
b) drawings must be submitted to the ASME
c) the manufacturer need not have a quality control program
in place
d) application fees will be waived
e) the CSA must approve the design
a) an application must be made to the Chief Inspector
The province of Alberta currently has various certificates of competency relative to Power Engineering and boiler operation, the number being a) 4 b) 6 c) 8 d) 10 e) 12
c) 8
Once you have taken over a shift in a high pressure boiler
plant, you may leave the boiler unattended for:
a) 4 hours
b) the time specified in the union agreement
c) 40 minutes
d) no period of time
e) 15 minute intervals
d) no period of time
The principal reason you should keep a boiler plant log book
or log sheet is to
a) satisfy the Boiler Inspector
b) provide a record of boiler operation and maintenance
c) provide the operator with an alibi when an accident
occurs
d) provide proof that the operator visited the boiler room
at the time stated
e) satisfy the chief engineer
b) provide a record of boiler operation and maintenance
A Fourth Class Engineer’s Certificate of Competency qualifies
the holder to take charge of a power plant not exceeding
a) 1,000 kW
b) 100 kW
c) 500 kW
d) 2,500 kW
e) 5,000 kW
a) 1,000 kW
A fitting as defined in the Act means
a) a stack
b) a fan
c) a gauge glass
d) a feedwater regulator
e) a pump
c) a gauge glass
After an initial inspection of a boiler or pressure vessel,
an Alberta identification number preceded by the letter “A”
in a __________, shall be stamped on the boiler or pressure
vessel.
a) square
b) rectangle
c) octagon
d) circle
e) hexagon
d) circle
A candidate for a welder’s performance qualification card
a) must have a high school diploma
b) must have successfully completed a vocational course
c) need not be able to write
d) requires at least three years practical experience as a
welder
e) must first pass a performance qualification test