Important Systems Flashcards
How long are the 250 VDC Plant Batteries expected to last during a Loss of Off-site Power?
3 hours
How long are the 250 VDC Plant Batteries expected to last during a Station Blackout?
4 hours
What are the bus and Trains for the CRIDs?
CRID 1 - C
CRID 2 - D
CRID 3 - A
CRID 4 - B
What is the normal power supply to the CRIDs?
250 V DC
What are the autostarts for the MDAFPs?
Both MFPs Trip (w control switch in auto)
AMSAC
Loadshed
Lo-Lo SG Level (1 SG)
SI
What are the TDAFP Auto Stared?
Undervoltage on RCP Bus
SG Lo-Lo (2 SGs)
AMSAC
What does the AMSAC Signal do?
Trips the Turbine and Starts all AFW pumps
What are the 3 autostarts of the CCW Pumps?
SI
Loadshed
Low discharge pressure (80#)
On an SI, what flow do the RHR Hx CCW Outlet valves throttle to?
3000-3500 gpm
What CCW Systems isolate on a Phase A?
SFP Hx
Excess LD
Rx Support Cooler
NBAE
What are the ESF Loads for CCS?
RHR Hx RHR pp Seal Hx CTS pp Seal Hx SI pp LO SI pp Seal Hx CCP LO Cooler CCP Speed Increaser
Does the control air compressor have a loadshed trip?
No
What are the key pressures of the plant and control air systems?
100 # - Normal
95# - Standy PAC Stars
90# - CAC Starts (sensed in wet air receiver)
85# - PA Hdr Isolation Valves Close
80# - Manual Trip
What signal stats the CTS Pumps?
Phase B
What signal opens the CTS Pump Discharge valves and the SAT Outlet Valves?
CTS Signal
What are the key levels and associated actions of QLC-451 for the VCT?
2.5% - Low-Low Alarm and half RWS signal
14% - Auto Makeup Starts + Low Alarm + MU Not in Auto Alarm
24% - Auto Makeup Stops
87% - Divert Trips Open + High Alarm
What are the key levels and associated actions of QLC-452 for the VCT?
2.5% - VCT LO-LO Alarm + 1/2 of RWS signal
7% - Low Alarm
78% Divert Starts
87% Divert Stops
WHat happens in the SVCS on a SI Signal?
Charging Hdr Iso Valves Close
CCW to LD Hx Closes
CCP Recircs Close and throttle based on pressure
CCP Suction realigns to RWST
BIT Valves Open
CCP Starts
What is the pressure input for QMO-225, East CCP ELO?
NPP-155
1812-1825#
What is the pressure input for the West CCP ELO?
NPP-153
1812-1825#
What is the ECCS Acceptance Criteria?
Peak Clad Temp - < 2200*F
Max Cladding Oxidation - < 17%
H2 Generation - < 1%
Core maintains a coolable geometry
Long term abundant cooling
What are the EDG Trips when needed for a SI or a LOOP with 250 VDC available?
Generator Phase Differential
Electronic Overspeed
Manual Push Button
What are the EDG Trips without 250 VDC available?
Manual Fuel Valve on the Worthington module
Mechanical Overspeed
If the EDG Electronic governor fails high, what happens?
EDG Speed will rise and machine will be controlled by the mechanical governor eventually