What is one limitation of Gypsum Panels?

A

Not recommended for use in solar or other heating systems when board will be in direct contact with surfaces exceeding 125F.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Describe USG Sheetrock Brand Regular Core

A

1/4”, lightweight, low-cost, utility gypsum panel, used as a base layer for improving sound control in multiplayer partitions and in covering old wall and ceiling surfaces. Also used for forming curved surfaces. Meets ASTM C1396.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Describe USG Sheetrock Brand Mold Tough Gypsum Panels

A

Have a noncombustible, moisture gypsum core encased in moisture-and mold-resistant, 100% recycled green face and brown back paper. The 5/8” Firecode and 1/2” Firecode C Core panels are UL classified for fire resistance (Type X).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Describe USG Sheetrock Brand Exterior Gypsum Ceiling Board

A

Weather resistant board designed for use on the soffit side of eaves, canopies and carports.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is a gypsom core?

A

Faced with specially treated, multilayered paper (blue) designed to provide a maximum bond to veneer plaster finishes.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is the minimum temperature for plastering?

A

50F

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

For curtain wall construction, cover the sheathing with ____ asphalt felt or other suitable water barrier within ___ days of sheathing installation. Felts should be applied _____ with ___ overlap and immediately anchored with metal lath, masonry ties or corrosion resistant screws or staples.

A

No. 15 asphalt felt
30 days
horizontally with a 2” overlap

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Gauge size for framing door frames?

A

20-gauge (33-mil) studs and runners

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Wire gauge for hangers in suspended ceiling grill work?

A

8

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Wire gauge for USG drywall suspensions system?

A

12

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Wire gauge for wire tying channels in wall furring and ceiling construction?

A

18

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is the benefit of a bugle head screw?

A

A form of self-drilling screw that’s specifically designed for drywall applications. Bugle head screws feature a countersunk head with a flat top and a concave under-head bearing surface spinning the face paper into the cavity under the screw head for greater holding power and helps prevent damage.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Type S screws are design for use with?

A

Steel

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Fastener selection - 1/2” single-layer panels to steel studs, runners, channels?

A

1” Type S Bugle Head

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Fastener selection - 5/8” double-layer panels to steel studs, runners, channels?

A

1-5/8” Type S Bugle Head

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Fastener selection - 3/8”, 1/2” and 5/8” single-layer panels to wood studs, joists?

A

1-1/4” Type W Bugle Head

17
Q

Wood framing maximum spacing on center is?

A

24” O.C. (2” from end)

18
Q

Hardware used with resilient channel installation?

A

3/8” Type S pan head screws

19
Q

Drive nails at least____” from ends or edges or gypsum board.

A

3/8”

20
Q

Double nailing application for Gypsum -
first nails at _____ OC along supports
perimeter at ____ OC

A

12” OC
7” OC

21
Q

With a 3/8” bead, approximately 3 - 5 gallons of adhesive will prepare framing for _____ Square feet of gypsum board.

A

1,000SF

22
Q

Control joints for plaster and lath surfaces should be provided at maximum _____ft. OC.

A

30

23
Q

Setting time for conventional basecoat plasters is generally _____ hours after mixing.

A

2 to 4

24
Q

When attaching a corner bead to the board in wood construction, the spacing of fasteners should be at______:

A

9” inch intervals in both flanges

25
Q

Using the ____ length nail possible is best to avoid nail pop when installing drywall.

A

Shortest

26
Q

The gypsum board that is both non-combustible and has a moisture core encased in moisture resistant brown paper is referred to as __________.

A

Green board.

27
Q

The maximum spacing of framing members used for 5/8” gypsum board installed perpendicular on a ceiling is______.

A

24” OC

28
Q

When using double-layer adhesive lamination, layout the face layer so all joints are offset____ from the parallel base-layer joints.

A

10”

29
Q

What size thickness of drywall is recommended for forming curved suraces?

A

1/4”

30
Q

Durabond (20) setting-type joint compound, that is used for gypsum board panels, has a setting time of_____.

A

20-30 minutes

31
Q

For levels of Gypsum Board Finish, which level of application finish is typically recommended for garages and warehouses?

A

Level 2

32
Q

To achieve the best results when plastering old surfaces, after removing the old plaster and lath, apply a _______ Rocklath plaster base to the framing and plaster in the same manner as new work.

A

3/8”

33
Q

When allowing for a control joint between gypsum panels, the minimum gap is _____.

A

1/2”